Impastato v. Senner

190 So. 2d 111, 1966 La. App. LEXIS 4714
CourtLouisiana Court of Appeal
DecidedJuly 5, 1966
DocketNo. 2290
StatusPublished
Cited by2 cases

This text of 190 So. 2d 111 (Impastato v. Senner) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Impastato v. Senner, 190 So. 2d 111, 1966 La. App. LEXIS 4714 (La. Ct. App. 1966).

Opinion

HALL, Judge.

Plaintiff, a licensed architect, was employed by defendants in connection with the-renovation and remodeling into a motel of a certain building owned by defendants located at 1001 Chartres Street in the City of New Orleans'. The motel is now being operated by defendants under the name and [113]*113style of “Chateau Motor Hotel.” Plaintiff, not having received payment for his professional services, brought this suit to collect his fee amounting to $9,521.78 and prayed for interest thereon at the rate of 7% per annum from May 2, 1953 until paid, plus an additional 15% as attorney’s fees. Answering the suit, defendants alleged that dilatory tactics on the part of plaintiff had delayed the completion of the job causing defendants a loss in profits in an amount considerably more than the amount claimed by plaintiff and consequently plaintiff is due nothing.

Following trial on the merits judgment was rendered in plaintiff’s favor for $7,-021.78 with legal interest thereon from date of judicial demand until paid plus 15% of that amount as attorney’s fees. Both parties moved for a new trial (reargument) which was granted. Following reargument the Trial Judge rendered judgment in plaintiff’s favor for $7,021.78 with legal interest thereon from judicial demand until paid. Plaintiff appealed. Defendant answered the appeal praying that the judgment appealed from be reversed and that plaintiff’s suit be dismissed at his cost.

The issues are: (a) whether plaintiff substantially performed his duties under the contract of employment; (b) whether this is a suit on a note or on the employment contract; and, (c) whether defendants are entitled to an off-set against the amount of plaintiff’s fee, and, if so, in what amount.

The following facts are undisputed (except as noted):

In March of 1962 defendants began negotiations for the purchase of the building at 1001 Chartres Street with the idea of transforming it into a motel. Hearing of this, plaintiff contacted defendants and solicited the architectural work on the project. Defendants informed him that they had put all their cash into the purchase of the land but if he would wait until completion of the project to collect his fee, he could have the job. Plaintiff agreed to this. His fee was to be 6% of the contract price. Defendants informed plaintiff that their budget for construction was $150,000.00, and that they hoped to have the motel in operation by January 1963. Plaintiff apparently set to work right away and submitted preliminary plans to the owners sometime in April 1962.

On April 3, 1962 defendants signed an agreement to purchase the building.

In May of 1962 plaintiff had defendants sign a standard form of contract issued by the American Institute of Architects. Notwithstanding the fact that this contract provided for the payment of 25% of the architectural fee of 6% upon completion of preliminary studies and the remaining 75% in monthly installments during preparation of the final plans and specifications, both parties agree that there was never any intention to alter their verbal agreement that payment would be due only on completion and acceptance of the motel.

Plaintiff submitted final plans to defendants on July 16, 1962 and on July 20, 1962 defendants took title to the property. The plans were revised by plaintiff on August 31, 1962 and then submitted to seven contractors allowing three weeks for the submission of bids. Only two bids were received, the lowest of which exceeded defendants’ construction budget by more than $100,000.00.

Mr. Steven G. Benton, d/b/a Tra-Mont Builders was one of the contractors who had been invited to bid but did not do so because in his opinion the plans were insufficient to form a basis for a realistic bid. However, negotiations were thereafter entered into between defendants and Mr. Benton with the view of altering the plans and specifications so that the project could be completed within the $150,000.00 budget limit. Most of these negotiations were conducted between defendants and Mr. Benton although plaintiff was consulted from time to time. The record shows in this connection that the services of an architect were necessary because a City building per[114]*114mit cannot be secured for renovation work in excess of $50,000.00 unless the plans and specifications are prepared and signed by a duly licensed architect.

Plaintiff’s plans and specifications were finally worked down and the changes and alterations therein were approved and signed by plaintiff. Mr. Benton agreed to do the work for $166,238.00 and a contract therefor was signed by Mr. Benton and the owners on October 15, 1962. The contract provided for substantial completion of the building within 151 days from issuance of the building permit by the City of New Orleans. Plaintiff filed the revised plans and specifications and secured the building permit on October 24, 1962. According to our calculation this meant that the motel should be substantially completed by March 23, 1963, it being testified that the 151 days meant “calendar days”.

On April 2, 1963 seven of the thirty-seven units of the motel were opened and the other thirty units were completed and opened by the end of April. Defendants recorded their acceptance of the building on May 2, 1963.

About the month of September 1962 relations between plaintiff and defendants became strained and by the middle of October when the building contract wás signed the parties were not on speaking terms. All contact between them was through Mr. Benton, the contractor. Sometime in October defendants exhibited to plaintiff an unsigned promissory note payable to his order for $9,974.28, this figure being the full amount of his architectural fee. The proposed note was rejected by plaintiff after consultation with his attorney who advised him that if he accepted the note in payment he would lose his lien on the building. Both parties agree that no part of plaintiff’s fee was to be paid until completion and acceptance of the job. Testimony on the part of defendants is that the note was offered plaintiff in response to plaintiff’s request for security for his fee. Plaintiff on the other hand states that he did not ask for the note nor had he asked security for his fee, and that the idea of the note was a scheme on the part of defendants to destroy his lien rights. However, plaintiff testified that following the note incident he got frightened and did demand security.

According to testimony adduced by defendants, plaintiff threatened, unless security for his fee was forthcoming, to pull his plans off the job and thereby cause the City to revoke the building permit; and that as a matter of fact one day the City did remove the permit from the building, but this was straightened out the same day. Plaintiff denied such threats.

Plowever negotiations looking toward the furnishing of security continued until on December 6, 1962 defendants secured plaintiff’s fee by putting a second mortgage note in escrow with the National Bank of Commerce and entering into an escrow agreement with plaintiff and the bank. The second mortgage note is in the principal sum of $9,521.78, is payable in certain installments and contains an acceleration clause. It bears interest at the rate of 7% per an-num from maturity until paid and 15% attorney’s fees in the event it “should be placed in the hands of an attorney for collection.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Miami Beach v. Fein
263 So. 2d 258 (District Court of Appeal of Florida, 1972)
Impastato v. Senner
191 So. 2d 639 (Supreme Court of Louisiana, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
190 So. 2d 111, 1966 La. App. LEXIS 4714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/impastato-v-senner-lactapp-1966.