in Re Application of Dte Electric Co for Approval of Facility

CourtMichigan Court of Appeals
DecidedFebruary 7, 2019
Docket344033
StatusUnpublished

This text of in Re Application of Dte Electric Co for Approval of Facility (in Re Application of Dte Electric Co for Approval of Facility) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
in Re Application of Dte Electric Co for Approval of Facility, (Mich. Ct. App. 2019).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

In re Application of DTE ELECTRIC COMPANY for Approval of Facility.

MICHIGAN ENVIRONMENTAL COUNCIL, UNPUBLISHED NATURAL RESOURCES DEFENSE COUNSEL, February 7, 2019 and SIERRA CLUB,

Appellants,

v No. 344031 MPSC DTE ELECTRIC COMPANY, LC No. 00-018419

Petitioner-Appellee,

and

MICHIGAN PUBLIC SERVICE COMMISSION and ASSOCIATION OF BUSINESSES ADVOCATING TARIFF EQUITY,

Appellees.

In re Application of DTE ELECTRIC COMPANY for Approval of Facility.

ENVIRONMENTAL LAW & POLICY CENTER, ECOLOGY CENTER, SOLAR ENERGY INDUSTRIES ASSOCIATION, UNION OF CONCERNED SCIENTISTS, and VOTE SOLAR,

v No. 344033 MPSC DTE ELECTRIC COMPANY, LC No. 00-018419

MICHIGAN PUBLIC SERVICE COMMISSION and ASSOCIATION OF BUSINESSES ADVOCATING TARIFF EQUITY,

Before: CAMERON, P.J., and BECKERING and RONAYNE KRAUSE, JJ.

PER CURIAM.

These consolidated appeals arise out of the Michigan Public Service Commission (PSC) granting “certificates of necessity” (CONs) to DTE Electric Company (DTE) for the construction of a new 1,100 megawatt (MW) power plant at a cost of almost $1 billion, to replace several coal-powered plants that are scheduled to close. CONs are essentially pre-approvals of the need or propriety of major utility projects, investments, or purchases. Appellants are a variety of intervenors in the matter below, who contend generally that the PSC erred in granting the CONs. We affirm.

I. STANDARD OF REVIEW

We emphasize at the outset that we are forbidden to substitute our own judgment for that of the PSC. Attorney General v PSC No 2, 237 Mich App 82, 88; 602 NW2d 225 (1999). However, we review questions of law de novo, although with “respectful consideration” given to an agency’s interpretation of a statute. In re Complaint of Rovas Against SBC Michigan, 482 Mich 90, 103, 108; 754 NW2d 259 (2008). An aggrieved party must “show by clear and satisfactory evidence that the order of the commission complained of is unlawful or unreasonable.” MCL 462.26(8). “Unlawful” means that “the commission failed to follow some mandatory provision of the statute or was guilty of an abuse of discretion in the exercise of its judgment.” Giaras v PSC, 301 Mich 262, 269; 3 NW2d 268 (1942). “ ‘Unreasonable’ is a word of art in our jurisprudence and means arbitrary, capricious, or totally unsupported by admissible and admitted evidence.” Associated Truck Lines, Inc v PSC, 377 Mich 259, 279; 140 NW2d 515 (1966). Courts accept an agency’s factual findings if they are supported by “substantial evidence,” which must be “more than a scintilla” but need not be a preponderance. In re Payne, 444 Mich 679, 692; 514 NW2d 121 (1994).

II. CERTIFICATES OF NECESSITY

Certificates of necessity (CONs) are governed by MCL 460.6s. Utilities may request several different kinds of CONs under MCL 460.6s(3); in relevant part:

-2- (a) A certificate of necessity that the power to be supplied as a result of the proposed construction, investment, or purchase is needed.

(b) A certificate of necessity that the size, fuel type, and other design characteristics of the existing or proposed electric generation facility or the terms of the power purchase agreement represent the most reasonable and prudent means of meeting that power need.

* * *

(d) A certificate of necessity that the estimated purchase or capital costs of and the financing plan for the existing or proposed electric generation facility, including, but not limited to, the costs of siting and licensing a new facility and the estimated cost of power from the new or proposed electric generation facility, will be recoverable in rates from the electric utility’s customers subject to subsection (4)(c). [MCL 460.6s(3).]

Under MCL 460.6s(4), the PSC is required to hold a contested case hearing on a utility’s CON application, inquiring into the reasonableness and prudence of the proposed project, and issue an order granting or denying the application within 270 days. MCL 460.6s(4) further provides that the application shall be granted if the PSC finds five enumerated criteria satisfied:

(a) That the electric utility has demonstrated a need for the power that would be supplied by the existing or proposed electric generation facility or pursuant to the proposed power purchase agreement through its approved integrated resource plan under section 6t or subsection (11).

