I.A. Construction Corp. v. Equiptec, Inc.

622 A.2d 206, 95 Md. App. 574, 1993 Md. App. LEXIS 60
CourtCourt of Special Appeals of Maryland
DecidedApril 2, 1993
Docket1015, September Term, 1992
StatusPublished
Cited by5 cases

This text of 622 A.2d 206 (I.A. Construction Corp. v. Equiptec, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
I.A. Construction Corp. v. Equiptec, Inc., 622 A.2d 206, 95 Md. App. 574, 1993 Md. App. LEXIS 60 (Md. Ct. App. 1993).

Opinion

GARRITY, Judge.

In this matter we are asked to decide whether the trial court erred in entering a Final Order Establishing a Mechanic’s Lien and Directing Sale of Property in favor of appellee Equiptec, Inc. (Equiptec) and against certain land and the improvements thereon owned by appellant I.A. Construction Corporation (I.A. Corp.).

BACKGROUND

Appellant, I.A. Corp., contracted with Gencor, its general contractor, to build an asphalt plant from used components at I.A. Corp.’s Delmar, Maryland facility. Gencor, in turn, sub-contracted with Equiptec, an erection company of asphalt plants and general structures. Essentially, I.A. Corp. and Gencor were to supply the plant and necessary materials, Gencor was to oversee the erection of the plant, and Equiptec was to supply all of the labor for the construction of the plant to be used to manufacture asphalt.

Under paragraph two of the contract, Equiptec had the duty to “erect the hot elevator, dryer, bag house and mirror filler bin along with related components.” The parties disputed whether “related components” included the hookup of the air lines to the valve that controlled the flow of asphalt between the asphalt tank and a lesser capacity asphalt bucket. The issues presented in this case center around the installation of the air lines, specifically, whether *577 Equiptec had a contractual duty to install the air lines, whether Equiptec negligently installed the air line valve, and whether the incorrect hook-up of the air lines caused an asphalt spill that occurred shortly after start-up of the plant.

After construction of the plant had proceeded significantly, Gencor supplied Equiptec with a “punch list” of items that remained uncompleted. The punch list did not include hooking up air lines to a certain three-way valve. In order to facilitate completion of the punch list items, Equiptec assigned two workers to complete the project: a welder and an unskilled laborer.

At some point thereafter, a Gencor supervisor (Troy Morrison) advised the unskilled laborer (George Black), who had no previous experience hooking up this type of air line system, how to hook-up the air lines. At a later point in time, the supervisor ordered the laborer to hook-up the lines to the valve. Unfortunately, the laborer connected the air lines incorrectly.

Managers for Equiptec were not informed of the need to connect the air lines or otherwise asked to assist in such installation of the lines to the three-way valve. Mr. Joseph Pecht, Jr., an on-site overseer employed by Equiptec, was, however, aware that Mr. Morrison had instructed Mr. Black how to connect the air lines to the valve. The Gencor supervisor, Mr. Morrison, did not check to see if the lines had been connected properly.

The system was designed to run with the valve controlling the air lines in a closed position so that the hot liquid asphalt would circulate within the plant from the heated asphalt tanks, past the air lines and then back into the top of the tanks. If the valve controlling the air lines was open, asphalt would not circulate but rather would be pumped through the air lines and into the “AC bucket” that had the capacity to hold 1,000 gallons of asphalt. A safety cut-off switch in the bucket is designed to shut off the supply pump when the bucket is full of asphalt.

*578 Gencor, while trying to meet a start-up deadline of April 15, 1991, started the asphalt supply pump on April 13, 1991, but it stalled out because the hot oil exchange system, which is supposed to heat the various pipes and ensure that the hot asphalt remains in an easily flowing liquid form, was inadequate. Gencor then substituted another pump, the “unloading pump,” to circulate the hot asphalt through the lines to keep them hot for use the next day. One of the ramifications of using this pump was that the safety cut-off switch in the AC bucket could not staunch the flow of asphalt from the unloading pump in the event the bucket filled. According to testimony given by a Gencor supervisor, the spill would not have occurred if the unloading pump had not been substituted for the regular supply pump.

Evidence established that, prior to initiating the start-up of the plant, Gencor did.not thoroughly inspect the plant or check to ensure that the air lines had been connected correctly. Immediately after starting the plant, Gencor personnel left the plant unattended for nine to ten hours and before leaving did not check to see if the heated asphalt was recirculating properly. Gencor did not notify Equiptec of the start-up of the plant, and none of Equiptec’s personnel were present when the plant was started.

At some point after start-up, approximately 6,000 gallons of hot asphalt fed through the air lines into the AC bucket and out onto the ground. The cost to clean up the spilled asphalt totalled $45,576.65.

The trial court, faced with conflicting evidence regarding the meaning of the contract, the alleged negligence of the various parties, and the causes of the asphalt spill, entered judgment in favor of Equiptec for a mechanic’s lien in the amount of $54,227.67.

The court found that Equiptec had met its burden of proving that it was due $54,227.67 under the contract for work it had performed. This finding is not challenged on appeal.

*579 The trial court then addressed I.A. Corp.’s claim to a set-off in the amount of $45,576.65. The court determined that I.A. Corp. was not entitled to a set-off for this amount because 1) I.A. Corp. failed to produce sufficient evidence to convince the court that Equiptec had a contractual duty to hook-up the air lines, 2) that the Equiptec employee who installed the air line valve was acting at the direction of Gencor, not Equiptec, and 3) that the spill was due in large part to Gencor’s negligence during the start-up of the plant.

QUESTIONS PRESENTED

We are asked to address a number of questions on appeal, including:

1. Whether Equiptec had a contractual duty to hook-up the air line valve.
2. Whether Equiptec was solely responsible for negligently installing the air line valve.
3. Whether Equiptec’s negligent actions directly and proximately caused the liquid asphalt spill at the asphalt plant.
4. Whether the trial judge erred in hearing the claim due to “unclean hands” on the part of Equiptec.

ANALYSIS

In an action that has been tried without a jury, we review the case on both the law and the evidence. We will not set aside the judgment of the trial court on the evidence unless clearly erroneous, and we must give due regard to the opportunity of the trial court to judge the credibility of witnesses. Md.Rule 8-131(c).

I.

In seeking to offset the costs of cleaning-up the asphalt spill against the amount otherwise due Equiptec for work done under the contract, I.A. Corp. sought first to prove that Equiptec had a contractual duty “to hook-up the air lines.” Paragraph 2 of the contract provided that *580 Equiptec would “erect the hot elevator ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ray v. Credit Suisse First Boston Corp.
200 F. Supp. 2d 532 (D. Maryland, 2002)
Post v. Bregman
686 A.2d 665 (Court of Special Appeals of Maryland, 1996)
Vito v. Sargis & Jones, Ltd.
672 A.2d 129 (Court of Special Appeals of Maryland, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
622 A.2d 206, 95 Md. App. 574, 1993 Md. App. LEXIS 60, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ia-construction-corp-v-equiptec-inc-mdctspecapp-1993.