In re: Appeal of Mount Corp. ~ Appeal of: Mount Corp.

CourtCommonwealth Court of Pennsylvania
DecidedDecember 20, 2024
Docket373 C.D. 2023
StatusUnpublished

This text of In re: Appeal of Mount Corp. ~ Appeal of: Mount Corp. (In re: Appeal of Mount Corp. ~ Appeal of: Mount Corp.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re: Appeal of Mount Corp. ~ Appeal of: Mount Corp., (Pa. Ct. App. 2024).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

In re: Appeal of Mount Corporation : from the Decision of the Zoning : Hearing Board of Bensalem Township : dated August 8, 2022 : No. 373 C.D. 2023 : Submitted: November 7, 2024 Appeal of: Mount Corporation :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge HONORABLE LORI A. DUMAS, Judge HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY JUDGE DUMAS FILED: December 20, 2024

Mount Corporation (Mount) appeals from the order entered in the Court of Common Pleas of Bucks County (trial court), which affirmed the decision by the Bensalem Township (Township) Zoning Hearing Board (Board) (collectively, Appellees). Mount contends that the trial court erred by affirming the Board’s denial of its application for a variance under the Township’s zoning ordinance. We affirm. I. BACKGROUND1 Mount owns a 3.3-acre improved property, which has a warehouse and associated parking and loading areas. Mount’s property is located within the Township’s light industrial zoning district and natural resource protection overlay district.2 The overlay district essentially requires that the property be at least 50%

1 We state the facts as presented by the Board and trial court, which we view in the light most favorable to the prevailing party. See Cinram Mfg., Inc. v. Workers’ Comp. Appeal Bd. (Hill), 975 A.2d 577, 583 (Pa. 2009). The Board admitted into evidence several exhibits, which were not transmitted to this Court. 2 “An overlay district creates a framework for conservation or development allowing for a new type of development or imposing restrictions that is superimposed over the zoning districts woodlands. The ordinance defines “woodland” as at least one acre of wooded land where (1) the largest trees measure a particular diameter; or (2) a grove of trees fulfills certain other criteria. In 2020, during the pandemic, Mount hired landscapers, who removed “145.6” trees covering almost an acre of land. This resulted in the property being comprised of less than 50% woodlands. At some point, the Township was alerted to the landscaping and directed Mount to stop work. The Township reviewed the matter and issued a retroactive land alteration permit—not a variance—authorizing the tree removal.3 In 2021, Mount applied to the Board for dimensional variances to build an addition to the existing warehouse. Specifically, Mount requested relief under sections of the ordinance that addressed stormwater drainage and steep slopes. Mount’s application omitted any discussion of the trees and did not request a variance from the ordinance’s 50% woodlands requirement. Following hearings, a 3-2 majority of the Board granted Mount’s application, reasoning that Mount did not create any hardship and the requested variances would not alter the neighborhood’s

on all or part of a municipality. The purpose of an overlay district is to create specific and targeted provisions that conserve natural resources or realize development objectives without unduly disturbing the expectations created by the existing zoning ordinance. In other words, overlay districts supplement existing zoning districts, [but] they do not supersede them either in fact or in practice.” Protect PT v. Penn Twp. Zoning Hr’g Bd., 220 A.3d 1174, 1187 (Pa. Cmwlth. 2019) (cleaned up). 3 The parties and record do not define a “land alteration permit.” The ordinance refers to a “land alteration permit” under Ordinance 212 of the Bensalem Township Code, which was not transmitted to this Court as part of the record. Bensalem Twp. Ordinance § 232-59 (July 3, 2024) (“No grading shall be undertaken prior to the granting of necessary land alteration permit pursuant to Ordinance 212 of the Bensalem Township Code.”). An entirely different chapter of the Bensalem Township Ordinance, however, also provides a process for obtaining a permit to alter the land. See, e.g., Bensalem Twp. Ordinance § 103-23 (“Applications for alteration of land utilized wholly or partially for nonresidential purposes . . . shall be issued . . . subject to satisfaction of the requirements of this article and a recommendation from the Township Engineer . . . .”).

