In re: Appeals of Beckstrom In re: Appeal of H.A. Manosh, Inc.

CourtVermont Superior Court
DecidedSeptember 28, 2001
Docket212-11-98 Vtec
StatusPublished

This text of In re: Appeals of Beckstrom In re: Appeal of H.A. Manosh, Inc. (In re: Appeals of Beckstrom In re: Appeal of H.A. Manosh, Inc.) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re: Appeals of Beckstrom In re: Appeal of H.A. Manosh, Inc., (Vt. Ct. App. 2001).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

In re: Appeals of Beckstrom, et } al. } Docket Nos. 212-11-98 } Vtec, 11-1-99 Vtec and 61- } 4-99 Vtec }

In re: Appeal of H.A. Manosh, } Inc. } } Docket No. 1-1-99 Vtec } }

Decision and Order on Motions to Reconsider and Clarify, to Alter Judgment, and Motion for Partial Summary Judgment

The project at issue in these related cases is the construction of a 100-foot, 150-foot, or 160-foot tall radio communications tower and associated buildings, on land in the Town of Hyde Park owned by H.A. Manosh, Inc. (Applicant), some of which is proposed to be leased to Vermont RSA Limited Partnership, then doing business as Bell Atlantic Mobile. A group of neighbors and other Hyde Park residents (the Appellant Group) is represented by Stephanie J. Kaplan, Esq. and Barry Kade, Esq.; H.A. Manosh, Inc. is represented by John H. Hollar, Esq.; Vermont RSA Limited Partnership is represented by Brian Sullivan, Esq.; and the Town is represented by Stephen F. Stitzel, Esq.

In Docket No. 212-11-98 Vtec, the Appellant Group appealed from two decisions of the Zoning Board of Adjustment (ZBA) of the Town of Hyde Park, one dated October 13, 1998 dismissing their appeal as untimely and one dated October 16, 1998 upholding the Zoning Administrator= s ruling regarding Permit No. 97-06 issued to Applicant. In Docket No. 1-1-99 Vtec, Applicant appealed from a December 10, 1998 decision of the ZBA that a conditional use hearing was required for the proposal. In what was mistakenly docketed (under Docket No. 11-1-99 Vtec) as a separate appeal, but was actually a cross-appeal of the same decision, the group of interested persons also appealed from several aspects of the December 1998 ZBA decision. In Docket No. 61-4-99 Vtec, the Appellant Group appealed from a March 9, 1999 decision of the DRB, granting a conditional use permit and site plan approval to Applicant to construct a 160' tower, enlarge one building, and construct a second building. Applicant cross-appealed from the requirement that it obtain site plan and conditional use approval for the project at all. In Docket No. 61-4-99 only1, Vermont RSA Limited Partnership d/b/a Bell Atlantic Mobile entered an appearance through Brian J. Sullivan, Esq. The Court issued an order resolving many of the issues in all four cases by summary judgment, and determined that other issues would require remand to the DRB. That order included findings describing the history and procedural posture of the project and the four cases, which will not be repeated here. Applicant and the Appellant Group have moved to reconsider and clarify, and to alter that judgment, and renewed aspects of their original motions for partial summary judgment. We will take the Statements of Questions raised by each party under each docket number and either note its status under the 2000 Order, or, for those questions which are the subjects of the pending motions, rule on those motions, and determine whether any issues remain for the Court= s decision prior to the remand to the DRB. The court order determined that both the merits of the July 1997 application for a 150-foot tower and the December 1998 application for the 160-foot tower and associated buildings would have to be remanded to the DRB for consideration for conditional use approval, site plan approval, and approval under the Telecommunications Facilities Interim Bylaw adopted in January 1999.

Docket No. 212-11-98 Appellant Group= s Question 1. Whether an untimely appeal from the April 1997 permit and the July 1997 permit should be heard, as a matter of due process, because the permits were improperly issued without notice and without conditional use hearing.

Docket Nos. 1-1-99 /11-1-99: Applicant= s Question 1. Whether the Couture appeal of the 1997 permit was withdrawn.

Docket Nos. 1-1-99 /11-1-99: Applicant= s Question 2. Whether the Couture appeal failed to meet the requirements of 24 V.S.A. ' 4465 and therefore whether the zoning administrator should have notified the board and scheduled a hearing.

These questions relating to the circumstances of the appeal of the permit were resolved as to the April 1997 permit. Appellant Group= s Question 1was not reached as to the July 1997 permit, because the Court found the appeal of that permit to have been timely filed and that it was not withdrawn. The Appellant Group has moved the Court to reconsider and reach this question, in case the Court= s decision on this point is reversed on appeal. At the present time, decision on this point would be an entirely advisory opinion, as we have ruled that the appeal was timely filed and not withdrawn. If that ruling should be reversed on appeal, then this question would require a ruling in any proceeding remanded to this Court. The Appellant Group= s request for reconsideration of this ruling is, therefore, DENIED. The Applicant= s Motion to Alter Judgment as to the ruling that the Couture appeal was not withdrawn is also DENIED. Facts are disputed as to whether he told the board or the town that it didn= t need to proceed with the appeal at the time it was filed, but the Court has ruled that as a matter of law it was not withdrawn. The Applicant= s Question 2 in Docket No. 1-1-99 Vtec depends upon these disputed facts. That is, even if the zoning administrator had refrained from scheduling the appeal at that time, based upon Mr. Couture= s statements, that action did not result in the withdrawal of the notice of appeal. Further, regardless of whether Mr. Couture= s notice of appeal was deficient in any way under ' 4465, the zoning administrator should have registered the fact that the appeal was filed, and could have informed Mr. Couture of any deficiencies or could have left it to a motion to dismiss the appeal before the board. Docket No. 212-11-98 Appellant Group= s Question 2. Whether the April 1997 application and the July 1997 request for a zoning permit should be denied because the project is neither a permitted nor a conditional use in the Rural Residential 2 zoning district.

This question was resolved as to the April 1997 permit. This question was also resolved as to the July 1997 permit: the Court ruled that it was not a permitted use and had to go before the DRB for consideration as a conditional use, the first step of which is for the Applicant to file a complete application for a conditional use permit and site plan approval. That is the status of the proposal for the 150-foot tower (July 1997 application); under 24 V.S.A. ' 4464(a) the 1997 permit does not take effect until the final adjudication of its appeal. The Appellant Group= s request for reconsideration of this ruling, requesting that the Court A deny@ the permit application and A void@ the 1997 Permit is DENIED.

Docket No. 212-11-98 Appellant Group= s Question 3. Whether the request for a zoning permit should be denied because no application (for the July 1997 permit) was filed and it therefore did not contain the information required for the processing of a conditional use application.

Docket Nos. 1-1-99 /11-1-99 Appellant Group= s Question 1. Whether the July 1997 Permit is void because the proposed use requires a conditional use permit and is beyond the jurisdiction of the zoning administrator.

Docket Nos. 1-1-99 /11-1-99: Applicant= s Question 3. Whether a conditional use hearing must be held regarding the application to construct a 150-foot tower.

The Court ruled that the lack of a paper application for the July 1997 permit meant both that the Zoning Administrator had no authority to act on it and that the ZBA should have required a complete application for a conditional use permit to be filed in December 1998.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barbagallo v. Gregory
553 A.2d 151 (Supreme Court of Vermont, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
In re: Appeals of Beckstrom In re: Appeal of H.A. Manosh, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-appeals-of-beckstrom-in-re-appeal-of-ha-manosh-inc-vtsuperct-2001.