In Re Appeal of the New Jersey Department of Environmental Protection's September 6, 2022 Denial of Request for Adjudicatory Hearing

CourtSupreme Court of New Jersey
DecidedApril 7, 2025
DocketA-42-23
StatusPublished

This text of In Re Appeal of the New Jersey Department of Environmental Protection's September 6, 2022 Denial of Request for Adjudicatory Hearing (In Re Appeal of the New Jersey Department of Environmental Protection's September 6, 2022 Denial of Request for Adjudicatory Hearing) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Appeal of the New Jersey Department of Environmental Protection's September 6, 2022 Denial of Request for Adjudicatory Hearing, (N.J. 2025).

Opinion

SYLLABUS

This syllabus is not part of the Court’s opinion. It has been prepared by the Office of the Clerk for the convenience of the reader. It has been neither reviewed nor approved by the Court and may not summarize all portions of the opinion.

In Re Appeal of the New Jersey Department of Environmental Protection’s September 6, 2022 Denial of Request for Adjudicatory Hearing (A-42-23) (089182)

Argued October 22, 2024 -- Decided April 7, 2025

HOFFMAN, J., writing for a unanimous Court.

In this appeal, the Court considers whether the Department of Environmental Protection’s (DEP) grant of a waiver suspending certain environmental remediation obligations creates a constitutionally protected property interest in that waiver.

The Industrial Site Recovery Act (ISRA) prohibits the owner of an industrial establishment from transferring ownership until certain conditions are met, unless the owner pursues one of the alternatives that ISRA provides. As relevant here, one of the listed exceptions, N.J.S.A. 13:1K-11.5, provides for an “[a]pplication for closing [or] transfer when remediation is already in progress.” Under that provision, an entity may apply to the DEP for a Remediation in Progress Waiver (RIP Waiver), which allows that entity to proceed with a triggering event (i.e., sale or cessation of operations) without the typical attendant ISRA requirements “if the industrial establishment is already in the process of a remediation.” N.J.S.A. 13:1K-11.5(a). To receive a RIP Waiver, an entity must submit evidence “that the property . . . is being remediated by a prior owner or operator” and that a compliant “remediation funding source” (RFS) has been created. N.J.A.C. 7:26B-5.4(c).

In 2006, the corporate predecessor of Clarios, LLC, purchased an industrial site (“the Site”), for which the seller had executed a remediation plan under ISRA and placed funds in trust for future remediation (“the RFS Trust”). In 2007, Clarios ceased operations, triggering its ISRA responsibilities. Clarios, therefore, sought a RIP Waiver. In March 2007, the DEP granted Clarios’s RIP Waiver but expressly reserved the right to enforce Clarios’s ISRA obligations in the future, informing Clarios that the DEP “continues to reserve all rights to pursue appropriate enforcement actions allowable under the law for violations of ISRA.”

In August 2011, Clarios sold the Site. In 2016, the purchaser of the Site filed for bankruptcy. In July 2021, the purchaser certified that the estimated cost to complete remediation was $563,000 but that the RFS Trust was fully depleted. The purchaser thereafter also missed its February 2022 deadline for completing 1 remediation of the Site. In April 2022, the DEP rescinded Clarios’s RIP Waiver because remediation of the Site was no longer in progress, the RFS Trust was depleted, and the Site was out of compliance.

Clarios requested an adjudicatory hearing before the DEP, arguing that the DEP’s rescission of the RIP Waiver without notice or an opportunity to be heard violated its due process rights. The DEP denied the request, stating that rescission of a RIP Waiver does not entitle Clarios to request an adjudicatory hearing pursuant to N.J.A.C. 7:26C-9.10(a) and that rescission does not constitute a contested case requiring a hearing under the Administrative Procedure Act.

Clarios appealed that decision. The Appellate Division ruled in favor of the DEP, holding that Clarios did not have a protected property interest in the RIP Waiver. 477 N.J. Super. 618, 628-29 (App. Div. 2024). The Court granted certification. 258 N.J. 55 (2024).

HELD: The DEP’s initial grant of the waiver did not create a property interest in the continued suspension of Clarios’s remediation obligations. Neither the controlling statutes and regulations nor a mutually explicit understanding between the parties provided an entitlement to the indefinite continuance of the waiver; to the contrary, the governing laws and agency materials all anticipate the DEP’s ability to enforce remediation obligations in the future.

