In re Application of E. Ohio Gas Co. (Slip Opinion)

2014 Ohio 3073, 24 N.E.3d 1098, 141 Ohio St. 3d 336
CourtOhio Supreme Court
DecidedJuly 16, 2014
Docket2012-2117
StatusPublished
Cited by1 cases

This text of 2014 Ohio 3073 (In re Application of E. Ohio Gas Co. (Slip Opinion)) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of E. Ohio Gas Co. (Slip Opinion), 2014 Ohio 3073, 24 N.E.3d 1098, 141 Ohio St. 3d 336 (Ohio 2014).

Opinion

Pfeifer, J.

{¶ 1} The East Ohio Gas Company, d.b.a. Dominion East Ohio (“Dominion” or “DEO”), appeals an order of the Public Utilities Commission reducing Dominion’s proposed customer charge to recover costs associated with Dominion’s automated-meter-reading (“AMR”) program. The commission reduced Dominion’s proposed AMR charge — from $0.54 per customer per month to $0.42 per customer per month — ostensibly because Dominion had failed to timely implement the AMR program. The reduction, according to Dominion, prevents Dominion from recovering from customers approximately $1.6 million in costs associated with the program.

{¶ 2} On appeal, Dominion argues that the commission’s order should be reversed because (1) the order is not supported by evidence in the record, (2) the order is unreasonable, (3) the commission lacks statutory and constitutional authority to issue retroactive orders that alter the significance of a utility’s previous conduct, and (4) the order is barred by collateral estoppel. Dominion also argues that the commission erred by denying Dominion’s motion for a stay of its order pending appeal.

{¶ 3} For the reasons explained more fully below, we agree that the commission’s order is substantively unreasonable. Accordingly, we reverse the commission’s order and remand this case for further proceedings, consistent with this opinion.

*337 I. Factual and Procedural Background

A. Dominion’s application to recover AMR program costs

{¶ 4} On December 7, 2006, the commission’s minimum gas-service standards took effect, which required natural-gas companies to, among other things, make reasonable attempts to obtain actual readings of customers’ meters every other month. See Ohio Adm.Code 4901:1-13-04(G)(1). Readings taken by AMR equipment qualified as “actual” readings, but readings taken by remote-meter-index equipment — the equipment then utilized by Dominion — did not qualify as “actual” readings. Id. Consequently, in December 2006, Dominion filed an application to recover costs associated with implementing an AMR-installation program.

{¶ 5} By installing AMR devices — small electronic modules — on customers’ existing gas meters, Dominion employees could then drive through neighborhoods collecting actual gas-meter readings through mobile data collectors installed in the employees’ vehicles. Before the installation of AMR devices, Dominion meter readers walked routes and had to access the inside of some of Dominion’s customers’ premises in order to obtain an actual gas-meter reading. Thus, AMR technology offered accurate gas-meter readings without the inconvenience of a meter reader accessing the inside of a customer’s property.

{¶ 6} In its AMR application, Dominion estimated that installing AMR devices on all of its meters would cost between $100 million and $110 million and would take as long as 15 to 20 years to complete if it were paid for through its normal budgeting process. To speed up the installation, Dominion applied for an automatic adjustment mechanism under R.C. 4929.11, which would allow Dominion to install AMR equipment on all of its meters over a five-year period by funding an accelerated installation program through an AMR-cost-recovery charge, or “AMR charge,” to each customer per month. Dominion proposed a process whereby it would file an application in February of each year seeking the commission’s approval for its proposed yearly AMR charge, which was to be based on the costs accumulated in the prior year for implementing the AMR program.

{¶ 7} The AMR charge was also meant to reflect the savings achieved as a result of using AMR devices. Because implementation of AMR equipment would reduce some of Dominion’s operations and maintenance expenses — especially meter-reading and call-center costs — Dominion proposed to reduce the AMR charge by the amount of savings generated by the program. For example, after installation of AMR devices, Dominion could begin reducing its meter-reader labor force because fewer meter readers would be necessary. The savings generated by the AMR program would be passed on to customers as a credit to the AMR charge.

*338 B. Ambiguity regarding the initial commencement date of the AMR program

{¶ 8} Dominion’s AMR application was consolidated with a then pending rate case, and the commission did not ultimately approve the application until October 2008. The commission’s order approving Dominion’s application failed to specify expected commencement or completion dates for the program. Dominion has maintained that the program did not have a firm start date, but that it began, at the earliest, in January 2008, the date specified in its application. In contrast, the commission’s staff has maintained that Dominion’s AMR program began in January 2007. As support, the staff points to the facts that Dominion actually began installing AMR devices in 2007 and that Dominion filed a related application in a separate proceeding suggesting that its AMR program began in 2007. Thus, throughout this litigation, Dominion and the commission’s staff have disagreed over when Dominion’s five-year AMR program officially began and, therefore, when the five-year program should have been completed.

C. The 2009 AMR order

{¶ 9} Once its plan was approved, Dominion was required to submit an application to the commission in February of each year justifying its yearly AMR charge based on the prior year’s accumulated AMR expenses. In the first three AMR cases — determining charges based on costs incurred in 2008, 2009, and 2010, respectively — Dominion and the commission’s staff ultimately agreed on the appropriate AMR charges. This appeal has resulted from Dominion’s application to recover costs incurred in 2011, in which'the commission’s staff and Dominion could not agree on the AMR-charge rate. The merits of this appeal, however, turn on the meaning of an order that the commission issued in the proceeding to recover the 2009 costs. For ease of reference, we refer to the order from the earlier proceeding as the “2009 AMR order,” despite the fact that the proceeding occurred in 2010, because it determined the AMR charge to recover 2009 costs.

{¶ 10} In the proceeding to recover the 2009 costs, the commission’s staff and Dominion agreed that the utility could charge $0.47 per customer per month to recover 2009 expenses. The Ohio Consumers’ Counsel (“OCC”), however, objected to the agreed rate. After a hearing, the commission issued an opinion and order rejecting the OCC’s arguments. But in its order, the commission also set forth the following instructions to Dominion regarding the timing of its AMR program:

While the evidence in this case supports DEO’s calculation, the Commission finds that DEO should be installing the AMR devices such that savings will be maximized and rerouting will be made possible in all of the *339 communities at the earliest possible time. Therefore, the Commission expects that DEO’s filing in 2011, for recovery of 2010 costs, will reflect a substantially greater number of communities rerouted. The Commission anticipates that, by the end of 2011, it will be possible to reroute nearly all of DEO’s communities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P.J. Lindy & Co., Inc. v. Savage
2019 Ohio 736 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 3073, 24 N.E.3d 1098, 141 Ohio St. 3d 336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-e-ohio-gas-co-slip-opinion-ohio-2014.