(b) The information supplied indicates that the existing or proposed electric generation facility will comply with all applicable state and federal environmental standards, laws, and rules.

(c) The estimated cost of power from the existing or proposed electric generation facility or the price of power specified in the proposed power purchase agreement is reasonable. [ . . . ]

(d) The existing or proposed electric generation facility or proposed power purchase agreement represents the most reasonable and prudent means of meeting the power need relative to other resource options for meeting power demand, including energy efficiency programs, electric transmission efficiencies, and any alternative proposals submitted under this section by existing suppliers of electric generation capacity under subsection (13) or other intervenors.

(e) To the extent practicable, the construction or investment in a new or existing facility in this state is completed using a workforce composed of residents of this state as determined by the commission. This subdivision does not apply to a facility that is located in a county that lies on the border with another state. [MCL 460.6s(4).]

-3- MCL 460.6s(11) sets forth certain requirements for the PSC to mandate in integrated resource plans (IRPs1) from utilities.

III. BACKGROUND

On July 31, 2017, DTE filed an application seeking three CONs for a proposed 1,100 MW natural gas combined cycle (NGCC) electric power plant. Specifically, DTE sought CONs (1) that the power to be supplied was needed, (2) that the proposed facility was the most reasonable and prudent means of meeting that need, and (3) that the almost $1 billion cost of the project would be recoverable in rates from DTE’s customers. DTE’s application was prompted by the imminent retirement of eight coal-fired power plants, which DTE predicted would incur a loss of approximately 1,822 MW of capacity. The PSC described the ensuing proceedings as generating “a record that is more voluminous than usual.” Ultimately, it found that DTE’s presentation suffered from various flaws and improprieties, but that DTE nevertheless satisfied its burdens of proof. The PSC therefore granted all three requested CONs.

Insofar as we can determine, only ABATE directly challenged the retirement of the coal plants per se, and therefore DTE’s need for the power, before the PSC. Although ABATE has filed an appearance in this appeal, it has done so as an appellee rather than an appellant, and in any event it has not submitted a brief or argument. The remaining appellants’ arguments are somewhat opaque and seemingly conflate the three CONs, but we can discern no coherently- expressed dispute whether there was a need for the power to be supplied. Likewise, we perceive no coherently-expressed dispute whether the cost of the project would be recoverable in rates from DTE’s customers. Consequently, we treat the PSC’s issuance of the first and third CONs as undisputed, and we are constrained to accept them as outside the scope of our review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Complaint of Rovas Against Sbc
754 N.W.2d 259 (Michigan Supreme Court, 2008)
Associated Truck Lines, Inc. v. Public Service Commission
140 N.W.2d 515 (Michigan Supreme Court, 1966)
Bunce v Secretary of State
607 N.W.2d 372 (Michigan Court of Appeals, 2000)
In Re Hensley
560 N.W.2d 642 (Michigan Court of Appeals, 1997)
People v. Poindexter
282 N.W.2d 411 (Michigan Court of Appeals, 1979)
Attorney General v. Public Service Commission No 2
602 N.W.2d 225 (Michigan Court of Appeals, 1999)
In Re Sprint Communications Co.
592 N.W.2d 825 (Michigan Court of Appeals, 1999)
Coates v. Drake
346 N.W.2d 858 (Michigan Court of Appeals, 1984)
Payne v. Muskegon
514 N.W.2d 121 (Michigan Supreme Court, 1994)
Wilcox v. Moore
93 N.W.2d 288 (Michigan Supreme Court, 1958)
Widmayer v. Leonard
373 N.W.2d 538 (Michigan Supreme Court, 1985)
Hayes-Albion Corp. v. Kuberski
364 N.W.2d 609 (Michigan Supreme Court, 1985)
Giaras v. Michigan Public Service Commission
3 N.W.2d 268 (Michigan Supreme Court, 1942)
Young v. Stephens
9 Mich. 500 (Michigan Supreme Court, 1862)
Taff v. Hosmer
14 Mich. 309 (Michigan Supreme Court, 1866)
Davis v. McMillan
105 N.W. 862 (Michigan Supreme Court, 1905)
Rovas v. SBC Michigan
482 Mich. 90 (Michigan Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
in Re Application of Dte Electric Co for Approval of Facility, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-dte-electric-co-for-approval-of-facility-michctapp-2019.