In Re Application of Consumers Energy Re Integrated Resource Plan

CourtMichigan Court of Appeals
DecidedMarch 23, 2023
Docket362294
StatusUnpublished

This text of In Re Application of Consumers Energy Re Integrated Resource Plan (In Re Application of Consumers Energy Re Integrated Resource Plan) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Application of Consumers Energy Re Integrated Resource Plan, (Mich. Ct. App. 2023).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

In re APPLICATION OF CONSUMERS ENERGY FOR APPROVAL OF AN INTEGRATED RESOURCE PLAN.

WOLVERINE POWER SUPPLY COOPERATIVE, UNPUBLISHED INC., March 23, 2023

Appellant,

V No. 362294 Public Service Commission MICHIGAN PUBLIC SERVICE COMMISSION, LC No. 00-021090 CADILLAC RENEWABLE ENERGY, LLC, GENESEE POWER PARTNERS LIMITED PARTNERSHIP, DECKER ENERGY-GRAYLING, LLC, TONDU CORPORATION, NATIONAL ENERGY OF LINCOLN, INC., NATIONAL ENERGY OF MCBAIN, INC., MICHIGAN ENVIRONMENTAL COUNCIL, HEMLOCK SEMICONDUCTOR OPERATIONS, LLC, SIERRA CLUB, NATURAL RESOURCES DEFENSE COUNCIL, and CITIZENS UTILITY BOARD OF MICHIGAN,

Appellees,

and

CONSUMERS ENERGY COMPANY,

Petitioner-Appellee.

Before: GLEICHER, C.J., and O’BRIEN and MALDONADO, JJ.

PER CURIAM.

-1- Appellant, Wolverine Power Supply Cooperative (Wolverine), appeals as of right the order of the Michigan Public Service Commission (MPSC) approving a settlement agreement for an integrated resource plan (IRP) filed by petitioner-appellee, Consumers Energy Company (Consumers). Wolverine contests the settlement agreement insofar as it binds Consumers to retire a coal-fired electricity-generating facility known as Campbell Unit 3 in 2025 instead of 2039 as originally planned. We affirm.

I. BACKGROUND

Effective April 20, 2017, MCL 460.6t requires the MPSC to periodically commence proceedings to assess many legal and practical concerns relating to production, delivery, and consumption of electricity in this state. MCL 460.6t(3) requires certain electric utilities to file an IRP with the MPSC, and subsection (8)(a) requires the MPSC to approve the IRP if it, among other things, “represents the most reasonable and prudent means of meeting the electric utility’s energy and capacity needs” by balancing enumerated factors.

Pursuant to this statute, Consumers filed an application with the MPSC on June 30, 2021, which, in pertinent part, proposed “accelerating the retirement of Campbell Unit 3 from December 31, 2039 to May 31, 2025” as part of its IRP. Wolverine is a joint owner of Campbell Unit 3. Proceedings commenced on Consumers’ application, and intervenor status was granted to Wolverine as well as appellees in this case.

Following an evidentiary hearing before an administrative law judge (ALJ), the ALJ issued a proposal for decision (PFD), recommending several modifications of the IRP and Consumers’ proposed course of action (PCA), including modifications to Consumers’ proposed retirement of Campbell Unit 3. The ALJ expressed concerns about Consumers’ capacity-sufficiency analysis on the ground that Consumers’ assumptions “are not consistent with how [Midcontinent Independent System Operator (MISO)1] operates, where all resources are used to serve all loads, and where the company is never in fact islanded.” The ALJ concluded that the record did not establish that early retirement of Campbell Unit 3 was the most reasonable and prudent plan, stating that “[t]he PFD agrees with Staff that additional modeling of Campbell [Unit] 3 retirement is necessary because the company’s decision to retire the unit in 2025 is not well supported.” The ALJ expressed concern about permitting Consumers to retire Campbell Unit 3 in 2025 on the basis of assumptions about Consumers’ purchasing other resources for power generation. It

