I. Koblitz & Son v. Arnold

33 Ohio C.C. Dec. 648, 22 Ohio C.C. (n.s.) 410, 1909 Ohio Misc. LEXIS 464
CourtCuyahoga Circuit Court
DecidedJanuary 11, 1909
StatusPublished

This text of 33 Ohio C.C. Dec. 648 (I. Koblitz & Son v. Arnold) is published on Counsel Stack Legal Research, covering Cuyahoga Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
I. Koblitz & Son v. Arnold, 33 Ohio C.C. Dec. 648, 22 Ohio C.C. (n.s.) 410, 1909 Ohio Misc. LEXIS 464 (Ohio Super. Ct. 1909).

Opinion

HENRY, J.

In this appeal all issues have been eliminated in which the original plaintiff was interested and the sole issue presented here is upon the validity of a mechanic’s lien claimed by Auld & Conger against the property of the defendant. The defendant is the successor in title to one Stevens, who began to erect a house on the property May 15, 1899. Before it was fully finished he negotiated a sale of the property to the defendant, who, after it was fully completed, as he testifies, moved into it October 31, 1899. Auld & Conger had, and performed a contract with Stevens to roof the house with slate. Their work was substantially done before Arnold occupied the property, but in August, 1900, ten months after Arnold’s occupancy had commenced, they undertook in his absence and without his knowledge, authority, or consent, to perform the final repairs to the roof which they found to be then necessary. Thereafter they filed their mechanic’s lien October 19, 1900, some fifteen months after the substantial completion of their contract, but with the time allowed by law for such filing, if it is to be reckoned from the date of said final repairs. They invoke a custom of slate roofers which makes it incumbent upon them after once substantially completing a slate roof, to wait until the work of all other trades upon the building is completed and then to repair whatever damage may have been caused by the workmen doing such work in the meantime.

Mr. Arnold, however, testifies that he and his son examined the roof at the time they moved in and caused the only defect in the roof, which they observed, to be repaired at his expense, by the replacing of one slate, during the month of November, 1899.

We do not think that the rule of Bernsdorf & Saylor v. Hardway, 6 Circ. Dec. 171 (7 R. 378), can be applied to the facts in this case. This court in its opinion by Baldwin, J., says:

“It is intimated in this case that Auld & Conger saw that it might be necessary to secure their lien at a time when it was more than four months after September, and had, with want of good faith, made some repairs in order to put on their lien. That claim is not borne out by the evidence. There is a class of eases that hold, where a mechanic’s lien holder has made alterations for the purpose of extending the time of getting his [650]*650lien, that it will not so operate. So far as the evidence shows, what they did was exactly in pursuance of the original contract between the parties.”

It is precisely in the particular thus pointed out that the case at bar differs from the decision cited. A decree will be entered for the defendant.

Winch and Marvin, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
33 Ohio C.C. Dec. 648, 22 Ohio C.C. (n.s.) 410, 1909 Ohio Misc. LEXIS 464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/i-koblitz-son-v-arnold-ohcirctcuyahoga-1909.