Illinois Steel Co. v. Koshinski

135 Ill. App. 587, 1907 Ill. App. LEXIS 558
CourtAppellate Court of Illinois
DecidedAugust 6, 1907
DocketGen. No. 4,832
StatusPublished
Cited by1 cases

This text of 135 Ill. App. 587 (Illinois Steel Co. v. Koshinski) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Steel Co. v. Koshinski, 135 Ill. App. 587, 1907 Ill. App. LEXIS 558 (Ill. Ct. App. 1907).

Opinion

Mb. Justice Thompson

delivered the opinion of the court.

This is an action on the case brought by Lawrence Koshinski, appellee, against the Illinois Steel Company, appellant, for personal injuries received by appellee on October 16, 1905, caused by an explosion in appellant’s steel mill at Joliet. The case went to the jury on the additional counts to the declaration, the jury being instructed there could be no recovery under the original declaration. The first additional count alleges that appellant was engaged in the manufacture of steel products and operated, as a part of its mills, a mill known as a converter, using therein certain vessels in which steel was heated or blown, known as Nos. 1, 2 and 3; and it avers that said vessels were moved by water power and were so constructed that hot air known as the blast was blown in from the bottom" or sides of said vessels, and the water used to move said vessels was connected by pipes in which were valves by which the water could be cut off and turned on; that in the operation of said vessels they were partially filled with metal which was then heated to a high degree, and when sufficiently heated the metal was poured out of the vessels into a ladle; that at the time of the injury plaintiff was in the employ of defendant and was working upon an elevated platform several feet above the ground, in the exercise of due care for his own safety, when the defendant by one of its servants not a fellow-servant of plaintiff, carelessly and negligently shut off the water from vessel No. 3 so that it could not be properly operated and before the water could be turned on the metal in the vessel No. 3 became overblown or overheated, and the defendant negligently caused other and cooler metal to be added to said vessel so overheated, and by reason of the negligence of defendant in shutting off said water and allowing said metal to be overblown and adding said cooler metal, an explosion was caused and the bottom of said vessel No. 3 blown out and a large quantity of molten metal struck plaintiff and knocked him off the platform, and he was greatly injured and burned and suffered a double hernia from the fall, etc. The second additional count alleges negligence in that defendant permitted the metal in one of said vessels to be overblown and immediately caused cooler metal to be added to it, etc. The third additional count alleges negligence in that defendant permitted the metal in one of said vessels to be overblown, and then added other cooler metal, thereby loading the vessel beyond its capacity, etc. There were three other additional counts one of which alleged careless and negligent operation. The jury returned a verdict for $2,500 upon which a judgment was rendered and the defendant appeals.

At the close of all the evidence the defendant moved to exclude all the testimony and requested that the jury be instructed to return a verdict of not guilty. The court overruled the motion and refused the instruction. This is relied on for error.

The evidence shows that the appellee was working on a mould-cleaning platform of the Bessemer mill of appellant, and that while thus employed he was injured by an explosion of the converting vessel known as No. 3. In the Bessemer process of making steel hot air is forced through a mass of molten metal, which causes the temperature to rise until the carbon and other impurities contained in the molten metal are burned out, leaving the steel. The ore is first melted, part in what is described as the cupola and part in the blast furnaces, then the two are combined and mixed in what is called the mixer mill, and then the metal, still being in a molten state, is pnt into what are called the converter vessels. Vessel No. 3 was a-twelve-ton vessel, that being the amount ordinarily put into it at one time. The converter that exploded is a large bottle-shaped vessel, about seven and one-half feet in diameter at the bottom and fifteen feet long, inside measurement, with a cone-shaped top, and has a cubical capacity of about seventy-five tons. It is suspended upon trunions in bearings, and is moved by hydraulic pressure by means of racks and gears attached to these trunions. The vessel can swing on the trunions in a semi-circle so that the molten metal may be poured out of it. In the bottom of the vessel are tubes or pipes called tuyeres made of refractory material through which the blast enters the vessel. The aperture at the mouth or nose of the vessel is about two feet nine inches in diameter. The bottom of the vessel is built on a steel shell of refractory material, and is fastened on by ten hangers, each capable of sustaining twenty tons weight. The vessels are relined on Sundays, and this accident happened on Monday night. "When the vessel is to be charged with metal it is turned on its side, with the mouth to the north, by hydraulic machinery, and the appropriate amount of molten metal, about twelve tons, is poured in through the mouth, the charge being about eighteen inches deep when the vessel is lying horizontal. The vessel is then raised to a vertical position when the molten metal fills the bottom to a depth of thirteen and one-half inches; the blast is turned on, while this is being done, by the “steel blower” who stands on a platform 150 feet distant. The time required to blow a heat'varies from seven to eighteen minutes, according to the evidence of Spencer, the superintendent of appellant’s Bessemer department, and from six to seven minutes according to the evidence of Zaworski, once an employe of appellant, but now with the Superior Chemical Company. The “steel blower” controls the time of the blast by hydraulic machinery, and sees when the heat is sufficiently blown by the color of the flame from the mouth of the vessel, which indicates to him when the impurities are burnt out. In making soft steel, after the heat is blown the vessel is turned to the south and the molten metal is poured into ladles and. taken to the moulds. In blowing soft steel the safe capacity of the vessel is put in when it is first charged. In blowing hard steel about 1,800 pounds less than the full charge is in the first instance placed in the vessel, and the heat is blown as in .making soft steel; then in place of the vessel being turned to the south and emptied, it is turned to the north and 1,500 to 1,800 pounds of the same kind of molten metal, as was put in at first, is added to recarbonize the steel, and the blast is again turned on and the vessel turned back to the south and emptied. At the time of the accident soft steel was being blown with a full heat in vessel No. 3. When the “steel blower” attempted to turn, the vessel for the purpose of running the metal into the ladle, he found something was wrong with the hydraulic machinery and the vessel could not be moved. A whistle was blown indicating that there was trouble. The superintendent of the converter hurried to see what the trouble was, and finding the vessel could not be moved sought the machinist, but could not find him at the moment. After some delay it was discovered that the back pressure valve on vessel No. 3 had been closed by mistake when the machinists were working on vessel No. 2. The valve was then turned so that the machinery would operate; in the meantime the heat had been blowing five minutes or more too long, before the cause of the trouble had been discovered and remedied. The metal was thus overblown or burned, and to try to save it, the superintendent ordered the vessel turned back to the north and 1,800 pounds of cooler molten metal added.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barretta v. Chicago Railways Co.
214 Ill. App. 455 (Appellate Court of Illinois, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
135 Ill. App. 587, 1907 Ill. App. LEXIS 558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-steel-co-v-koshinski-illappct-1907.