In Re Application 7600 to Appropriate Water

272 P. 225, 73 Utah 50, 1928 Utah LEXIS 92
CourtUtah Supreme Court
DecidedNovember 10, 1928
DocketNo. 4638.
StatusPublished
Cited by3 cases

This text of 272 P. 225 (In Re Application 7600 to Appropriate Water) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Application 7600 to Appropriate Water, 272 P. 225, 73 Utah 50, 1928 Utah LEXIS 92 (Utah 1928).

Opinion

GIDEON, J.

Whether the district court erred in approving an order of the state engineer granting an extension of time to the Granite Creek Irrigation Company to complete the appropriation of water under an application numbered 7600 is the question here presented for review. This is the second appeal in this controversy. See in re Application 7600 to Appropriate 30 Second Feet of Water, 63 Utah 311, 225 P. 605. Reference to the opinion in that case is hereby made for a more detailed statement of the facts involved.

In the year 1918 the predecessors in interest of the Granite Creek Irrigation Company filed with the state engineer application No. 7600 for the appropriation of 30 second feet of water from Red Cedar creek in Juab county, this state. The application was approved May 27, 1919. The condition imposed by the engineer was that actual construction work should begin within six months, and that the appropriation should be completed on or before March 1, 1922. In October, 1921, a Mr. H. B. Johnson filed with the state engineer application No. 8925 for the appropriation of 20 second feet of water from Red Cedar creek. This *53 application was approved in February, 1922. Johnson was the predecessor in interest of the protestants here. In February, 1922, the Granite Creek Irrigation Company, owner of application No. 7600, applied to the state engineer for an extension of time from March 1, 1922, to March 1, 1923, within which to complete the work under said application. Thereafter an additional or subsequent application was made for a further extension of time in which to complete the appropriation. Protest was filed by the owners of application No. 8925 against application No. 7600, alleging impracticability of the project and also objecting and protesting against the granting of additional time within which to complete the appropriation, for the reason that work had not been commenced within six months from the approval of the application and had not been diligently prosecuted. Affidavits were filed by the respective parties in support of the protest and objections, and likewise in favor of the granting of additional time. Evidence was taken by the state engineer. That officer granted additional time and dismissed the protest. An appeal was taken from that ruling to the district court of Juab county. There the matter came on for hearing. That court entertained the view that the state engineer had no authority to grant an extension of time for the completion of the work necessary under an application for the appropriation of water. The Granite Creek Irrigation Company appealed to this court. This court, in Re Application 7600, etc., held that the engineer was authorized and had power to grant an extension. Only one question was considered and determined on that appeal. As the court in the opinion said:

“The concrete question to be determined is: Did the State Engineer have power to grant an extension of time to application 7600 within which to complete the work beyond the time originally fixed by the State Engineer when he approved the application?”

The judgment of the district court of Juab county was reversed, and the cause was remanded to be heard upon the *54 merits. Thereafter, by stipulation of counsel, the case was transferred to the district court of Salt Lake county, and was there heard in September, 1926. The trial in the last-named court resulted in a judgment approving the order of the state engineer granting the additional time requested for the completion of the work and dismissing the protest. Motion for a new trial was made. This was denied. From the judgment so rendered by the district court of Salt Lake county this appeal is prosecuted by the protestants, S. F. Falkenberg and W. N. Lord, who are the successors in interest of H. B. Johnson, the original owner of application No. 8925.

Red Cedar creek is a small stream of water having its source in the mountains in Juab county and running in a southeasterly direction over or through the lands sought to be irrigated with the waters applied for under application No. 7600. Granite creek is also a small stream of water. It lies to the west of Red Cedar creek and has its source in the mountains to the northwest. The course of Granite creek is also southeasterly. These two streams come together in the valley below. Lying between the two streams and below the canyons from which they emerge is land suitable for irrigation. The project undertaken by the Granite Creek Irrigation Company and its predecessors in interest is to use these waters for the irrigation of some of this land down in the valley. An appropriation of water from Granite creek was also made. The project contemplates piping water from Granite creek to a natural reservoir lying between Granite creek and Red Cedar creek and also the construction of conduits or pipes to take the water from Red Cedar creek into the same reservoir. As described by the state engineer, the reservoir site lies higher up than does the land sought to be irrigated and is a natural reservoir site. The water is taken from the reservoir by pipe line and conveyed into the laterals which carry the water to the land sought to be irrigated. The testimony is quite definite that the Granite Creek Irrigation Company had ex *55 pended large sums of money in its efforts to take the water from Granite creek to the reservoir site and to convey it from the reservoir to the land to be irrigated, and also in constructing the laterals for carrying water to the land proposed to be irrigated. These same laterals were to be used, at least in a partial way, in the distribution of the water from Red Cedar creek.

The cause, as heard before the trial court, was narrowed to two issues: First, that the owner of application No. 7600 did no actual construction work in the diversion or appropriation of water within six months after the date of the approval of the application. Second, that the owner of application No. 7600 failed to prosecute the work under said application with due diligence. While it is true that the Protestants alleged other grounds against the extension of time to complete the work, the district court treated the issues limited as indicated, and was authorized to do so by reason of the statement of counsel representing the protestants, appellants here. In the course of the trial, and while addressing the court upon the objections made to certain evidence, counsel for protestants said:

“I will state to the court frankly that our evidence was directed towards two issues that Your Honor designated in the first place, the issue that they [the Granite Creek Irrigation Company] did not begin construction work within the six months and that they did not diligently prosecute that work.”

On the former appeal in this case it was determined that the state engineer, by virtue of his office, has authority to grant extensions of time for the completion of the appropriation of water under applications so to do upon good showing made. Necessarily, in the exercise of that power, such officer is given a certain degree of discretion in the granting or refusing of extensions. That was the view entertained by the trial judge, and accordingly he interpreted his duty to be to determine whether or not the engineer had abused' his discretion in granting the ex *56 tension in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edwards v. Clark
83 P.2d 1021 (Utah Supreme Court, 1938)
Townsend v. Holbrook
56 P.2d 610 (Utah Supreme Court, 1936)
Paxton v. Paxton, Walker Et Ux. v. Same
15 P.2d 1051 (Utah Supreme Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
272 P. 225, 73 Utah 50, 1928 Utah LEXIS 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-7600-to-appropriate-water-utah-1928.