This text of 2016 SD 65 (Hyde v. Sully County Board of Adjustment) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hyde v. Sully County Board of Adjustment, 2016 SD 65, 886 N.W.2d 355, 2016 S.D. LEXIS 110, 2016 WL 5637003 (S.D. 2016).

Opinion

SEVERSON, Justice.

[¶ 1.] Petitioners appealed the decision of the Sully County Board of Adjustment to grant a conditional use permit to Ring-Neck Energy & Feed, LLC, for an ethanol plant. Petitioners appeal from the circuit court’s dismissal of the appeal as untimely. We affirm.

Background

[¶ 2.] On July 20, 2015, the Sully County Board of Adjustment (the Board) considered an application by Ring-Neck Energy & Feed, LLC, for a conditional use permit (CUP) that would allow construction and operation of an ethanol plant. The Board granted the CUP and adopted findings of fact and conclusions of law to that effect. Ring-Neck Energy’s application was marked approved, and the Board’s chairman signed and dated it on July 20, 2015. The approved permit was filed that same day in the Sully County Planning and Zoning office. When the Board next met, on August 4, 2015, it approved the minutes from the July 20th meeting. When doing so, it approved additional language to be added to the conditions of the CUP. After the addition, which is underlined below, condition f(1) reads:

Applicant shall remain responsible either individually or through cooperation with the County in any combination of the funding sources set forth in Exhibit 2, Section 10, so as to ensure the Sully County budget is protected from the estimated $1.2 million cost for road paving and/or restructuring and rebuilding to account for the truck traffic of 186th Street from U.S. Highway 83 east to 305th Avenue, and then south to Applicant’s site entrance (apx. 1.2 miles); In the event that funding sources described in Exhibit 2, Section 10, are insufficient or unobtainable, Applicant shall. bear that responsibility_

[¶ 3.] On August 20, 2015, Petitioners filed a petition for writ of certiorari with the circuit court. Petitioners alleged that the Board’s decision granting the CUP was illegal. In their petition, Petitioners claimed that the Board’s decision was ultra vires because the meeting violated open- *357 meetings laws, the Board failed to adopt rules in accordance with SDCL 11-2-54, and it failed to adopt criteria pursuant to SDCL 11-2-17.3 for evaluating each conditional use. Petitioners also alleged that an ethanol plant is not allowed in the zoning district where Ring-Neck Energy plans to build and that various aspects of the ethanol plant did not meet zoning ordinance requirements or were not allowed under the ordinances. The court granted the writ on August 25, 2015, and ordered the Board to produce a transcript of the record and proceedings for the court’s review.

[¶ 4.] Ring-Neck Energy moved to intervene, and the circuit court granted its motion. Ring-Neck Energy subsequently moved to quash the writ and dismiss the petition as untimely. The court decided to defer the motions hearing’ until the entire matter eould be heard on the merits on October 26, 2015. The .court issued its decision on November 10, 2015. The court determined that it lacked subject-matter jurisdiction because the petition was untimely under SDCL 11-2-61. On appeal to this Court, Petitioners assert that their petition was timely. They also contend that the Board failed to follow the State’s open-meetings laws, that it did not act within its authority when it allowed uses that did not comply with the zoning ordinances, and that the Board’s failure to follow procedural rules voids the Board’s decision.

Analysis

[¶ 5.] We first address the timeliness of the petition for writ of certiorari. “This [C]ourt has consistently recognized that the right to an appeal is purely statutory and no appeal may be taken absent statutory authorization.' An attempted appeal from which no appeal lies is a nullity and confers no jurisdiction on the court except to dismiss it.” Elliott v. Bd. of Cty. Comm’rs of Lake Cty., 2005 S.D. 92, ¶ 15, 703 N.W.2d 361, 368 (quoting Appeal of Lawrence Cty., 499 N.W.2d 626, 628 (S.D.1993)). “We review issues regarding a [c]ourt’s jurisdiction as questions of law under the de novo standard of review.” Elliott v. Bd. of Cty . Comm’rs of Lake Cty., 2007 S.D. 6, ¶ 9, 727 N.W.2d 288, 289.

[¶ 6.] At the time Petitioners sought relief, SDCL 11-2-61 1 provided:

Any person or persons, jointly or severally, aggrieved by any decision of the board of adjustment, or any taxpayer, or any officer, department, board, or bureau of the county,, may present to a court of record a petition duly verified, .setting forth that the decision is illegal, in whole or in part, specifying the grounds of the illegality. The petition shall be presented to the court within thirty days after the filing of the decision in the office of the board of adjustment.

(Emphasis added). In this case, Petitioners petitioned the circuit court for relief on August .20, 2015, thirty-one days after the Board’s decision approving' the permit was filed in the Sully County Planning and Zoning office on July 20, 2015. The statute clearly provides that the time for appeal begins to run upon the filing of the decision. It provides that an aggrieved person must present a petition “within thirty days after the filing of the decision in the office of the board of adjustment.” SDCL 11-2-61 (emphasis added). The Board’s decision was filed in the. Sully County Planning and Zoning Office, which for filing purposes, serves as the Sully County Office of the Board of Adjustment.

[¶ 7.] Petitioners maintain that the object of their appeal is the Board’s approval of the meeting minutes and not the *358 Board’s decision to grant the CUP. Their position is unsupported. Because SDCL 11-2-61 requires that the petition set “forth that the decision is illegal” and specify “the grounds of the illegality,” the relevant decision that the statute is referencing is that which the petitioner is claiming is illegal. Petitioners have not contended that by adding language in the minutes, the Board has failed to regularly pursue its authority. 2 See Elliott, 2005 S.D. 92, ¶ 14, 703 N.W.2d at 367 (quoting SDCL 21-31-8) (“The standard of review for a writ of certiorari ‘cannot be extended further than to determine whether the board has regularly pursued the authority of such board.’”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hauck v. Clay County Commission
994 N.W.2d 707 (South Dakota Supreme Court, 2023)
McLAEN v. WHITE TOWNSHIP
974 N.W.2d 714 (South Dakota Supreme Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2016 SD 65, 886 N.W.2d 355, 2016 S.D. LEXIS 110, 2016 WL 5637003, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hyde-v-sully-county-board-of-adjustment-sd-2016.