Idaho Trust & Savings Bank, Ltd. v. Ridenbaugh

161 P. 868, 29 Idaho 647, 1916 Ida. LEXIS 114
CourtIdaho Supreme Court
DecidedDecember 9, 1916
StatusPublished
Cited by1 cases

This text of 161 P. 868 (Idaho Trust & Savings Bank, Ltd. v. Ridenbaugh) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Trust & Savings Bank, Ltd. v. Ridenbaugh, 161 P. 868, 29 Idaho 647, 1916 Ida. LEXIS 114 (Idaho 1916).

Opinion

BUDGE, J.

On January 18, 1906, a judgment was rendered by the district court of the third judicial district (now the seventh judicial district), in and for Canyon county, in the case of Farmers’ Co-operative Ditch Company, Plaintiff, v. Riverside Irrigation District, Limited, W. H. Ridenbaugh et al., Defendants, by which .judgment there was assessed against defendants W. H. Ridenbaugh and A. Rossi the sum of $962.50, as the pro rata share to be borne by them of the total expense incurred by the state engineer of Idaho in making surveys under authority of the act of the legislature of March 11, 1903 (1903 Sess. Laws, pp. 223-252), in connection with said action, for use in determining the priorities of the users of water on the Boise river and for the purpose of fixing the duty of water.

The state engineer, in the course of making these surveys, and prior to the rendition of the judgment above mentioned, from time to time issued some 73 so-called certificates of indebtedness to persons furnishing services or supplies in connection with the surveys, and at the time of the commencement of the trial of this cause in the lower court plaintiff, Idaho Trust and Savings Bank, was the owner and in rightful possession of some 59 such certificates, which had been assigned to it by the original holders thereof; plaintiff Carl Maughmer was the owner and in rightful possession of 3 certificates, which had been issued to him; and the remaining 11 certificates were held by other parties.

The judgment of January 18, 1906, was appealed from by the Nampa & Meridian Irrigation District, and affirmed, in the case of Farmers’ Co-operative Ditch Co. v. Riverside Irr. Dist., 14 Ida. 450, 94 Pac. 761. Thereafter certain other defendants moved for a new trial, and their motion was [651]*651denied, and they appealed, and were granted a rehearing by this court for the “sole and only purpose of determining the duty of water on the two classes of land involved, . . . . namely, bench and bottom lands.” (Farmers’ Co-operative Ditch Co. v. Riverside Irr. Dist., 16 Ida. 525, 102 Pac. 481.)

On January 17, 1912, the Idaho Trust & Savings Bank, being the owner of 59 certificates assigned to it as aforesaid, brought suit against the defendant, who is the appellant here, to recover the amount of the judgment for costs entered against him for $962.50, with interest thereon. During the course of the trial of the action, nine of the eleven unpaid certificates held by other parties than the respondent were paid by the state engineer to the respective holders thereof. The amount of the two remaining certificates, held by other parties, together with interest thereon, was paid by the state engineer into court for the holders thereof, and 23 of the 59 certificates held by the Idaho Trust & Savings Bank were paid by the state engineer to said bank, so that at the termination of the action in the trial court 35 certificates were held by the Idaho Trust & Savings Bank and 3 certificates were held by Carl Maughmer, who was subsequently joined as plaintiff, and were the only remaining unpaid certificates representing indebtedness incurred by the state engineer covered by the judgment of January 18,1906. • The total amount of these certificates was $2,207.00, and interest thereon, while the judgment against the defendant was for $962.50 and interest.

The trial court found, in its findings of fact, among other things, that the parties to this action are the only parties in interest; that they were properly joined; that the pending hearing for the determination of the duty of water upon bench and bottom lands does not affect this action in any manner; that the parties plaintiffs are the legal and equitable owners of the judgment of January 18, 1906, and entitled to sue thereon; that the cause is not barred by the statute of limitations, and that the defendant Ridenbaugh is liable for the amount of the judgment of January 18, 1906, with interest thereon at seven per cent per annum from the date [652]*652thereof. Accordingly, on Janizary 18, 1915, judgment was entered in favor of plaintiff and against defendant for $962.50, with interest at the rate of seven per cent per annum from January 18, 1906, amounting in all to the sum of $1,568.88, together with interest on said sum from January 18, 1915, until paid, and plaintiff’s costs and disbursements amounting to $16.50.

This is an appeal from the judgment and order overruling a motion for a new trial.

For a reversal of this judgment, appellant assigns and relies upon thirty assignments of error. These assignments will be considered and discussed so far as is deemed necessary in connection with the four following contentions, which they are designed to support:

1. That the judgment sued upon is absolutely and ab initio void, as it runs in favor of no one, at best to no one who is a party to the action in which it was rendered.

2. That, granting the judgment is valid, the plaintiffs were neither parties to the judgment nor showed in themselves any interest therein by assignment or otherwise.

3. That there is a defect of parties, in that all persons holding state engineer’s certificates or otherwise having an interest in the judgment sued upon are not joined as parties in this action, or, if joined, have never been served with process.

4. That no action can be maintained upon the judgment sued upon, for the reason that it has been set aside by an order of this court sustaining the motion for a new trial in the action wherein it was entered.

The judgment of January 18, 1906, above mentioned, was for money due for services rendered by and under the directions of the state engineer, in accordance with the provisions of the act of the legislature of March 11, 1903 (1903 Sess. Laws, pages 249, 250, sec. 3-7).

The second paragraph of sec. 37, supra, provides:

“Whenever the State Engineer shall make such examination at the request of the court or a judge thereof, the actual cost of making such examination by the State Engineer or his assistant, and of preparing such maps and statement as [653]*653shown by sworn statement of snch costs prepared by such State Engineer, shall be paid by the persons interested in such suit for the determination of such priorities, the amount of such costs to be prorated by such court to thé persons whose rights have been adjudicated by such suit.....”

An examination of the record discloses the fact that the state engineer, acting under the order of the court made in pursuance to the above section of the Session Laws of 1903, had actually made an examination of the Boise river and the works diverting water therefrom.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
161 P. 868, 29 Idaho 647, 1916 Ida. LEXIS 114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-trust-savings-bank-ltd-v-ridenbaugh-idaho-1916.