Illinois Environmental Protection Agency v. Illinois Pollution Control Board

2018 IL App (4th) 170144
Appellate Court of Illinois·Decided October 29, 2018·No. 4-17-0144·Unpublished·Cited by 1 cases

Opinion

2018 IL App (4th) 170144

NO. 4-17-0144 FILED October 29, 2018

Carla Bender

IN THE APPELLATE COURT

4th District Appellate

Court, IL

OF ILLINOIS

FOURTH DISTRICT

THE ILLINOIS ENVIORNMENTAL ) Direct Review of the Illinois PROTECTION AGENCY, ) Pollution Control Board Petitioner, ) PCB No. 16-66 v. )

THE ILLINOIS POLLUTION CONTROL ) BOARD and BRICKYARD DISPOSAL ) & RECYCLING, INC., )

Respondents. )

JUSTICE KNECHT delivered the judgment of the court, with opinion Presiding Justice Harris and Justice Steigmann concurred in the judgment and opinion.

OPINION

¶1 Respondent, Brickyard Disposal & Recycling, Inc. (Brickyard), filed a permit application with petitioner, the Illinois Environmental Protection Agency (Agency), seeking to modify the design of its Vermilion County landfill to allow a “wedge” area to be filled with municipal solid waste as opposed to inert material. The Agency denied the petition as incomplete, finding Brickyard failed to obtain local governmental approval for the proposed expansion under section 39(c) of the Environmental Protection Act (Act) (415 ILCS 5/39(c) (West 2014)) and failed to include a new or updated groundwater impact assessment (GIA).

¶2 Brickyard appealed the Agency’s decision to the Illinois Pollution Control Board (Board). Before the Board, both parties filed summary judgment motions. The Board granted

Brickyard’s motions, finding local governmental approval was not required as Brickyard was not seeking to expand the boundaries of its pollution control facility and determining Brickyard’s GIA was not incomplete. The Board ordered the Agency to consider the technical merits of Brickyard’s application.

¶3 The Agency petitioned this court for direct administrative review, arguing the Board erroneously found Brickyard’s request to fill the wedge area is not a request for a “new pollution control facility” that requires local siting review. We affirm.

¶4 I. BACKGROUND

¶5 Brickyard owns and operates a landfill in Vermilion County, Illinois. In June 1981, the Agency issued to Brickyard a development permit for construction of a landfill facility. The Agency authorized the development of a 293-acre site with waste disposal occurring on 152 acres under a single landform with a height not to exceed 675 feet.

¶6 At the time Brickyard acquired its development permit, the Agency had the task of approving the site of pollution control facilities. As of November 1981, the Act was amended to provide for the siting review of “new pollution control facilities” to be performed by local governmental authorities. See Pub. Act 82-682, § 1 (eff. Nov. 12, 1981) (amending 415 ILCS 5/39).

¶7 In April 1987, the Agency issued a supplemental permit to divide the landfill into two units. Unit 1 consisted of the southern portion of the facility. Unit 2 constituted the northern portion. The permit affirmed the final elevation contours and the waste boundaries set forth in the June 1981 development permit.

¶8 In September 1991, Brickyard filed a “Request for Site Approval for a Regional

-2­

Pollution Control Facility” with the Vermilion County Board. Brickyard sought local siting approval for “the volumetric expansion of the existing landfill.” In the public notice of the request, Brickyard stated it was seeking an expansion consisting of a lateral expansion of approximately 21 acres and a 40-foot vertical expansion in height “over a 90-acre portion of the total 293-acre facility.” The drawings included a profile of the proposed vertical expansion that depicted an expansion across a single landform to a height of 715 feet.

¶9 In February 1992, the Vermilion County Board approved Brickyard’s request for an expansion of the vertical and lateral boundaries. The county board approved “a lateral and vertical expansion of permitted landfill boundaries, within existing property boundaries.” In October 1992, the Agency issued a supplemental permit, approving the “revised final contours within the approval granted by the Vermilion County Board” and final contours for unit 1 consistent with a drawing submitted with the permit application.

¶ 10 In May 1995, the Agency issued a permit for units 1 and 2 of the facility. The stipulated facts present show a condition of the permit was that a “separate berm shall be maintained between Unit I and Unit II which will allow independent groundwater monitoring.” The parties refer to this berm as the “wedge.”

¶ 11 On August 31, 2015, Brickyard filed a permit application, seeking to modify the permit to allow disposal of municipal waste in the wedge between unit 1 and unit 2. Brickyard made the following statement in its application:

“The total waste volume of the Brickyard Disposal and Recycling Landfill will be increased by approximately 1,010,000 yd.3 thereby providing a total Unit 2 waste volume of 15,210,000

-3­

yd.3 fill capacity as opposed to the currently permitted 14,200,000 yd.3 capacity. The documented estimated remaining life expectancy of Brickyard Disposal and Recycling Landfill is 16 years per the January 1, 2015[,] Annual Landfill Capacity Certification. With the addition of 1,010,000 yd. 3 of waste capacity in the ‘Zone A’ Fill Area the life expectancy of the landfill increases to approximately 21 years.”

¶ 12 The Agency, by a letter later dated September 24, 2015, informed Brickyard its application was incomplete due to lack of local siting approval under section 39(c) of the Act (415 ILCS 5/39(c) (West 2014)) and the absence of a new GIA.

¶ 13 On October 30, 2015, Brickyard responded to the Agency’s letter by submitting a supplemental application. In November 2015, the Agency concluded Brickyard had not corrected the errors of its initial filing and issued a final incompleteness determination. The Agency did not consider the technical merits of the permit application. Brickyard appealed to the Board.

¶ 14 Brickyard filed a timely petition to the Board, seeking review of the Agency’s permit determination. The Agency moved for summary judgment on its determination that Brickyard, by law, was required to provide local siting approval for its proposed expansion. Brickyard filed two motions for summary judgment, arguing its application was complete, as local siting approval was not required. Brickyard disputed the Agency’s finding that it was creating a new pollution control facility, arguing it was not seeking an expansion beyond the boundaries of its current facility. Brickyard further maintained it need not provide a new GIA.

¶ 15 The Board issued its opinion and order in November 2016. The Board granted

-4­

summary judgment to Brickyard on both grounds, finding the proposal to fill the wedge area with waste does not require new local siting approval as it is not a “new pollution control facility.” The Board concluded “a waste-free wedge was never required by the County” and the county “would have had no reason to expect anything but waste to be in what only later the Agency would delineate as a non-waste wedge.” The Board further found Brickyard’s GIA complete. The Board directed the Agency to perform a technical review of Brickyard’s permit application.

¶ 16 On the Agency’s motion for reconsideration, the Board affirmed its holding. The Board further observed the following: “Taking the Agency’s argument to its conclusion, the Agency would have the County consider whether to approve siting for waste disposal in the middle of an existing landfill under a 40-foot waste layer it already approved in 1992. This cannot be what the General Assembly intended.” The Board denied the motion to reconsider.

¶ 17 The Agency seeks direct review of the Board’s decision.

¶ 18 II. ANALYSIS

¶ 19 A. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Illinois Environmental Protection Agency v. Illinois Pollution Control Board, 2018 IL App (4th) 170144 (Ill. Ct. App. 2018).

2018 IL App (4th) 170144 (Illinois Environmental Protection Agency v. Illinois Pollution Control Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lee County, Illinois v. Lee County Landfill, Inc.
2022 IL App (4th) 220362-U (Appellate Court of Illinois, 2022)