Igoe Bros. v. National Surety Co.

169 A. 841, 112 N.J.L. 243, 96 A.L.R. 1422, 1934 N.J. LEXIS 265
CourtSupreme Court of New Jersey
DecidedJanuary 5, 1934
StatusPublished
Cited by19 cases

This text of 169 A. 841 (Igoe Bros. v. National Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Igoe Bros. v. National Surety Co., 169 A. 841, 112 N.J.L. 243, 96 A.L.R. 1422, 1934 N.J. LEXIS 265 (N.J. 1934).

Opinion

The opinion of the court was delivered by

Peksicie, J.

Appellant seeks to review an order and rule, each dated November 19th, 1932, made by the late Chief Justice G-ummere during the progress of the cause. The order denied appellant’s motion to dismiss the respondent’s cause *245 of action, summons in which was tested September 24th, 1932; and the rule permitted the respondent to consolidate its two causes of action against the appellant. The rule of consolidation provided that the allegations of the first cause should be known as “First Count” of the consolidated action and the allegations of the second cause should be known as “Second Count” thereof. Appellant also seeks to review the final judgment entered in favor of the respondent, after trial before Circuit Court Judge Smith, sitting without a jury.

The trial disclosed the following facts: On September 23d, 1930, Maggi & Schoonover entered into a contract with the New Jersey state highway commission for the furnishing of labor and materials to complete the undertaking described in the contract as “Passaic river bridge and approaches, Paterson to East Paterson, New Jersey, in section 7 of route 4 of the state highway system of New Jersey.” Pursuant to chapter 75 (Pamph. L. 1918, p. 203), the contractor furnished a bond with the appellant as surety thereon. It is in the usual statutory form. The respondent sold Maggi & Schoonover structural steel, which was actually incorporated in the undertaking contemplated by the contract, and upon which the admitted balance of $7,000 was due.

On January 11th, 1932, after the engineer in charge had reported that the undertaking was completed, the state highway commission adopted a resolution whereby “it approved acceptance of the contract with Maggi & Schoonover * * * and authorized final payment therein when in order.” Respondent informed of that resolution, served a statement of its claim on the surety, on March 26th, 1932, and on April 12th, 1932, instituted suit. On February 2d, 1932, the state highway commission passed a resolution rescinding its action of January 11th, 1932, and instead thereof approved “of the acceptance of the completed work on this contract of the making of semi-final payment thereof less than one hundred and twenty-five per cent, of the value of the uncompleted work which cannot be performed until spring.” It appeared that some seeding, &c., that had not been done and could not bo done until spring, necessitated the foregoing action on the *246 part of the state highway commission. Thereafter, on July 5th, 1932, the state highway commission again adopted a resolution and “approved of final acceptance of the completed work * * * and authorized the making of final payment thereon when the necessary formalities have been observed.” A dilemma faced the respondent. It was in a quandary. What was the actual date of acceptance ? Unwilling, and properly so, to subject itself to the consequences of the uncertainty thus created, through no act or fault of its own, its counsel served the surety a second statement of its claim on August 2d, 1932, and brought a second suit against the appellant on September 24th, 1932. Appellant filed an affidavit of merits to this second suit and thereafter noticed respondent on a motion to dismiss the second cause on the ground of the pendency of the first cause of action- — -for the same cause and between the same parties. Respondent countered with a motion for a consolidation of the two suits with the results already indicated. Was the consolidation of the two suits erroneous ? We think not.

As we understand the contention of the appellant, it is that there is but a single right upon which respondent could predicate its action, and having sued under appellant’s bond, in the first suit, it could not, during the pendency of that suit, bring another action upon the same bond, based on the same subject. Ap.pellant summarizes its contention on this point as follows:

“If a prior action on the same bond for the same claim, as between the same parties, is not a bar to the second action, then by the same token a litigant in doubt of the date of acceptance might well bring fifty actions in the trembling hope that one of them might contain the proper date of acceptance. The common law system did not tolerate such practice.”

