Ideal Cement Co. v. The Tug Tickfaw

143 F. Supp. 904, 1956 U.S. Dist. LEXIS 3056
CourtDistrict Court, E.D. Louisiana
DecidedSeptember 7, 1956
DocketNo. 533
StatusPublished

This text of 143 F. Supp. 904 (Ideal Cement Co. v. The Tug Tickfaw) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ideal Cement Co. v. The Tug Tickfaw, 143 F. Supp. 904, 1956 U.S. Dist. LEXIS 3056 (E.D. La. 1956).

Opinion

BENJAMIN C. DAWKINS, Sr., District Judge.

February 20, 1954 this libel was filed against the two tugs above named -for damages, allegedly done to the barge Ideal Cement No. 7 through negligence1 of the captains and crews of the tugs in towing said barge from Baton Rouge to Newellton, Louisiana by way of the Mississippi River.

Some six months later August 27, 1954 Baton Rouge Coal & Towing Company, as the owner of the tugs, filed its petition under the 56th Rule in Admiralty, 28 U.S.C.A. impleading T. L. James & Company, setting forth the contract relations2 between them, but denying, negligence and liability» It admitted it had towed the barge under said agreement with James & Company and prayed that the demand be rejected but if claimant were held liable it have a decree over' and against James & Company. On the same day (August 27, 1954), claimant answered the libel, denying generally and specially the charge of negligence, but admitting the Tug Walker No. 9 “came to fetch the barge” in question from Baton Rouge to Burn Landing on Lake Palmyra near Newellton, Louisiana; and that the “flotilla” was made up for pushing. It further admitted the barge had stranded and described the circumstances.3

September 10, 1954 libelant answered the interpleader denying authority of James & Company to make any agreement that the barge Ideal Cement No. 7 should be towed at owner’s risk.

June 14, 1955 James & Company answered admitting claimant undertook “the towage of the barge * * * pursuant to an arrangement between Re[906]*906spondent and Claimant”, but denied that in engaging claimant for the tow, it had acted as agent of anyone. Thereafter on September 8, 1955 James & Company filed its exception to the interpleader admitting claimant had, on June 1, 1958 written a letter 4 to the exceptor attempting to relieve itself from liability for its own negligence, to which exceptor acceded, but that the Supreme Court in its decisions handed down on May 16, 1955 in the cases of Bisso v. Inland Waterways Corporation, 349 U.S. 85, 75 S.Ct. 629, 99 L.Ed. 911, 1955 A.M.C. 899; Boston Metals Co. v. The Winding Gulf, 349 U.S. 122, 75 S.Ct. 649, 99 L.Ed. 933, 1955 A.M.C. 927; and United States v. The S. S. Christopher Gale v. Nielson, 349 U.S. 129, 75 S.Ct. 654, 99 L.Ed. 939, 1955 A.M.C. 935, had held similar stipulations in towage contracts invalid and contrary to public policy. (Emphasis added.)

After these decisions claimant on March 29, 1956 filed its “supplemental and amended answer” alleging that the barge in question had been “consigned by libelant to the Louisiana Department of Highways c/o James & Company” under a straight bill of lading prepared and presented by libelant, signed by the Master of the Tug Walker No. 9 under which the barge and its cargo moved as freight, subject to Section 3 of The Harter Act, 46 U.S.C.A. § 192 and to all the terms and conditions of said bill of lading,5 which also relieved it from liability or negligence of its agents and employees. Further that claimant had used due diligence to make the tug seaworthy, it was properly manned, equipped and supplied, and if there was any negligence, which it denied, the same was due to negligent navigation of the tug by her master.

Pursuant to this change of position and on motion of the claimant on April 16, 1956 Judge Christenberry signed a decree prepared and presented by claim[907]*907ant’s attorneys dismissing James & Company from the case.6

March 27, 1956 the parties stipulated certain facts including amount of damage if recovery was had and agreed that the court might render a final decree without further hearing.

It is conceded that the Tug Tickfaw was not involved.

The first question is, of course, was the arrangement between James & Company and the claimant by which the former’s cement was to reach Newellton, one of towage or of carriage ? There is apparently no doubt but that at the inception the parties in their pleadings treated the arrangement as towage.

James & Company chartered the barge Ideal Cement #7 in which to transport the cement it had bought from the libelant, to the point where it was to be used in performing a construction contract with the State Highway Department, as it had been doing with other barges for some time, under the same contract, and the claimant’s sole obligation was to tow the barges thus furnished with their cargo to the landing near the work being done. In fact the latter’s name and the business in which it was engaged, its manner of operations etc. point rather clearly to the fact that the arrangement was primarily one of towing the barges, either empty or with cargo, and not one for transporting or carrying freight as ordinarily understood. And it can hardly be denied that libelant, under the charter, warranted the seaworthiness of its said barge, and had the cargo been lost due to defects in the barge alone, Ideal Cement Company or its barge would have been sued by James & Company, not the claimant, for the simple reason that the latter had nothing to do with furnishing the barge and had no information as to its condition of repair. Plainly all the documents and testimony of the witnesses show that the agreement of James & Company with claimant was to pick up the barges already loaded and to tow them to Burn Landing. Until this last shipment, it is conceded there was no privity of contract between it and libelant, and any change in that condition must depend upon this purported bill of lading, which the Captain of the tug signed. The original contract between James & Company and the claimant could not be changed from one of towage so as to bind the former without its consent. All Claimant’s tugs used were employed in the same manner by James & Company, who paid the towage presumably, as well as the fee for the charter and the price of the cement to the libelant. The two contracts of charter and towage were entirely separate both in their nature and as to parties, although James & Company was a party to both. Its rights against libelant, in case of loss, rested upon an entirely different basis i. e. the condition of the barge and its seaworthiness while as to claimant they would depend on the degree of care used.

Ordinarily, if the undertaking is one of carriage, the carrier furnishes the vehicle of carriage, its own bill of lading [908]*908with such, terms as it provides, within the range of limitations imposed, either by law or <the governing State of Federal Commission. Its customers may, for convenience, have in their possession blank forms of bills of lading, but they are usually supplied by the carrier. For some reason, not entirely clear, libelant had this document prepared with its own name printed therein, which the Captain of the tug signed, as he would have, according to the president of his company, any other form which would serve as a receipt for the tow.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stevens v. the White City
285 U.S. 195 (Supreme Court, 1932)
Bisso v. Inland Waterways Corp.
349 U.S. 85 (Supreme Court, 1955)
Boston Metals Co. v. the Winding Gulf
349 U.S. 122 (Supreme Court, 1955)
United States v. Nielson
349 U.S. 129 (Supreme Court, 1955)
Stall & McDermott v. The Southern Cross
196 F.2d 309 (Fifth Circuit, 1952)
The Ernest H. Meyer
84 F.2d 496 (Ninth Circuit, 1936)
The Silver Palm
94 F.2d 754 (Ninth Circuit, 1937)
The George Hughes
183 F. 211 (Second Circuit, 1910)
The Florence
88 F. 302 (N.D. New York, 1898)
The Nathan Hale
91 F. 682 (S.D. New York, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
143 F. Supp. 904, 1956 U.S. Dist. LEXIS 3056, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ideal-cement-co-v-the-tug-tickfaw-laed-1956.