2 character. The Board noted that Mount still had to comply with the rest of the Township’s zoning ordinance. Mount then applied for the appropriate land development permits from the Township. The Township advised Mount that it needed additional variances because the property was less than 50% woodlands and thus did not comply with the overlay district. The Township apparently notified Mount that it must replant 75 trees, which reflects 50% of the 145.6 trees that Mount removed. Notes of Testimony (N.T.) Hr’g, 6/2/22, at 16-17 (quoting the Township’s engineer’s letter).4 Mount applied for a variance from the Board in 2022, specifically requesting relief from two sections of the zoning ordinance, which we discuss below. Simply, Mount wanted a variance from the requirement that the property be at least 50% woodlands. The Board held two hearings. At the initial hearing, Mount’s principal, Jake Kaplan, testified that Mount could not replace all of the trees because of insufficient space. N.T. Hr’g, 6/2/22, at 15. Per Kaplan, Mount would have had to plant trees “on top of each other” and Mount was advised not to “ask for a variance to plant trees right next to each other because long term that’s not a good solution.” Id.; accord id. at 14 (reflecting Farrall’s comment that if the proposed addition was built, there was only “room for some, but not all” of the trees so Mount would have to “donate to the tree bank or something”). Mount’s proposed plans—apparently not a “landscape plan”—depict “trees . . . as tightly spaced as is permitted under the code to be planted in the remainder of the property. So areas that are currently turf would essentially become woodlands based on our plans.” Id. at 16, 18 (“I don’t have a big

4 No one addressed the math discrepancy. Kenneth Farrall, the Township’s Director of Building and Planning/Zoning Officer, was apparently quoting the letter. Farrall was not sworn in, and the letter is not part of the record.

3 enough property I believe to replace every one of them.”). The Board continued the hearing to permit Mount to present a “landscape plan.” Id. at 19. At the subsequent hearing, Mount submitted a landscape plan that would add 73 trees to the property. N.T. Hr’g, 7/7/22, at 6. Mount’s counsel explained that in Mount’s view, if it had “146 trees, woodlands on site, [it] would need to retain 73 trees to be compliant” with the ordinance. Id. at 7; accord N.T. Hr’g, 6/2/22, at 16-17 (reflecting Township’s notice that Mount must replant half of the trees it removed). Mount’s counsel stated that “if we had 146 trees, woodlands on site, we would need to retain 73 trees to be compliant from a zoning standpoint. Instead of retaining the trees, we are replacing the trees, so we are, again, in my opinion, complying with the ordinance as it’s intended to be understood.” N.T. Hr’g, 7/7/22, at 7. Kaplan similarly acknowledged that Mount could not “put back the trees that we took down,” but reiterated that Mount was doing “everything in [its] power to” comply with the ordinance. Id. at 8. The Board expressed its concern that the new trees would average 2.5 inches in diameter in contrast to the removed trees, which averaged 9.5 inches in diameter. Id. at 12. The Board questioned Mount as to whether it could replant similarly sized trees. Id. at 12-13. Kaplan explained that the “success rates of” replanted “larger trees are much lower than the smaller trees long term.” Id. at 15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry A. v. Zoning Hearing Board
626 A.2d 1147 (Supreme Court of Pennsylvania, 1993)
Hertzberg v. Zoning Board of Adjustment
721 A.2d 43 (Supreme Court of Pennsylvania, 1998)
Cinram Manufacturing, Inc. v. Workers' Compensation Appeal Board
975 A.2d 577 (Supreme Court of Pennsylvania, 2009)
Weaver v. Harpster
975 A.2d 555 (Supreme Court of Pennsylvania, 2009)
Larsen v. Zoning Board of Adjustment
672 A.2d 286 (Supreme Court of Pennsylvania, 1996)
Goldstein v. Zoning Hearing Board of the Township of Lower Merion
19 A.3d 565 (Commonwealth Court of Pennsylvania, 2011)
S & H Transport, Aplt. v. City of York
210 A.3d 1028 (Supreme Court of Pennsylvania, 2019)
Tri-County Landfill, Inc. v. Pine Township Zoning Hearing Board
83 A.3d 488 (Commonwealth Court of Pennsylvania, 2014)
Stratford Arms, Inc. v. Zoning Board of Adjustment
239 A.2d 325 (Supreme Court of Pennsylvania, 1968)
Boyd v. Wilkins Township Board of Adjustment
279 A.2d 363 (Commonwealth Court of Pennsylvania, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
In re: Appeal of Mount Corp. ~ Appeal of: Mount Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-appeal-of-mount-corp-appeal-of-mount-corp-pacommwct-2024.