IEA Renewable Energy, Inc. v. Permian Basin Materials LLC D/B/A PB Materials Holdings, Inc.

Court of Appeals of Texas·Decided February 2, 2021·No. 07-20-00082-CV·Published

Opinion

In The

Court of Appeals

Seventh District of Texas at Amarillo

No. 07-20-00082-CV

IEA RENEWABLE ENERGY, INC., APPELLANT V.

PERMIAN BASIN MATERIALS LLC D/B/A PB MATERIALS HOLDINGS, INC., APPELLEE

On Appeal from the 237th District Court Lubbock County, Texas

Trial Court No. 2018-530,583, Honorable Les Hatch, Presiding

February 2, 2021

MEMORANDUM OPINION

Before QUINN, C.J., and PARKER and DOSS, JJ.

Wind turbines and concrete are the foundation of this appeal. IEA Renewable Energy Inc. (IEA) builds the former and Permian Basin Materials LLC (PB) pours the latter. And, in furthering each other’s business, IEA contracted with PB to pour the base and pedestal of a particular wind turbine as part of the General Electric (GE) Elsie Project. Part of PB’s charge was to derive a concrete mix meeting certain strength and alkali-silica reaction (ASR) levels required by project engineers. Those levels differed between the base and pedestal. While PB had little difficulty deriving the requisite formula for the

base, the same was not true concerning the pedestal. Its initial formula met the strength requirement, but not the ASR. Nonetheless, IEA urged PB to continue its efforts to derive a satisfactory formula while knowing that the requisite ASR test period of 16 days would exceed previously designated pour dates. It also agreed to pay for the additional ASR testing costs to be incurred by PB and began work on developing its own formula satisfying the ASR parameters. The latter was done with the assistance of PaveTex, the entity PB used to conduct the tests. Apparently, PB gave IEA permission to contact PaveTex directly. And, in communicating with each other, IEA and PaveTex compiled a mix deemed acceptable. That mix consisted of the mix developed by PB but with the addition of 5% more fly ash. Indeed, the percentage of fly ash (20%) utilized mirrored that included in PB’s formula for the 5,000 psi base, and IEA was so certain it would work, it opted not to submit the mix to ASR testing. PB too came upon a 6,500 psi mix tested to be sufficiently nonreactive (“innocuous” for purposes of ASR testing). Yet, IEA opted to use its own concoction and directed PB to pour it. PB complied, and the base and pedestal were poured.

PB sought payment for its work, and IEA responded by claiming breach of contract.

The contractual defaults underlying the claim included PB’s purported failure to abide by the originally scheduled pour date and to apprise IEA of the difficulties it encountered. The claims and counterclaims of the parties were submitted to a jury, which ultimately awarded PB recovery from IEA. The latter appealed and urged through its multiple issues that the evidence did not support the jury’s verdict. We affirm.

As summarized by IEA: “[t]he jury found that both parties breached the contract, that IEA breached first, that PB’s breach was excused, and that IEA’s breach was not

excused. None of these findings are supported by legally or factually sufficient evidence.” The standards of review we utilize in addressing this argument are discussed in Crosstex N. Tex. Pipeline, L.P. v. Gardiner, 505 S.W.3d 580 (Tex. 2016), and City of Keller v. Wilson, 168 S.W.3d 802 (Tex. 2005). Before applying them to address the issues, we make these preliminary observations.

First, the cause was submitted via oral argument. During same, the parties generally conceded that both breached their respective obligations in some way. 1 The main issue, therefore, devolves into who breached first.2 Second, who breached first, though, is not necessarily dispositive for the jury found that the PB’s failure to comply with the accord was “excused” while IEA’s was not. Logically, then, if the jury’s decision to excuse PB from its defaults has the support of legally and factually sufficient evidence, then it does not matter if PB breached first. This is so because there would only be one breach that could be the subject of recovery, and that would be IEA’s. So, initially assessing whether the jury had sufficient evidence upon which to excuse the failures of PB may avoid extended exposition, and, consequently, we address that first.

The pertinent jury question and instruction submitted by the trial court read:

Was Defendant PB’s failure to comply excused?

Failure to comply by Defendant PB is excused if compliance is waived by Plaintiff lEA.

