Hydro Well Drilling LLC v. Ryan

2018 WI App 66, 921 N.W.2d 531, 384 Wis. 2d 415
CourtCourt of Appeals of Wisconsin
DecidedSeptember 5, 2018
DocketAppeal No. 2018AP192
StatusPublished
Cited by1 cases

This text of 2018 WI App 66 (Hydro Well Drilling LLC v. Ryan) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hydro Well Drilling LLC v. Ryan, 2018 WI App 66, 921 N.W.2d 531, 384 Wis. 2d 415 (Wis. Ct. App. 2018).

Opinion

DUGAN, J.1

¶ 1 Hydro Well Drilling LLC appeals the circuit court's order denying its damages claim and dismissing its action against Basil Ryan, III ("Ryan III") and Jennifer Ryan (collectively the "Ryans"); Basil Ryan, II ("Ryan II"); and Ryan Management LLC (collectively the "Ryan Defendants"). This matter arises from work done in November 2016 on a property owned by the Ryans. Subsequently, Hydro Well filed a small claims action against the Ryan Defendants seeking damages. The matter was tried to the court.

¶ 2 On appeal, Hydro Well contends that the trial court erred because it found that (1) Hydro Well had no right to recover any damages from any Ryan Defendant; (2) there was no implied contract between it and any Ryan Defendant, and (3) Hydro Well had not established damages for unjust enrichment.

¶ 3 We conclude that the trial court properly found that Hydro Well failed to prove that it had any right to recover any damages from any of the Ryan Defendants, failed to prove that there was an implied contract between it and any of the Ryan Defendants, and failed to prove that it was entitled to recover damages for unjust enrichment. Furthermore, we conclude that the trial court properly found that, even if Hydro Well had proven that it was entitled to recover damages for unjust enrichment, it failed to prove the value of any benefit that was conferred upon the Ryans. We also deny the Ryan Defendants' motion for sanctions on appeal.

¶ 4 The following background facts are taken from the trial court's decision and supplemented by the record. Additional relevant facts are included in the discussion.

BACKGROUND

¶ 5 Ryan II and Burgarino have known each other for thirty years. During that time, the two men "traded" work, without paying each other for the work. The two men "basically just did favors for each other over the years." Ryan II and Burgarino arranged crews for the work that they did for each other and those crews were never compensated. Over the years that Ryan II and Burgarino worked together, they never had a written agreement or memorandum.

¶ 6 In November 2016, Burgarino did work on an existing well at the subject property, which involved removing an old pump, and installing a new pump, lateral, tank, and fittings. He did the work pursuant to informal conversations he had with Ryan II. There was no written agreement. There was no agreement to compensate Burgarino with any money. Ryan II did not think that he would be paying Burgarino for what he was doing. There was no agreement that included Ryan III. Hydro Well never came up in the discussions.

¶ 7 Burgarino purchased some materials for the work and paid for them from Hydro Well's account. Burgarino also paid Timothy Schmidt a $600 fee, for renting the machine that was used to dig a trench on the property, from Hydro Well's account. Burgarino also used some materials that he had on his truck. Burgarino was not reimbursed for any of those items. Ryan II set up the crew for the job on the property.

¶ 8 On November 10, 2016, Burgarino removed the old pump from the well, and on November 11, 2016, he installed the new pump, pump cable, and other parts. He also installed a tank in the barn and dug part of a trench for the lateral pump pipe. Schmidt helped Burgarino dig the trench. Burgarino also provided a new adapter on November 11, 2016, which he purchased using Hydro Well's account, but he never installed the adapter.

¶ 9 According to Ryan II, he "fired" Burgarino on November 11, 2016, because the newly installed tank was leaking, the trench was open, and he was getting frustrated that Burgarino was going on vacation. The next day, Ryan II had a temporary tank installed, and eventually the well system was redone. The following week, Burgarino telephoned Ryan II to discuss "squaring up." Ryan II told Burgarino that they had to "duplicate everything," that he was not paying him, and that he could come and pick up all the materials that he had used on the property, including the plastic piping, the pump, the wiring, the copper, and the fittings. Ryan II also never used the adapter that Burgarino had provided. However, the trench that Burgarino and/or Schmidt dug was not redone.

¶ 10 Eventually, Burgarino delivered a bill from Hydro Well in the amount of $3950 to Ryan III, and Ryan III gave the bill to Ryan II. Ultimately, when Hydro Well did not receive payment, it gave the Ryans notice of intent to file a claim for a construction lien, and in February 2017, Hydro Well filed the underlying small claims action.

¶ 11 Following a bench trial, the trial court held that there was no contract, express or implied, between Hydro Well and any of the Ryan Defendants. It concluded that the parties "played sort of fast and easy with corporate entities and when they were working as individuals."

¶ 12 The trial court also held that there would be a claim for unjust enrichment because at least some benefit was conferred upon the Ryans based on the fact that a trench was dug by Burgarino and/or Schmidt. The trial court also noted that Burgarino paid $600 to Schmidt, so at least some money was owed to someone by Ryan III. However, the trial court found that "the testimony was also unclear as to what the precise dollar amount was of that benefit[.]" The trial court stated that the value of the benefit had not been established because the testimony focused on a theory that there was an existing contract or an implied contract and the testimony did not address any benefits to the Ryans under an unjust enrichment claim.

¶ 13 The trial court also stated that the testimony suggested that the party that should actually receive something was "probably" Burgarino or Schmidt and that it had considered offering Hydro Well the opportunity to amend its complaint to substitute Burgarino as the plaintiff. However, it held that even if that was done, the precise dollar value of any benefit conferred had not been proven. Therefore, it held that no one was entitled to any damages. The trial court then dismissed the action. This appeal followed.

DISCUSSION

¶ 14 On review of a factual determination made by a trial court without a jury, we will not reverse unless the finding is clearly erroneous. See WIS. STAT. § 805.17(2). In addition, "when the trial judge acts as the finder of fact, and where there is conflicting testimony, the trial judge is the ultimate arbiter of the credibility of the witnesses." Cogswell v. Robertshaw Controls Co. , 87 Wis. 2d 243, 250, 274 N.W.2d 647 (1979). "When more than one reasonable inference can be drawn from the credible evidence, the reviewing court must accept the inference drawn by the trier of fact." See id. However, the application of the law to the facts of this case is a question of law that we determine without deference to the trial court's determination. See Wisconsin Title Serv., Inc. v. Kirkland & Ellis , 168 Wis. 2d 218, 222,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2018 WI App 66, 921 N.W.2d 531, 384 Wis. 2d 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hydro-well-drilling-llc-v-ryan-wisctapp-2018.