Idaho Irrigation Co. v. Pew

141 P. 1099, 26 Idaho 272, 1914 Ida. LEXIS 62
CourtIdaho Supreme Court
DecidedJuly 3, 1914
StatusPublished
Cited by7 cases

This text of 141 P. 1099 (Idaho Irrigation Co. v. Pew) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Irrigation Co. v. Pew, 141 P. 1099, 26 Idaho 272, 1914 Ida. LEXIS 62 (Idaho 1914).

Opinion

AILSHIE, C. J.

The complaint in this case is almost identical with the one in Idaho Irr. Co. v. Dill, recently decided by this court (25 Ida. 711, 139 Pac. 714), and the action is of the same nature. In that case the question presented was whether the lower court erred in sustaining a demurrer to the complaint upon the ground that the United States was a necessary party to the action, and upon that question this court reversed the court below.

By stipulation of counsel it was agreed that the contract which the plaintiff corporation made with the defendant in [274]*274this case was the same as in the Dill ease, the only difference being in the date, name of purchaser, description of the land, etc., which minor differences were admitted to be immaterial, and the contracts introduced in evidence in the Dill ease, including the contract and supplemental contract between the company and the state, were stipulated to be considered part of the record in this ease.

The defendant Pew,- the original purchaser, had assigned all his interest under the contract to the defendant Cornell, who alone appeared and demurred to the complaint. The lower court overruled the demurrer. Defendant elected to stand thereon and declined to plead further. The demurrer alleged that the complaint did not state facts sufficient to constitute a cause of action, and particularly in (1) that the plaintiff has not alleged that the irrigation system, which by the terms of the contracts set up in the complaint it agreed to construct, has been completed; (2) that the plaintiff has not alleged that the amounts sued upon and for which a lien is claimed are “the actual cost of reclamation (of the land described in the complaint) and reasonable interest thereon from the date of reclamation until disposed of to (an) actual settler (s) ”; (3) “that no valid lien can be created under existing law against either land or water, as is attempted to be done under the allegations of the complaint herein. ’ ’

1. We do not think it necessary for the plaintiff to allege that the entire reclamation system has been completed, in an action to foreclose a lien against a single purchaser of a water right under the Carey Act. The essential thing that concerns the particular land owner and purchaser of the water right is whether or not the reservoir and main canal have been so far completed as to enable the company to regularly and permanently supply him with water for the irrigation of his land, and that the company has commenced and continues to do so. The amendment to the Carey Act (29 U. S. Stats, at L., p. 435), after authorizing the state to create the lien against the land for the cost of reclamation, continues as follows: “And when an amply supply of water is actually furnished in a substantial ditch or canal, or by artesian wells or reser[275]*275voirs, to reclaim a particular tract or tracts of such lands, then patents shall issue for the same to such state without regard to settlement or cultivation.” This language explicitly refers to a “particular tract,” implying that the issuance of patent for any one tract is not dependent on the completion of the whole reclamation system, but on the actual furnishing of a permanent supply of water to that “particular tract.” The government then considers that the contract has been executed on the side of the state so far as that tract is concerned, and parts with its title accordingly, and it would certainly seem that the settler is assured of a permanent water supply when the “particular tract” has been so far reclaimed in the view of the government of the United States as to entitle the state and himself to a patent therefor. The fact that some other land owner and purchaser of a water right is not yet receiving water, or that the system has not been so far completed as to furnish another with water, does not justify one who has and is receiving a permanent and continuous supply of water for the irrigation of his land in refusing to pay for it. We find no provision in the Carey Act, nor in the laws of this state, nor in the contracts in evidence, which requires that the reclamation works shall be entirely completed before any of the deferred payments shall mature. If, as a matter of fact, a company that is seeking to foreclose such a lien has not made water permanently available to the land in question, and available in sufficient quantities and seasons to comply with the provisions of the contract, such defense will always be open to the settler.

A similar question arose on rehearing in the recent case of Childs, v. Neitzel, ante, p. 116, 141 Pac. 77, in which the contract with the settler also contemplated the payment for water rights by annual instalments, and the court said:

“We did not mean to hold in the original opinion that the annual instalments provided for by said water contracts did not become due and payable until the entire system was completed; but when the system was so far completed as to make water permanently available for any particular user for all [276]*276seasons, the instalments* agreed to be paid by the user would become due and payable in accordance with the terms of the contract. Then he has no reason to complain of lack of water for other land owners, because he has water available for the irrigation of his land.”

There are practical reasons which Congress doubtless had under consideration when by the 1896 amendment to the Carey Act it specified the character of completion necessary in order to obtain patent, with reference to “a particular tract or tracts of such lands, ’ ’ instead of making it apply to all the lands embraced in the project. For instance, a Carey Act project may include several distinct segregations or units of land to be reclaimed, but all of which are covered by the one contract with the state. The entire completion of such a system may extend over a compáratively long period. An ample supply of water may be permanently furnished to one or more of these units for years before other portions of the system are finished. It would manifestly be a great financial burden upon the enterprise to exact from its promoters the condition that no deferred payments should be collected nor liens securing them attach until all lands on all the tracts embraced in the project were permanently supplied with water. Such a requirement, besides being unnecessary to protect a settler who was already in possession of what he had contracted for, would obviously increase the cost of the enterprise to the settler by making the investment less attractive to the capitalist, who would require a higher rate of interest, or its equivalent, to compensate him for the increased risk.

2. The next question raised by defendant’s demurrer is that the complaint does not allege that the amounts sued for, and for which a lien is sought to be foreclosed, are the actual cost of reclamation of the land described in the complaint and reasonable interest thereon. The language of the 1896 amendment to the Carey Act on this point is as follows: “A lien or liens is hereby authorized to be created by the state . . . . against the separate legal subdivisions of land reclaimed, for the actual cost and necessary expenses of reclama[277]*277tion and reasonable interest tbereon from the date of reclamation until disposed of to actual settlers.” This “actual cost of reclamation” in any given case was evidently intended by the act to be determined by the state, and that determination would at least constitute prima facie

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Side Canal Co. v. Idaho Farms Co.
96 P.2d 232 (Idaho Supreme Court, 1939)
Columbia Trust Co. v. Eikelberger
245 P. 78 (Idaho Supreme Court, 1925)
Aberdeen-Springfield Canal Co. v. Bashor
214 P. 209 (Idaho Supreme Court, 1923)
Craig v. Smith
196 P. 1038 (Idaho Supreme Court, 1921)
Idaho Irrigation Co. v. County of Lincoln
152 P. 1058 (Idaho Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
141 P. 1099, 26 Idaho 272, 1914 Ida. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-irrigation-co-v-pew-idaho-1914.