In Re Application of Consumers Energy Co for Reconciliation

CourtMichigan Court of Appeals
DecidedFebruary 1, 2024
Docket362931
StatusPublished

This text of In Re Application of Consumers Energy Co for Reconciliation (In Re Application of Consumers Energy Co for Reconciliation) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Application of Consumers Energy Co for Reconciliation, (Mich. Ct. App. 2024).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

In re APPLICATION OF CONSUMERS ENERGY COMPANY FOR RECONCILIATION.

CONSUMERS ENERGY COMPANY, FOR PUBLICATION February 1, 2024 Petitioner-Appellant/Cross-Appellee, 9:10 a.m.

v No. 362931 Public Service Commission MICHIGAN PUBLIC SERVICE COMMISSION, LC No. 00-020526

Appellee/Cross-Appellee,

and

CADILLAC RENEWABLE ENERGY, LLC, GENESEE POWER STATION LIMITED PARTNERSHIP, GRAYLING GENERATING STATION LIMITED PARTNERSHIP, HILLMAN POWER COMPANY, LLC, TES FILER CITY STATION LIMITED PARTNERSHIP, NATIONAL ENERGY OF LINCOLN, LLC, and NATIONAL ENERGY OF MCBAIN, LLC,

Appellees,

ASSOCIATION OF BUSINESSES ADVOCATING FOR TARIFF EQUITY,

Appellee/Cross-Appellant.

Before: BORRELLO, P.J., and SWARTZLE and PATEL, JJ.

-1- SWARTZLE, J.

In Michigan, an energy utility estimates its upcoming power-supply costs as part of its rate- setting process. Like any estimate, the utility’s estimate can be off, sometimes way off. Anticipating the problem of how to reimburse a utility for increased power-supply costs, our Legislature enacted a reconciliation process, by which the utility can apply to the Public Service Commission (PSC) to increase upcoming rates to help recoup prior unanticipated costs.

Not all missed estimates are, however, created equal—some are due to acts outside of the utility’s control, while others result from the utility’s negligence or imprudent management. In a lightly regulated market, short sellers, hostile takeovers, proxy wars, and the like, serve as the discipline against poor estimates by management. In a highly regulated market like the one for energy in Michigan, however, that discipline must primarily come from elsewhere. Relevant here, our Legislature has conditioned a utility’s recoupment of under-recovered costs on that utility having acted reasonably and prudently with respect to decisions impacting those costs.

In this appeal, Consumers Energy Company argues that the PSC erred in concluding that the utility did not act reasonably and prudently with respect to a prolonged outage. The record confirms, however, that Consumers provided “unreasonable or imprudent management” (or, put another way, failed to provide “reasonable and prudent management”) with respect to the outage, causing the very increased costs of which it now complains. Seeing no reversible error, we affirm.

I. BACKGROUND

To better understand this dispute, it is helpful to look briefly at how the energy market in Michigan deals with large-scale power outages. When an electricity-generating facility has an outage, or when the demand for electricity in a given area is unexpectedly high, the utility that services the affected area will provide replacement electricity to its affected customers. The replacement electricity often comes from electricity-generating facilities owned by other utilities, and this electricity is exchanged on a market for “wholesale electricity.” Midcontinent Independent System Operator, Inc. (MISO) oversees the market for wholesale electricity in much of Michigan, and utilities can purchase and sell “zonal credits” through MISO’s “planning resource auction.” In essence, a “zonal credit” represents the right of the credit holder to a unit of deliverable “unforced capacity” that can be bought or sold on the MISO-managed market.

The cost of this replacement electricity is generally higher than the cost of the electricity generated by a utility’s own facility. A utility can include the higher cost of replacement electricity in its cost-recovery plan so that consumers bear the ultimate burden of the higher cost, as opposed to the utility. If, at the end of the year, the utility faces an “underrecovery” of power-supply costs, then that utility can seek to “true up” the actual costs of power supply with its earlier, too-low estimate through the PSC’s reconciliation process. The costs are passed along to consumers in the form of higher future rates.

In 2020, Consumers Energy had a planned outage for upgrades at Unit 3 of its Ludington Pumped Storage Plant. The upgrades and consequent outage had an original estimated completion date in Spring 2020, 140 days after it began. The outage was extended, however, to 366 days after material defects on a “discharge-ring extension” were found during installation. Consumers

-2- Energy had selected Toshiba America Energy Systems Corporation as its contractor on the upgrade project, and Toshiba manufactured and installed the defective extension.

The original estimate for the Unit 3 outage was included in Consumers Energy’s power- supply-cost plan for 2020. With the significantly longer outage, however, Consumers Energy had to purchase replacement electricity, and the utility claimed that this resulted in an under-recovery of power-supply costs. Consumers Energy accordingly sought reconciliation between its estimated and actual power-supply costs for the year.

The PSC’s Administrative Law Judge Sally L. Wallace presided over the reconciliation proceedings. ALJ Wallace permitted several parties to intervene, including the Michigan Department of Attorney General and cross-appellant Association of Businesses Advocating Tariff Equity (ABATE). The department opposed Consumers Energy’s application for reconciliation because, as it argued, the utility’s increased power costs resulted from its unreasonable and imprudent management under MCL 460.6j. ABATE agreed with the department and further argued, in the alternative, that Consumers Energy generated revenue from the sales of its zonal credits through MISO, and that revenue should be included in the overall calculus as an offset against the higher cost of replacement power.

During an evidentiary hearing, a witness for Consumers Energy confirmed that the Unit 3 outage was longer than expected because material defects on the discharge-ring extension were discovered during installation. The witness explained that, to fix the problem, Toshiba ultimately had to design and manufacture a replacement. He acknowledged that contractor errors were responsible for most of the Unit 3 delays, though he cited the COVID-19 pandemic as an additional source of increased cost.

Another witness for Consumers Energy testified that the utility owned 51% of the Ludington Plant and DTE Energy owned the rest. The scheduled upgrade to the plant was a joint project between Consumers Energy, DTE, and Toshiba. Similar to the utility’s other witness, this witness put the blame for increased costs on the contractor because it had designed, manufactured, and installed the materially defective discharge-ring extension. The witness further explained that it was a joint decision of both Consumers Energy and DTE that Toshiba should repair the defective extension. They moved away from this plan to repair only after several third-party experts concluded that any repair would itself be defective. Consumers Energy eventually instructed Toshiba to manufacture an entirely new discharge-ring extension.

For its part, ABATE provided written testimony from a consultant. The consultant noted that Consumers Energy’s revenue from selling zonal credits was larger than its under-recovery of power-supply costs for 2020. The consultant argued that Consumers Energy would not have realized the increased revenue from sales of the zonal credits but-for the extended outage of Unit 3. Given this, the consultant concluded that the PSC should offset any purported under-recovery of Consumers Energy by that utility’s revenues generated from the sale of its zonal credits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Complaint of Rovas Against Sbc
754 N.W.2d 259 (Michigan Supreme Court, 2008)
Rovas v. SBC Michigan
482 Mich. 90 (Michigan Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
In Re Application of Consumers Energy Co for Reconciliation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-consumers-energy-co-for-reconciliation-michctapp-2024.