1. The chief ingredient in a property interest protected by the due process clause is a legitimate claim of entitlement, and an express statutory or regulatory grant is the clearest and strongest proof of an entitlement. One indication that a statute or regulation creates a protected property interest is through limitations placed on agency decision-making with respect to an alleged benefit. If the decisionmaker is not required to base its decisions on objective and defined criteria, but instead can deny the requested relief for any constitutionally permissible reason or for no reason at all, the State has not created a constitutionally protected interest. And a mere subjective expectancy is not sufficient to establish a protected interest. If an entitlement is not granted and secured through explicit language or limitations on discretion, it may be derived from mutually explicit understandings. But for an “understanding” to give rise to a property interest, the party asserting an entitlement must establish that both parties mutually recognized the existence of an entitlement. When an agency has broad discretion to grant, deny, or remove a purported benefit, there is also not likely to be a mutually explicit understanding of an entitlement. (pp. 14-19)

2. Here, the question is whether Clarios was entitled to the RIP Waiver in April 2022, when the rescission letter was sent. Looking to the language of the relevant statutes and regulations to answer the operative question, the Court finds no such 2 indication of an express statutory grant of entitlement in the indefinite continuation of the RIP Waiver at the time of rescission. ISRA provides no guidance on how the DEP should exercise its discretion in enforcing remediation obligations once a property falls out of compliance. And, unlike the statute at issue in Cleveland Board of Education v. Loudermill, 470 U.S. 532 (1985), ISRA does not guarantee Clarios continued viability of the RIP Waiver, regardless of the Site’s compliance status. Nor is there any indication of such an entitlement in ISRA’s implementing regulations. To the contrary, ISRA’s implementing regulations expressly state that the DEP retains discretionary authority to rescind a RIP Waiver. N.J.A.C. 7:26B- 1.8(b). And N.J.A.C. 7:26B-5.4 governs the requirements for receiving and maintaining a RIP Waiver while remediation is “in progress.” ISRA’s implementing regulations thus make clear that the recipient of a RIP Waiver would not be exempt from future remediation obligations if the relevant industrial property were to fall out of compliance -- as it did here. As the Supreme Court found in Board of Regents v. Roth, 408 U.S. 564, 567 (1972), there simply is no entitlement if the decision, as it was here, is left to the “unfettered discretion” of the State. (pp. 19-23)

3. Clarios also has failed to demonstrate that an extra-statutory or extra-regulatory understanding existed that would support its claim of entitlement. Clarios alleges that such an understanding was evidenced by silence during the fifteen years that the DEP did not enforce Clarios’s residual remediation obligations. But an “understanding” capable of establishing a property interest cannot exist when, as here, the government has ample discretion to deny or withdraw the benefit in question. Furthermore, the DEP was not completely silent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goldberg v. Kelly
397 U.S. 254 (Supreme Court, 1970)
Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Perry v. Sindermann
408 U.S. 593 (Supreme Court, 1972)
Goss v. Lopez
419 U.S. 565 (Supreme Court, 1975)
Codd v. Velger
429 U.S. 624 (Supreme Court, 1977)
Leis v. Flynt
439 U.S. 438 (Supreme Court, 1979)
O'Bannon v. Town Court Nursing Center
447 U.S. 773 (Supreme Court, 1980)
Connecticut Board of Pardons v. Dumschat
452 U.S. 458 (Supreme Court, 1981)
Olim v. Wakinekona
461 U.S. 238 (Supreme Court, 1983)
Cleveland Board of Education v. Loudermill
470 U.S. 532 (Supreme Court, 1985)
Town of Castle Rock v. Gonzales
545 U.S. 748 (Supreme Court, 2005)
Doe v. Poritz
662 A.2d 367 (Supreme Court of New Jersey, 1995)
JE on Behalf of GE v. State
622 A.2d 227 (Supreme Court of New Jersey, 1993)
Bally Manufacturing Corp. v. New Jersey Casino Control Commission
426 A.2d 1000 (Supreme Court of New Jersey, 1981)
State v. Habeeb Robinson(078900) (Essex County and Statewide)
160 A.3d 1 (Supreme Court of New Jersey, 2017)
Jerome McKinney v. University of Pittsburgh
915 F.3d 956 (Third Circuit, 2019)
Claudio Tundo v. County of Passaic
923 F.3d 283 (Third Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
In Re Appeal of the New Jersey Department of Environmental Protection's September 6, 2022 Denial of Request for Adjudicatory Hearing, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-appeal-of-the-new-jersey-department-of-environmental-protections-nj-2025.