1 MCL 460.6w(12)(a) recognizes MISO as the “[a]ppropriate independent system operator” for purposes of the applicable statutory scheme. MISO in turn describes itself as “an independent, not-for-profit, member-based organization focused on . . . [m]anaging the flow of high-voltage electricity across 15 U.S. states and” a province of Canada, “[f]acilitating one of the world’s largest energy markets,” and “[p]lanning the grid of the future,” and boasts that “45 million people depend on MISO to generate and transmit the right amount of electricity every minute of every day— reliably, dependably, and cost-effectively.” https://www.misoenergy.org/about/ (accessed March 1, 2023). MISO has established 10 zones for its purposes, and the zone pertinent to this case— Local Resource Zone 7—covers most of Michigan’s Lower Peninsula. In re Implementing Section 6w of 2016 PA 341 for Cloverland Electric Coop, 329 Mich App 163, 168; 942 NW2d 38 (2019).

-2- recommended that Consumers “evaluate the retirement of Campbell 3 in isolation, with the objective of retiring the unit in 2025, but with analysis of other resource options,” including the purchase of additional power-generating resources, as well as “additional renewables, storage, and strategically installed [reciprocating internal combustion engine] generation.” The ALJ further recommended that Consumers “update its input assumptions for solar and battery storage, using company results where possible, supplemented with more recent [outside] data in cases where the company has limited cost or performance information.”

After the PFD was issued, Consumers entered into a settlement agreement with the appellees. As recounted by the MPSC’s final order on appeal:

The settlement agreement recommends approval of Consumers’ [PCA] with changes and covers issues such as: the acquisition of new resources; investments in demand response (DR), conservation voltage reduction (CVR), and energy waste reduction (EWR); deployment of energy storage; retirement of certain coal-fired generation units and associated decommissioning costs; a financial compensation mechanism (FCM); avoided cost methodology under the Public Utility Regulatory Policies Act of 1978 (PURPA); and implementation of competitive bidding.

As to the “retirement of certain coal-fired generation units” relevant to this appeal, the settlement agreement provided for the retirement of Campbell Unit 3 “on or before May 31, 2025.”

Certain intervenors, including Wolverine, filed responses objecting to the settlement agreement. The competing parties (i.e., signatories to the settlement agreement and those objecting to the agreement) then filed direct testimony, rebuttal testimony, initial briefs, and reply briefs, creating an evidentiary record of the contested settlement proceeding consisting of 315 pages of transcript and 22 exhibits. As relevant to this appeal, and as noted by the MPSC in its final order, witnesses disagreed about the reasonableness of retiring Campbell Unit 3 as specified in the settlement agreement, with Wolverine in particular coming out against this facet of the agreement.

The MPSC, however, was persuaded by witnesses who testified in favor of retiring Campbell Unit 3, finding that the retirement of Campbell Unit 1, 2, and 3 “will result in savings to ratepayers, reduce the production of environmental pollutants, such as SO2, NOx, and particulate matter, and advance Michigan’s clean energy goals as outlined in the MI Healthy Climate Plan as well as provide additional public health benefits[.]” The MPSC ultimately concluded:

[T]he Commission finds that . . . the settlement agreement is in the public interest. The Commission also finds that the proposed settlement agreement is a fair and reasonable resolution of this proceeding. In addition, having read the record, the Commission likewise finds the settlement agreement to be supported by substantial evidence on the record as a whole. Moreover, as agreed to by the parties . . . and supported by the record, the Commission finds that Consumers’ PCA as amended by the settlement agreement is the most reasonable and prudent means of meeting Consumers’ energy and capacity needs and otherwise meets the requirements of MCL 460.6t(8).

This appeal followed.

-3- II. STANDARD OF REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Consumers Energy Co.
756 N.W.2d 253 (Michigan Court of Appeals, 2008)
Tomczik v. State Tenure Commission
438 N.W.2d 642 (Michigan Court of Appeals, 1989)
VanZandt v. State Employees' Retirement System
701 N.W.2d 214 (Michigan Court of Appeals, 2005)
Attorney General v. Public Service Commission No 2
602 N.W.2d 225 (Michigan Court of Appeals, 1999)
In Re MCI Telecommunications Complaint
596 N.W.2d 164 (Michigan Supreme Court, 1999)
In re Consumers Energy Co.
279 Mich. App. 180 (Michigan Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
In Re Application of Consumers Energy Re Integrated Resource Plan, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-consumers-energy-re-integrated-resource-plan-michctapp-2023.