Illinois Malleable Iron Co. v. Brennan

174 Ill. App. 38, 1912 Ill. App. LEXIS 234
CourtAppellate Court of Illinois
DecidedOctober 16, 1912
DocketGen. No. 16,773
StatusPublished
Cited by6 cases

This text of 174 Ill. App. 38 (Illinois Malleable Iron Co. v. Brennan) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Malleable Iron Co. v. Brennan, 174 Ill. App. 38, 1912 Ill. App. LEXIS 234 (Ill. Ct. App. 1912).

Opinion

Mr. Presiding Justice Duncan

delivered the opinion of the court.

This suit in assumpsit was brought December 31, 1909, by Illinois Malleable Iron Company, plaintiff in error, against D. G. Brennan and M. J. Dempsey, as contractor and owner, respectively, under Section 28 of the Mechanic’s Lien Act, to recover the sum of $362.48 for plumbing and heating material furnished the contractor for improving a building of the owner at 2550 Logan Boulevard, Chicago, and under a contract with said owner. Dempsey was personally served with process and in a jury trial contested the action. Brennan had moved to Sullivan, Mich., and was served by publication, but did not appear to resist judgment. The evidence did not disclose a single disputed fact submitted to the jury, except upon the question of whether or not Brennan had at different dates made two separate contracts with Dempsey, one for plumbing and the other for a heating plant for said premises.

The court overruled plaintiff in error’s motion at the close of all the evidence to direct a verdict in its favor, and instructed the jury, in substance, that if they found from the evidence that Dempsey and Brennan entered into two distinct contracts for work and materials for the said premises, and if they also found from the evidence that one of said contracts was completed before the other was begun and that notice of plaintiff in error’s claim for lien was served upon Dempsey more than sixty days after the last quantity of material was delivered for the first contract by plaintiff in error, that in such case' the plaintiff in error could not recover for the materials delivered under the first contract. The jury returned a verdict for the defendants in error, and the court rendered a judgment thereon against plaintiff in error and for costs, in favor of Dempsey and Brennan, after overruling its motion for a new trial.

Plaintiff in error made proof of every material fact necessary to establish its right to a subcontractor’s lien under the statute, and save only in the particular above named, its evidence is absolutely undisputed. We are unable to see how plaintiff in error’s right to recover in this case can be defeated in any part, if it be conceded that the evidence does establish two separate and distinct contracts, one for plumbing or the installation of bath and toilet and other such fixtures, and the other for the installation of a heating plant. Both jobs were done on the same building and for the same owner, and if the heating plant was the second job, it properly comes under the head of “extra or additional work and material,” mentioned in the statute, and for which both the contractor and subcontractors are entitled to their liens the same as for the original work and materials contracted for. The two jobs are usually done by the same workmen, and are both done by plumbers regularly, and are known as plumbers’ jobs. We can see no difference in principle in these contracts and two contracts by a carpenter, one to build a house complete except as to lathing and plastering, and a later contract to lath the building or do any other additional or extra carpenter work not contemplated in the original contract. We hold that in such case any subcontractor who had a contract with such contractor to furnish lumber for the building of the house, even though made before such additional work was contracted for, would have his lien for the lath, or additional material furnished, and for the lumber furnished in the original contract, even though his notice was served more than sixty days after the last item furnished under the original contract, provided the notice was served within sixty days of the last delivery of the additional material. The last date of delivery of the additional material or work is the day from which the sixty days is reckoned, and section 24 of the Mechanic’s Lien Act so provides. It was error to give said instruction and the jury were thereby misled. Besides, it is against the preponderance of the evidence to find that there were two distinct contracts. Dempsey testified when first examined that he said to Brennan: “I have got some work to be done over on the house; go over and do it.” He said no price was fixed and that nothing was said by him what it would cost or anything else. He then testified that he paid Brennan for the plumbing $225 September 3, 1909, when that job was completed, and $375 for the heating plant when that was completed, October 11, 1909. Plaintiff in error delivered the material right along without notice of any claim that there were two contracts between defendants in error, and its contract was single and for material to be used for the building without any notice that the same was to be considered other than a single contract. Brennan’s evidence supports Dempsey’s first evidence that there was such a single contract for both jobs, and the only evidence contradictory to that idea was given by Dempsey on his final examination.

Defendant in error also insists that the Municipal Court was without jurisdiction to try this cause, because in plaintiff in error’s statement of claim it claimed that it was “entitled to a judgment and a lien against said premises.” The judgment contemplated under said Section 28 is for money only, but as a prerequisite to such a judgment against the owner a plaintiff must show.that he is entitled to a lien on the premises. The fact that he is entitled to a lien is one of the ultimate facts to be proved and should be recited in the judgment. No mechanics’ lien can be enforced by this section or by a judgment thereunder, and .therefore the judgment is for money only within the meaning of the Municipal Court Act, which provides that said court' shall have jurisdiction in fourth class cases, “which shall include all civil actions, quasi-criminal actions excepted, for the recovery of money only when the amount claimed by the plaintiff, exclusive of costs, does not exceed one thousand dollars.”

It is also insisted by defendant in error that no satisfactory proof of the delivery of the material for use in Dempsey’s premises were made. The proof is ample and positive by Brennan and others that the material was not only delivered to Brennan on the premises, but was accepted by him, and that it was all used by Mm in Ms work on the building. There is no evidence in the record to the contrary.

Upon the claim that plaintiff in error failed to join Ml necessary parties as defendants, we must hold that the contention is not supported by the record. The evidence positively shows that there were no other contractors or subcontractors except Brennan and plaintiff in error, and the record discloses no other parties with mortgage liens, even if it be conceded that they should have joined as defendants, if there were such mortgage lienors. Service by publication was had on Brennan as provided by said Section 28 of the Mechanic’s Lien Act. The court, therefore, had jurisdiction of his person and could render a personal judgment against him and Dempsey jointly, as Dempsey was personally served by process. Smith v. Slaughter, 138 Ill. App. 46.

The court also erred in holding that the evidence of Brennan, on his cross-examination by plaintiff in error, was competent only as against Brennan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis v. State
22 Ill. Ct. Cl. 11 (Court of Claims of Illinois, 1954)
Edwards v. Martin
117 N.E.2d 864 (Appellate Court of Illinois, 1954)
Day v. Ukena
113 N.E.2d 574 (Appellate Court of Illinois, 1953)
Combs v. Younge
281 Ill. App. 339 (Appellate Court of Illinois, 1935)
Weil v. Bomash
237 Ill. App. 544 (Appellate Court of Illinois, 1925)
Boothman v. Wulfing
194 Ill. App. 289 (Appellate Court of Illinois, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
174 Ill. App. 38, 1912 Ill. App. LEXIS 234, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-malleable-iron-co-v-brennan-illappct-1912.