Idaho Power v. New Energy Two & IPUC

CourtIdaho Supreme Court
DecidedJune 17, 2014
StatusPublished

This text of Idaho Power v. New Energy Two & IPUC (Idaho Power v. New Energy Two & IPUC) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Power v. New Energy Two & IPUC, (Idaho 2014).

Opinion

Docket No. 40882-2013

IDAHO POWER COMPANY, ) ) Boise, April 2014 Term Petitioner-Respondent, ) ) 2014 Opinion No. 49 v. ) ) Filed: June 17, 2014 NEW ENERGY TWO, LLC, an Idaho limited ) liability company, and NEW ENERGY ) Stephen W. Kenyon, Clerk THREE, LLC, an Idaho limited liability ) company, ) ) Respondents-Appellants, ) ) and ) ) IDAHO PUBLIC UTILITIES ) COMMISSION ) ) Intervenor-Respondent. ) )

Appeal from the Public Utilities Commission of the State of Idaho.

The order of the Public Utilities Commission is affirmed.

Angelo L. Rosa, Salt Lake City, Utah, argued for appellants.

Donovan E. Walker, Boise, argued for respondent Idaho Power Company.

Donald L. Howell, II, Deputy Attorney General, Boise, argued for respondent Public Utilities Commission.

EISMANN, Justice. This is an appeal from an order of the Idaho Public Utilities Commission holding that it had jurisdiction to decide whether the force majeure clauses in the Appellants’ contracts with Idaho Power Company excused them from their contractual obligations to have their power generation facilities constructed and in operation by specified dates in order to sell electricity to Idaho Power. We affirm the order of the Commission. I. Factual Background.

On May 24, 2010, Idaho Power entered into two Firm Energy Sales Agreements, one with New Energy Two, LLC, and the other with New Energy Three, LLC, under which Idaho Power agreed to purchase electricity from them that was to be generated by the use of biogas. The agreement with New Energy Two stated that the project would be operational on October 1, 2012, and the agreement with New Energy Three stated that the project would be operational on December 1, 2012. Both contracts were submitted for approval to the Idaho Public Utilities Commission, and it approved them on July 1, 2010. Each of the agreements contained a force majeure clause. By written notice dated September 28, 2012, New Energy Two and New Energy Three (collectively “New Energy”) informed Idaho Power that they were claiming the occurrence of a force majeure event, which was ongoing proceedings before the Public Utilities Commission. New Energy asserted that until those proceedings were finally resolved “the entire circumstance of continued viability of all renewable energy projects in Idaho is undecided” and that as a consequence “renewable energy project lenders are unwilling to lend in Idaho pending the outcome of these proceedings.” On November 9, 2012, and November 21, 2012, respectively, Idaho Power filed petitions with the Commission against New Energy Two and New Energy Three seeking declaratory judgments that no force majeure event, as that term was defined in the agreements, had occurred and that Idaho Power may terminate both agreements for the failure of the projects to be operational by the specified dates. The Commission ordered that the two cases be consolidated into a single proceeding. On December 27, 2012, New Energy filed a motion to dismiss both petitions on the ground that the Commission lacked subject matter jurisdiction to interpret or enforce contracts. After briefing from both parties, the Commission issued its order on March 5, 2013, denying New Energy’s motion to dismiss. The Commission’s order was an interlocutory order that is not appealable as a matter of right. New Energy filed a motion with this Court requesting a permissive appeal pursuant to Idaho Appellate Rule 12, and we granted the motion. New Energy then filed a notice of appeal.

2 II. Did the Commission Err in Holding that It Had Subject Matter Jurisdiction to Adjudicate Idaho Power Company’s Petitions?

