Imeson v. Newport & Covington Bridge Co.

12 Ky. Op. 492, 5 Ky. L. Rptr. 685, 1884 Ky. LEXIS 214
CourtCourt of Appeals of Kentucky
DecidedFebruary 21, 1884
StatusPublished
Cited by1 cases

This text of 12 Ky. Op. 492 (Imeson v. Newport & Covington Bridge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Imeson v. Newport & Covington Bridge Co., 12 Ky. Op. 492, 5 Ky. L. Rptr. 685, 1884 Ky. LEXIS 214 (Ky. Ct. App. 1884).

Opinion

Opinion by

Judge Pryor:

This action was instituted to recover the reasonable value of appellants’ services in the construction of a piece for appellee’s bridge over the Licking river between the cities of Covington and Newport. The original petition was based on a written contract between the parties by which the appellants agreed to construct the pier according tó certain specifications and places as set forth in exhibit “A”, the specifications and drawings made by John Gray.

According to the plan, the pier was to rest on bed rock 88 feet 4 inches from the floor of the bridge and 12 feet below the bed of the river, for which the appellants were to receive $21,478. The contract contained this proviso: “It being further understood and agreed that all excavations below the depth designated in the plan referred to, if any, shall be done at the rate of $2.50 per cubic yard, and all masonry required below the same depth shall be done at the rate of $14.25 per perch of 25 cubic feet.” The parties therefore anticipated that the excavation or depth of the pier might exceed twelve feet and contracted in plain terms that if such was the [494]*494case they were to receive $2.50 per cubic yard for the excavation and for the masonry $14.25 per perch of 25 cubic feet. We perceive no ambiguity in the contract, or anything upon the face of the writing that would authorize the introduction of parol testimony to vary or contradict its terms in the absence of any allegation of fraud or mistake in its execution. The intention and purpose of the parties can not be mistaken when looking to the subject-matter of the contract and the stipulations embraced by it.

It may appear unreasonable that the appellants should contract to construct this masonry, and make the excavation a distance of thirty-two feet at the prices fixed by the agreement; and while that fact, if established, may conduce to show a mistake in the execution of the agreement or fraud in its procurement, still in the absence of the existence of fraud or mistake the party must be held to its terms. The appellants have contracted to go down until they reach bed rock and must be presumed to have understood the meaning of the language used when contracting with the appellee. A contract may be neither rational nor just, still if there is no ambiguity in the contract the court has no right to say that the parties did not mean to contract in the manner their language plainly imports. The fact that one has made an improvident contract by which loss must reasonably follow will not authorize a reformation of the instrument, but it may be a circumstance conducing to show that the contract was not reduced to writing as the párties intended it should have been, or was improperly obtained by the parties benefited b)'- its provisions.

The appellants filed several amended petitions in which fraud and mistake are alleged in obtaining the contract and in reducing it to writing. Also an amended pleading, alleging in substance that after going the depth of fifteen feet they ascertained that bed rock could not be reached without going a distance of thirty-two feet, and they notified the company that by the agreement which should have been embodied in the writing fifteen feet was the ultimatum or as far as they were required to go, and that the company then agreed that they should go on with their work until they reached bed rock and it would pay what it was worth.

A letter is exhibited which it is alleged was the notice given the company, and whether received or not is immaterial, as we deem it unnecessary to pass upon the testimony. The appellants upon the question of fraud and mistake are met with the objection that the [495]*495chancellor alone had jurisdiction to reform the contract if any mistake existed in reducing it to writing. While the common-law judge and the chancellor have concurrent jurisdiction on the question of fraud, as to the reformation of a part of the contract, changing its stipulations in important particulars, a court of equity has the jurisdiction. When the consideration of a contract attempted to be enforced is wholly based on a mistake it may be pleaded at law. Pope v. Wickliffe, 7 T. B. Mon. (Ky.) 412. Or where the obligor in a note is sued he may plead that it was executed for too much. Banton v. Hoomes Exrs., 1 A. K. Marsh. 19. The general doctrine is that mistakes in drawing instruments may be shown by parol and the relief granted by a court of equity. The testimony should be clear and convincing, and therefore the danger of submitting such a question to a jury where a partial reformation of the writing must be established in order to recover. The appellants, therefore, on this branch of the case were compelled to go into a court of equity, and there was no error in transferring the case to the chancellor for the purpose of having the issue as to the mistake established; and the whole case having been transferred, the chancellor, having concurrent jurisdiction on the subject of fraud, had the right to dispose of both issues without the intervention of a jury. The testimony on the issues of fraud and mistake is not so convincing as would authorize this court to reverse his judgment on either ground.

The third amended petition offered by appellants is in substance “that when the appellants had reached the depth of fifteen feet below the surface of the water and not finding bed rock they refused to proceed further in the construction of the pier unless the defendant would agree to pay them what the work below that point was reasonably worth, and in a settlement of the differences between them as to what was the contract or as a compromise of the controversy the board of directors, being then in session and having under consideration the protests of the plaintiffs and the compromise of the controversy, then and there agreed that if the plaintiffs would proceed with the execution of the work to its completion they would pay the plaintiffs what said excavation and masonry made below the depth of fifteen feet should be worth, and the same was communicated to the plaintiffs by James M. Boyd, one of the board of directors, and thereupon the plaintiffs did proceed in the execution of the work with the knowledge and approval of the board of directors [496]*496that they were so proceeding under said agreement, that the defendant would pay them what the work was reasonably worth.”

This contract if established by the testimony was a substitute or in lieu to that extent of the original contract, and the controversy existing between them as to what should have been embraced by the terms of the writen contract was a sufficient consideration for the parol understanding. The burden was oh the appellants to establish a change in the agreement, and what evidence they may have in support of this pleading it is unnecesary to determine as no proof was permitted to go to the jury on the issue. It was not incumbent ón the appellants to show a resolution of the board approving the change of contract, if any was made. The officers of the company or those authorized to superintend and control the work with the right to change or alter the specifications or plan may do so if they deem it essential to the interest of the company.

If in this case there had been no change in the original plan fixing the bed rock at twelve feet below the surface, and the appellants finding no rock foundation at that point had proceeded with the knowledge of the company and its agents superintending the work to excavate a distance of thirty-two feet, the law would create an implied promise to pay its reasonable value.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Illinois Central R. R. v. Manion
67 S.W. 40 (Court of Appeals of Kentucky, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
12 Ky. Op. 492, 5 Ky. L. Rptr. 685, 1884 Ky. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/imeson-v-newport-covington-bridge-co-kyctapp-1884.