Ideal Wrench Co. v. Garvin Machine Co.

92 A.D. 187, 87 N.Y.S. 41
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 15, 1904
StatusPublished
Cited by4 cases

This text of 92 A.D. 187 (Ideal Wrench Co. v. Garvin Machine Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ideal Wrench Co. v. Garvin Machine Co., 92 A.D. 187, 87 N.Y.S. 41 (N.Y. Ct. App. 1904).

Opinions

Ingraham, J.:

The action is to recover damages caused by the breach of a contract for the manufacture by the deféndant of a tool called the “Ideal Wrench.” Upon an appeal from a judgment entered upon a dismissal of the complaint on a former trial it was held that- there was a breach of the contract by the defendant which, in the absence of other proof of damage, authorized the recovery of $500 deposited with the defendant which was to be applied on the last payment. It was also intimated in the opinion that the plaintiff might be , entitled to recover other damages depending on the proof upon a new trial1 (65 App. Div. 235). Upon the new trial the court submitted the case to. the jury, who found a verdict for the plaintiff for $2,000. . .

The contract, dated March 6, 1897, was between Walter 0. Stokes (plaintiff’s assignor) of the first part, and the defendant ¿f the second part. It provided that for and in consideration of the sum of $500, the receipt of which was acknowledged, the defendant agreed to “ build and deliver” 10,000 wrenches known as the “ Ideal Pattern,” a mould of which was to be furnished Stokes'; that 7,500 of said wrenches, blue finish, were to he manufactured at forty cents each, and 2,500 full nickel finish at fifty cents each, pay[189]*189ment for which was to be made within thirty days of delivery, less $500 advanced, which was to be applied on the last payment. The wrenches were to be made in a first-class manner, in every way equal to that of the model submitted. The complaint alleges the making of this agreement, the assignment of the contract and of all Stokes* rights and claims to damages thereunder to plaintiff; that Stokes and the plaintiff have made all payments and performed all the acts which by the terms of the said contract were to be made and performed by Stokes, but that the defendant corporation has neglected, failed and refused to carry out said contract or to perform the acts therein by it agreed to be performed; that the defendant has failed and refused to build or deliver any wrenches made in a first-class manner, and has failed to build or deliver any wrenches made in every way equal to that of the model, although such model was duly furnished to the defendant; that the defendant failed and refused to deliver any wrenches within a reasonable time, and not. until months after the execution of said contract, although frequently and urgently requested to do so; that the defendant, after the month of May, 1897, from time to time and at long intervals, until the month of October, 1897, delivered wrenches in small quantities, amounting in the aggregate to about 2,000 wrenches, and since said month of October, 1897, has failed, refused and neglected to tender or deliver any wrenches meeting the requirements of said contract; that all the wrenches tendered or delivered by the defendant were weak and defective, and neither made in a first-class manner nor equal to that of said model; that large numbers of said wrenches of the number delivered as aforesaid were delivered in turn and distributed by said Stokes or said plaintiff, and broke with ordinary use in the hands of intending purchasers, and were returned by such purchasers to said Stokes or the plaintiff to the great damage and detriment of their business, and the defendant failed to' deliver any wrenches, the parts of which were interchangeable, to the great detriment and loss of plaintiff; that by reason thereof and of the unreasonable delay in the delivery of wrenches, the failure to. deliver any wrenches in accordance with the contract, the failure and neglect to deliver more than 2,000 wrenches in all, and the failure to make the tools necessary for the manufacture of said wrenches, the defendant has caused damage to Stokes and the plaintiff.

[190]*190The answer admits the making of the contract; admits that the defendant delivered .to the plaintiff about 2,000 wrenches in pursuance thereof, and denies the other allegations of the complaint; and for a separate defense it alleges, that after the execution of the contract' the plaintiff’s assignor requested a modification thereof, wishing all the wrenches to be full nickel wrenches; that said Stokes was there and then informed by said defendant that the defendant had already made up and caused to be cast the said 7,500 wrenches which were to be completed in blue or plain finish, and in order to change the style of finish, and to complete them in full nickel finish instead of the blue finish, as called for by the contract, it would be necessary to grind certain parts of the wrenches so as to receive the nickel plate and that some of the parts of the wrenches would be necessarily somewhat thinner than the sample; that thereupon the said Stokes changed the contract and the said order, and directed the defendant to go on and complete the wrenches so cast, and make them up in full nickel finish instead of the blue finish, or plain finish, as called for by the contract; that the defendant, acting under the said instructions, proceeded to complete the wrenches as directed by Stokes; and that if the wrenches tendered to the plaintiff, and the wrenches so delivered, were different or in any particular varied from the samples as called for by the contract, it was not the fault of the defendant, but was the fault of the said Stokes.

TJpon the trial Stokes (plaintiff’s assignor) testified that prior to the making of the contract the defendant’s president stated that the wrenches called for by the contract would be manufactured and delivered in six to eight weeks, and introduced in evidence a letter from the defendant dated February 5, 1897, in which it was said : “ We are in excellent shape to take hold of a job of this character, and can make deliveries in about eight to ten weeks from receipt of .order.” Subsequently on the 6th of March, 1897, the contract in question was executed and Stokes paid $500 to the defendant, and subsequently paid to defendant for the tools manufactured by it $1,500. • Stokes further testified that the dates of the delivery of wrenches were May twenty-second, one wrench; May twenty-fourth, eight wrenches; June second, sixty wrenches; that ■ the ' first delivery in quantity was on August sixth of five hundred and twelve wrenches, and so on down to October when it would seem [191]*191that the last delivery of five hundred wrenches was made; that on June seventh there were returned to the defendant twenty-nine wrenches; that no wrenches were received from the defendant after November ninth; that neither the $500 paid upon the execution of the contract nor the $1,500 paid by the plaintiff or Stokes to the defendant have ever been repaid; that the plaintiff also paid to the defendant the'net sum of $616 for the wrenches delivered. Upon cross-examination Stokes testified that he had a wooden model of the wrench at the time he went to see the defendant; that he submitted this wooden model to the defendant, who stated that they could improve upon it, and that they subsequently made an improved model, which was approved by Stokes. There was also the testimony of an engineer who tested the wrenches furnished by the defendant under this contract, and who testified to the defects and variations from the model.

There can be no question, I think, bnt that the verdict of the jury that there was a breach of the contract by the defendant was justified, and the only substantial question is as to the correct measure of damages. This was, I think, a contract to manufacture and deliver, and not a sale by sample. When the. contract was made there were no goods in existence, a sample of which was produced and upon which a sale was made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neverfail Lighter Co. v. Blum
201 A.D. 153 (Appellate Division of the Supreme Court of New York, 1922)
Marx v. Locomobile Co. of America
82 Misc. 468 (City of New York Municipal Court, 1913)
Finkelstein v. Selwitz
79 Misc. 28 (Appellate Terms of the Supreme Court of New York, 1913)
Crane Co. v. Collins
103 A.D. 480 (Appellate Division of the Supreme Court of New York, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
92 A.D. 187, 87 N.Y.S. 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ideal-wrench-co-v-garvin-machine-co-nyappdiv-1904.