Illinois Power Co. v. Champaign Asphalt Co.

310 N.E.2d 463, 19 Ill. App. 3d 74, 1974 Ill. App. LEXIS 2578
CourtAppellate Court of Illinois
DecidedApril 25, 1974
DocketNo. 12208
StatusPublished
Cited by2 cases

This text of 310 N.E.2d 463 (Illinois Power Co. v. Champaign Asphalt Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Power Co. v. Champaign Asphalt Co., 310 N.E.2d 463, 19 Ill. App. 3d 74, 1974 Ill. App. LEXIS 2578 (Ill. Ct. App. 1974).

Opinion

Mr. JUSTICE SIMKINS

deivered the opinion of the court:

This is an appeal from a judgment for $7923.47 in favor of the plaintiff power company for electricity supplied to the defendant over a 3-year period in excess of the amount billed and paid for as measured and recorded by plaintiff’s defective transformer and metering equipment.

The plaintiff, Illinois Power Company, entered into a contract in July 1959 to supply defendant, Champaign Asphalt Company, with electricity. On October 27, 1969, the plaintiff filed a complaint alleging that from April 1964 to May 1967 the plaintiff supplied electricity and the defendant paid for the amount billed as registered by the plaintiff’s meter. The complaint further alleged that a routine review of accounts by the plaintiff indicated a likely error in the defendant’s account in that there was a sudden decrease of approximately 50% in the amount billed to the defendant in April 1964, continuing up to the time of the review, and that on May 25, 26 and 27, 1967, tests were performed which indicated that the meter at the defendant’s premises was recording only 50% of the current actually being used. The complaint therefore concluded that from April 1964 to May 1967 the defendant had only been billed for one-half of the electricity used and that the defendant would owe $7923.47 for the used, but unpaid-for, electricity.

The defendant filed a motion to dismiss on the grounds that plaintiff’s complaint failed to state a cause of action because it did not state that the plaintiff had complied with general order 161 of the Illinois Commerce Commission nor affirmatively state the steps taken to comply with that general order. It further alleged that on its face it was clear that the basis of the claim arose more than 1 year after such electricity was furnished, and, since under section 76 of the Public Utilities Act (Ill. Rev. Stat, ch. 111⅔, par. 76), the defendant could not contest any rate charge after 1 year, equal protection would require the plaintiff’s right also to be barred. After its motion to dismiss was denied, defendant filed an answer to the complaint admitting the relationship between the parties and the using and paying for electricity billed between April 1964 and May 1967, but denied that electricity had been used in addition to that billed and paid for. The defendant denied that plaintiff had performed all the terms of the contract and alleged that plaintiff had failed to test the meter as required in Rules 12 and 13 of General Order 161 of the Illinois Commerce Commission. The answer contended that the plaintiff would be barred by Rule 16(c) of the General Order because it allowed the inaccurate meter to remain in service and relied upon it for 3 years, sending bills each month which were promptly paid, and finally, asserted that the provision of Rule 16(b) that where a non-registering meter has been read while not working the utility is limited to billing only for the estimated consumption not to exceed twice the period of the regular interval between readings would preclude plaintiff from recovering for more than that period, if any recovery at all were proper.

A bench trial was held on August 4, 1970, at which the plaintiff produced testimony concerning the review of accounts in May 1967 which disclosed that the defendant’s usage of electricity had dropped by approximately one-half in April 1964 and introduced records of the monthly meter readings and bills of the defendant’s account from 1959 through 1967 showing the drop in usage during the time in question as compared to the corresponding months in years prior to 1964. An instrumentation engineer employed by the plaintiff described the metering devices used at the defendant’s premises and testified to the periodic tests, some of which were performed annually, and further testified to tests made on all the metering devices before installation. It was brought out that a large commercial or industrial user like the defendant does not utilize a simple watt hour meter as commonly used in private homes, but rather a demand type meter is used because it is impractical to have a meter large enough to actually measure all the electricity passing through it. The demand type meter diverts a particular constant proportion of the total current and measures it, thus requiring two steps, the transformer which separates the relatively small proportion of the total current, and the regular watt hour meter which measures and records it. Plaintiffs witnesses testified that the watt hour meter was tested annually and was apparently functioning correctly in past years and at the time of the test in May 1967. However, those more extensive tests made after the discovery of a probable under reading showed that the instrument transformer was malfunctioning. A parallel installation test showed a constant load pattern which would indicate the transformer was damaged, and upon further inspection the tank and transformer portion of the metering device appeared to have been damaged, in the opinion of the engineer, by lightning. The engineer further testified that the watt hour meter would not work without the instrument transformer, but that there could be a partial failure which would result in an under-registration by the watt hour meter. It was brought out that the watt hour meter was tested annually, but the instrument transformer had not been tested since its installation because, although there were tests that could be performed, they would only be accurate at high load and the plaintiff power company did not make tests during times of defendant’s high usage because it was considered to be dangerous due to the location of the metering equipment.

The defendant’s evidence consisted of testimony from the manager of another power company who testified it was their practice to review the accounts of large commercial users three or four times a year. The defendant also produced testimony to the effect that there are three lights on demand transformers which would indicate a malfunction by one or more of them not being lighted. In addition the defendant elicited testimony to the effect that it was possible to test the instrument transformer as well as the watt hour meter periodically while installed and in operation.

On January 26, 1971, the court filed an order which summarized the evidence indicating that the fact of the under-registration to the extent of 50% during the 37-month period was established, but “The court finds from all the evidence introduced and from all the facts and circumstances in this case that the plaintiff utility was at fault in not making a more thorough test of the meter, transformer, and all of the measuring equipment between the period of May 1964 and May 1967, and that it was further at fault and negligent in not reviewing the customer accounts and determining that it was metering inaccurately the use of electricity subsequent to April 1964 prior to doing so in May 1967.” However, language in the next paragraph where the court found that large accounts should be reviewed more often than once in 3 years, there being evidence in the record that another company reviews their large accounts as often as three or four times a year, indicates that the primary reason for finding the plaintiff “at fault” was the lack of diligence in reviewing accounts and the fact that the plaintiff relied on its defective meter readings for 37 months, rather than a failure to comply with the technical testing requirements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Narragansett Electric Co. v. Carbone
898 A.2d 87 (Supreme Court of Rhode Island, 2006)
Peoples Gas, Light & Coke Co. v. Illinois Commerce Commission
529 N.E.2d 671 (Appellate Court of Illinois, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
310 N.E.2d 463, 19 Ill. App. 3d 74, 1974 Ill. App. LEXIS 2578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-power-co-v-champaign-asphalt-co-illappct-1974.