The issue on appeal as stated by New Energy is “[w]hether the PUC has jurisdiction to adjudicate whether or not an event of force majeure excusing performance under certain contracts has occurred.” “Idaho case law indicates in general that contract interpretation is for the courts, not the Commission . . . .” McNeal v. Idaho Public Utilities Comm’n, 142 Idaho 685, 689, 132 P.3d 442, 446 (2006). However, this Court’s decisions “have been careful to use words such as ‘generally’ and ‘normally’ and also, to provide for exceptions to the norm,” id., and this Court has recognized several exceptions to the general rule. One exception is that the Commission has authority to interpret contracts where the parties have agreed to permit the Commission to do so. Bunker Hill Co. v. Washington Water Power Co., 98 Idaho 249, 252, 561 P.2d 391, 394 (1977); Afton Energy, Inc. v. Idaho Power Co., 111 Idaho 925, 929, 729 P.2d 400, 404 (1986) (recognizing this rule). Although we have not explained the basis of this exception, it is obvious. “Freedom of contract is a fundamental concept underlying the law of contracts and is an essential element of the free enterprise system.” Rawlings v. Layne & Bowler Pump Co., 93 Idaho 496, 499, 465 P.2d 107, 110 (1970). The parties to a contract can agree to the manner in which they will resolve disputes regarding the interpretation of their contract. Although they cannot require a third party to resolve their dispute, they can agree to permit a third party to do so. Each of the agreements in this case included as section 19.1 a provision stating, “All disputes related to or arising under this Agreement, including, but not limited to, the interpretation of the terms and conditions of this Agreement, will be submitted to the Commission for resolution.” The Commission held that by this provision, the parties had agreed to have the Commission resolve disputes regarding the interpretation of their agreements, including the meaning of the force majeure clause. New Energy does not even address section 19.1 in its briefing, nor does it dispute that the language of the provision would include determining whether the claimed force majeure was within the scope of the force majeure clause in the agreements. Therefore, the Commission did not err in holding that the interpretation of the agreements was within the scope of section 19.1.

3 The Commission also based its order upon decisions of this Court regarding the Commission’s statutory authority. The agreements in this case were executed pursuant to the Public Utility Regulatory Policies Act of 1978 (PURPA), and the biogas generation facilities to be constructed by New Energy were to be qualifying facilities (QFs) under that act. The Commission wrote as follows: We further find that there is a statutory basis for our jurisdiction in this matter. Just as in the case where QFs may bring complaints against utilities under PURPA (Afton I/III, 107 Idaho at 781, 693 P.2d at 427), the Commission is authorized under Idaho Code § 61-621 to hear complaints made by public utilities. As the Idaho Supreme Court noted in Afton I/III, Section 61-612 “gives the Commission jurisdiction to hear complaints against public utilities alleging violations of rules, regulations or any provision of laws; I.C. § 61-502 gives the Commission jurisdiction to determine reasonable rates, including rates collected under contracts; and I.C. § 61-503 gives the Commission power to investigate a single contract . . . .” 107 Idaho at 784, 693 P.2d at 430. The PPAs at issue in this case directly affect Idaho Power’s rates through the annual Power Cost Adjustment (PCA). Idaho Code § 61-502

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Energy Regulatory Commission v. Mississippi
456 U.S. 742 (Supreme Court, 1982)
Rawlings v. Layne & Bowler Pump Company
465 P.2d 107 (Idaho Supreme Court, 1970)
Empire Lumber Co. v. Washington Water Power Co.
755 P.2d 1229 (Idaho Supreme Court, 1988)
Afton Energy, Inc. v. Idaho Power Co.
729 P.2d 400 (Idaho Supreme Court, 1986)
Grever v. Idaho Telephone Company
499 P.2d 1256 (Idaho Supreme Court, 1972)
Bunker Hill Co. v. Washington Water Power Co.
561 P.2d 391 (Idaho Supreme Court, 1977)
McNeal v. Idaho Public Utilities Commission
132 P.3d 442 (Idaho Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Idaho Power v. New Energy Two & IPUC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-power-v-new-energy-two-ipuc-idaho-2014.