Id 100250022 v. BP Exploration & Production, Inc.

847 F.3d 167, 2017 WL 365495, 2017 U.S. App. LEXIS 1358
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 25, 2017
Docket16-30258
StatusPublished
Cited by20 cases

This text of 847 F.3d 167 (Id 100250022 v. BP Exploration & Production, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Id 100250022 v. BP Exploration & Production, Inc., 847 F.3d 167, 2017 WL 365495, 2017 U.S. App. LEXIS 1358 (5th Cir. 2017).

Opinion

PER CURIAM:

Alabama Coastal Radiology, P.C. (“ACR”), filed a claim under the Business Economic Loss (“BEL”) Framework of the Deepwater Horizon Economic Loss and Property Damage Settlement Agreement. The Court Supervised Settlement Program (“CSSP”) denied the claim, and an Appeal Panel affirmed the CSSP’s denial. ACR requested that the district court grant review of the CSSP’s decision, but ACR’s request was denied. ACR now appeals the district court’s denial of discretionary review. We AFFIRM.

I.

This case relates to the Deepwater Horizon Economic Loss and Property Damage Settlement Agreement (“Settlement Agreement”), which was reached in the wake of the 2010 Deepwater Horizon oil spill incident. 1 As a result of its obligations under the Settlement Agreement, BP has distributed millions of dollars in damages to affected entities. In re Deepwater Horizon, 910 F.Supp.2d 891, 903-04 (E.D. La. 2012), aff'd, 739 F.3d 790 (5th Cir. 2014).

ACR attempted to obtain compensation as a Multi-Facility Business under the BEL Framework of the Settlement Agreement. ACR is a group of sixteen radiologists. Infirmary Health Services (“IHS”), a separate entity from ACR, owns several hospitals where ACR provides radiology services. In each hospital, the ACR radiologists interpret imaging scans taken by the hospital; the scans are reviewed in a designated location referred to as a “reading room.” According to ACR’s certified public accountant, ACR does not have a physical office and outsources all of its administrative tasks. IHS contracted with ACR to provide the radiology services; IHS owns the “reading room” space and all of the equipment ACR uses to carry out its imaging scan review services.

ACR submitted a BEL claim under the Multi-Facility Business Framework for a reading room located inside Infirmary 65, a hospital situated in Mobile, Alabama. The Settlement Agreement allows for business claims that “include separate specialized frameworks addressing Business Economic Loss Claims by MULTI-FA-CILITY BUSINESSES.” Exhibit 5 of the Agreement defines “multi-facility business” as “[a] business entity that, during the period April 1, 2010 through December 31, 2010, maintained Facilities in more than one location and had at least one Facility within the Gulf Coast Areas.” A “Facility” is then defined as “[a] separate and distinct physical location of a Multi-Facility Business at which it performs or manages its operations.” Policy 467, enacted by the CSSP, expands upon the definition of “Facility” and provides that an entity must satisfy three elements to be classified as a “Facility” under the Agreement: It must be (1) “[a] separate and distinct physical structure or premises”; (2) “[ojwned, leased or operated by the Business Entity”; and (3) “[a]t which the Business Entity performs and/or manages its operations.” Under the “Overall Criterion” section of Policy 467, the CSSP ex *169 plains that “[a]n Entity does not ‘perform’ or ‘manage’ operations at a location unless it can identify the expenses and revenues, if any, associated with the operations at that location separately from the expenses and revenues of other locations owned, leased or operated by the Entity.”

The CSSP denied ACR’s claim. It explained in its denial notice that ACR had failed to meet all three elements of the definition of “Facility.” ACR then requested a denial summary from the CSSP for additional explanation. It received the following summary:

[ACR] only has a contract to provide radiology services at the facilities. The Claimant’s Attorney also explained that the Claimant does not have an office space at the facilities for which they pay rent or lease expenses.... According to Policy 467, this Claimant does not have the option of filing a separate claim for operations performed at one of the hospitals. The claim should be closed, as the Claimant has filed a separate claim for a location that is not a facility.

ACR requested re-review of the denial after submitting a statement from its CPA and photographs of the reading room. The CSSP denied the claim again after re-review, and again after ACR requested reconsideration of the post-re-review denial notice. ACR appealed to an Appeal Panel. The Appeal Panel affirmed the denial of ACR’s claim, explaining that “Claimant does not pay rent or lease expenses on the reading room ... [and] [t]here is not evidence that Claimant pays for janitorial services, electricity, or other items a tenant normally has.” The Panel also announced that its decision “[would] stand as the Settlement Program’s final determination on this claim.”

Pursuant to the procedure for appeals to federal court arising out of the application of the Settlement Agreement, ACR appealed to Judge Barbier of the Eastern District of Louisiana. See In re Deepwater Horizon, 785 F.3d 1008, 1007 (5th Cir. 2015) (“A party may then appeal the Appeal Panel’s determination to the district court of Judge Barbier in the Eastern District of Louisiana, which has discretion to hear such appeals.”). The district court denied discretionary review of the decision by the Appeal Panel. ACR timely appealed.

II.

The standard of review that we apply to the district court’s denial of discretionary review is abuse of discretion. Holmes Motors, Inc. v. BP Exploration & Prod., Inc., 829 F.3d 313, 315 (5th Cir. 2016) (citing In re Deepwater Horizon, 785 F.3d at 1011). Our unpublished decisions addressing actions pursuant to the Settlement Agreement have expounded upon our abuse of discretion inquiry, “askfing] ‘whether the decision not reviewed by the district court actually contradicted or misapplied the Settlement Agreement, or had the clear potential to contradict or misapply the Settlement Agreement.’ ” Id. (citing series of cases). In the event that we find a contradiction or misapplication of the Settlement Agreement, we will agree that the district court abused its discretion. Id.

III.

ACR argues that the Infirmary 65 reading room constitutes a “Facility” of ACR because ACR has a contract with IHS to use the location as a “separate and distinct office space under ACR’s exclusive use and control.” BP counters that the reading room is a “Facility” of IHS, and thus that it cannot also be a “Facility” of ACR. The focus of the Settlement Agreement BEL Framework, BP explains, is upon remedying actual economic loss caused by the oil *170 spill. Further, BP argues that the costs of maintaining the equipment and reading room space are those of IHS, not ACR. Thus, BP contends, “Infirmary 65 is an IHS ‘facility.’ ”

In reaching our decision that the district court did not abuse its discretion in denying discretionary review of the Appeal Panel decision in the instant case, we need not examine whether the CSSP was actually correct in refusing to classify Infirmary 65’s reading room as a “Facility” of ACR. Rather, we look to whether the Appeal Panel decision contradicts or misapplies the Settlement Agreement, and we find that it does not.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
847 F.3d 167, 2017 WL 365495, 2017 U.S. App. LEXIS 1358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/id-100250022-v-bp-exploration-production-inc-ca5-2017.