To this contention we think that it might well be observed that since the right of the respondent to sue is based on the statute (Warren Brothers Co. v. Hartford, &c., Co., 102 N. J. L. 616 (at p. 618); see Skillman v. United States Fidelity, &c., Co., 101 Id. 511), and the statute makes that right de *247 pend upon certain proceedings being taken with reference to the date of acceptance of the work; then if the body, as in this instance, the state highway commission, would pass fifty resolutions of acceptance and forty-nine of revocation it may well be that a claimant would be obliged to go through the formalities of suing on each occasion, otherwise a law suit regarding the subject-matter might well be worthless. It might indeed be purely a matter of chance. Technical rules must yield to practical requirements. Appellant’s answer shows a rather evasive tendency, or a lack of knowledge on appellant’s part as to when it regarded that the state highway commission had actually accepted the work, for its answer to the first count set out that the contract was accepted on some date other than January 11th, 1932, and its answer to the second count set out that the contract was accepted on some day other than July 5th, 1932, and then when compelled by a demand for particulars to recite on what other day than January 11th it answered July 5th, and when compelled to state on what other date than July 5th it answered January 11th. Appellant, of course, had a right to present inconsistent defenses. The respondent also had the privilege or rights of setting out its cause of action and base it on the two different dates of acceptance. The actual date of acceptance could not be and was not determined until trial. The suits were thus as though they were in the alternative. If respondent had limited its cause of action to one or the other day of acceptance it might well have been caught in the position of the court finally determining that the date of actual acceptance was not the date elected by the respondent. It therefore elected to sue on each date of the alleged acceptance. It was a precautionary act. It proved to be a wise act. The statute was enacted primarily for the protection of the public body and secondarily as an “additional obligation” for the protection of materialmen, &c. Franklin Lumber Co. v. Globe Indemnity Co., 102 Id. 9; affirmed, Ibid. 715. A dismissal of either suit before trial might have resulted in a denial of justice. The learned and discerning late Chief Justice Gum-mere did the eminently sensible and proper thing in con *248 solidating the two suits. He was fortified by precedent. Den v. Kemble, 9 Id. 335; Metropolitan Casualty Insurance Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlantic City Casino Ass'n v. Kimmelman
499 A.2d 1049 (New Jersey Superior Court App Division, 1984)
Bankers Trust Co. v. Woltz
326 N.W.2d 274 (Supreme Court of Iowa, 1982)
Nitchals v. Williams
590 P.2d 582 (Supreme Court of Kansas, 1979)
Gilbert A. Cuneo v. Donald H. Rumsfeld
553 F.2d 1360 (D.C. Circuit, 1977)
Liberty Mutual Insurance v. Home Insurance Indemnity Co.
371 A.2d 1171 (Supreme Court of New Hampshire, 1977)
Jeffcoat v. Highway Contractors, Inc.
1972 OK CIV APP 5 (Court of Civil Appeals of Oklahoma, 1972)
Fidalgo Island Packing Co. v. Phillips
149 F. Supp. 260 (D. Alaska, 1957)
Goldenberg v. Sebersky
105 A.2d 700 (New Jersey Superior Court App Division, 1954)
State v. Otis Elevator Co.
95 A.2d 715 (Supreme Court of New Jersey, 1953)
Paul H. Jaehnig, Inc. v. Standard Acc. Ins. Co.
87 A.2d 558 (New Jersey Superior Court App Division, 1952)
In Re Application of Wellhofer
83 A.2d 827 (New Jersey Superior Court App Division, 1951)
John S. Westervelt's Sons v. Regency, Inc.
70 A.2d 767 (Supreme Court of New Jersey, 1950)
Beneficial Industrial Loan Corp. v. Smith
170 F.2d 44 (Third Circuit, 1948)
Alexander v. Manza
34 A.2d 11 (Supreme Court of New Jersey, 1943)
Fagliarone v. Consolidated Film Industries, Inc.
26 A.2d 425 (Hudson County Circuit Court, N.J., 1942)
Savitt v. L. & F. Construction Co.
8 A.2d 110 (Supreme Court of New Jersey, 1939)
Feinsod v. L. & F. Construction Co.
4 A.2d 692 (Essex County Court, 1939)
Bruin, Exr. v. Leveline
9 N.E.2d 895 (Ohio Court of Appeals, 1936)
Robinson v. Jackson
187 A. 918 (Pennsylvania Court of Common Pleas, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
169 A. 841, 112 N.J.L. 243, 96 A.L.R. 1422, 1934 N.J. LEXIS 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/igoe-bros-v-national-surety-co-nj-1934.