Waiver is the intentional surrender of a known right or intentional conduct inconsistent with claiming the right.

1 The jury found that PB breached the agreement in failing to 1) “[p]rovide the concrete in

accordance with the project schedule”; 2) “[i]mmediately notify Plaintiff lEA of any actual or potential delays”; and 3) “[a]dvise . . . IEA of measures being taken to avoid or reduce delays.” So, too did it find that IEA breached the agreement but was not asked to specify the way the company did.

2 According to the jury, IEA failed to “comply with the Agreement” first.

Failure to comply with an agreement is excused if a different performance was accepted as full satisfaction of performance of the original obligations of the agreement.

Failure to comply by Defendant PB is excused if the following circumstances occurred:

1. Plaintiff lEA

a. by words or conduct made a false representation or concealed material facts, and

b. with knowledge of the facts or with knowledge or information that would lead a reasonable person to discover the facts, and

c. with the intention that Defendant PB would rely on the false representation or concealment in acting or deciding not to act; and

2. Defendant PB

a. did not know and had no means of knowing the real facts and

b. relied to its detriment on the false representation or concealment of material facts.

As can be seen from this, excuse had several aspects, those being waiver, acceptance of alternate performance, and estoppel. That said, we turn to the evidentiary record before us.

IEA formally placed its “order” for concrete to be used in the base and pedestal of the foundation on November 8, 2017, according to the initial purchase order (PO). The base was to withstand a “psi” (pound-force per square inch) of 5,000 psi while the pedestal was to withstand 6,500 psi. The PO also mentioned an “expected” date of performance as December 15, 2017. PB had a pre-existing mix or recipe for concrete meeting 5,000 psi. It did not have one meeting 6,500 psi, had to formulate it, and represented same to IEA. Its initial attempt began by the end of November and was submitted for testing.

The PO was revised by IEA and sent to PB on November 29th. It retained the “expected” delivery date of December 15th and also included, among other things, a project schedule. Per that schedule, the period within which preliminary items for the foundation (e.g., “conduit/grounding”) would be procured ended as late as December 20th, while the “Foundation As Builts” date (or date for completion of the foundation) was January 18, 2018. The schedule said nothing of a specific date upon which the concrete for the foundation would be poured by PB. Nevertheless, IEA selected a December 22nd date, despite the December 15th “expected” date mentioned in the PO.

Again, PB’s effort to formulate the necessary pedestal mix had begun before the revised PO was sent. According to a PB representative, trial batches for the 6,500 psi were prepared on November 27th and 28th. The ensuing tests mandated by the engineers controlling the project required a 28-day testing period. Within that period both strength and ASR testing were to be performed. Those tests began around December 4, 2017, and IEA knew of this. Given the need for such a lengthy testing period, the pour date was then moved by IEA to January 4, 2018, or 14 days before the January 18th “Foundation As Builts” date accompanying the modified PO.

Free access — add to your briefcase to read the full text and ask questions with AI

IEA Renewable Energy, Inc. v. Permian Basin Materials LLC D/B/A PB Materials Holdings, Inc., (Tex. Ct. App. 2021).

IEA Renewable Energy, Inc. v. Permian Basin Materials LLC D/B/A PB Materials Holdings, Inc. (IEA Renewable Energy, Inc. v. Permian Basin Materials LLC D/B/A PB Materials Holdings, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Carpet Services, Inc. v. GEORGE A. FULLER CO. OF TEXAS, INC.
802 S.W.2d 343 (Court of Appeals of Texas, 1990)
Aguiar v. Segal
167 S.W.3d 443 (Court of Appeals of Texas, 2005)
George A. Fuller Co. v. Carpet Services, Inc.
823 S.W.2d 603 (Texas Supreme Court, 1992)
Jernigan v. Langley
111 S.W.3d 153 (Texas Supreme Court, 2003)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Enchilada's Northwest, Inc. v. L & S Rental Properties
320 S.W.3d 359 (Court of Appeals of Texas, 2010)
Laredo Hides Co., Inc. v. H & H Meat Products Co., Inc.
513 S.W.2d 210 (Court of Appeals of Texas, 1974)