Huxol v. Nickell

476 P.2d 606, 206 Kan. 102, 1970 Kan. LEXIS 444
Supreme Court of Kansas·Decided November 7, 1970·No. 45,821·Published·Cited by 4 cases

Opinion

The opinion of the court was delivered by

Kaul, J.:

The appellant, E. L. Nickell, d/b/a Nickell Construction Company, appeals from a judgment of the trial court denying indemnification against appellee, Al M. Rome, d/b/a Rome Ditching Service, for a judgment recovered by appellee Huxol against appellant Nickell which was affirmed by this court in Huxol v. Nickell, 205 Kan. 718, 473 P. 2d 90.

Huxol sustained personal injuries as a result of falling into a hole on the Fort Hays Kansas State College campus, during a construction project on the campus. Nickell was the general contractor and Rome a subcontractor on the project, both were sued by Huxol.

*103 In Huxol v. Nickell, supra, a jury trial resulted in a verdict for Huxol against Nickell and, by an answer to a special question, the jury absolved Rome of any negligence causing Huxol’s fall. In the principal action Nickell and Rome filed cross claims against each other. The issue of indemnification, framed by the cross claims, was reserved by stipulation and tried to the court after the judgment in the principal case was affirmed by this court on appeal.

The facts concerning Huxol’s fall, his injuries and the relationship of the parties are fully set out in Huxol v. Nickell, supra, and need not be repeated. Insofar as pertinent the opinion is incorporated herein by reference.

In the action before us now Nickell contends that he should be indemnified by Rome in the amount of the verdict rendered in favor of Huxol against Nickell. Nickell contends that indemnification is required of Rome because the damages were caused by the negligence of Rome or by the breach of his contract with Nickell.

In addition to evidence relative to the issue of indemnification submitted at the jury trial, the trial court heard and considered further evidence bearing on the issue in this subsequent proceeding. The trial court made the following findings:

"No. 1
“The applicable implied covenant of Al M. Rome to E. L. Nickell was to indemnify E. L. Nickell for any loss to Nickell for defective workmanship and for negligent acts of Al M. Rome resulting in injuries to third parties such as ♦he plaintiff in this case.
“No. 2
“In the case before us the jury has already decided the factual issue of negligence and found that the defendant Al M. Rome, through himself or his employees, was not negligent, and that E. L. Nickell and his employees were negligent; and that the negligence of E. L. Nickell and his employees was the proximate cause of the injuries to the plaintiff. The claim of plaintiff for damages was tried on allegations of negligence only, there being no allegations of defective workmanship, and there is no evidence of defective workmanship in the case.
“No. 3
“Thus, the jury by specific finding (see the special questions and answers) exonerated the defendant Al M. Rome of any fault as a proximate cause of the accident and injuries to the plaintiff. The jury apparently found that Al M. Rome had no legal duty to erect barricades and provide lights in view of the contract, which is defendant’s exhibit 3, and the conditions of supervision by Nickell’s superintendent as shown by the evidence. The jury apparently found only the defendant Nickell had that duty by contract.
*104 “No. 4
“The general contract, defendant’s exhibits 3 and 4, provides specifically for E. L. Nickell to provide such safeguards and there is no evidence that he subcontracted that contractual obligation to Al M. Rome. (See defendant’s exhibits 7 and 8 and defendant Nickell’s testimony in his deposition taken October 30, 1967, at pages 7 and 8.)
“No. 5
“The Court finds that the policy of liability insurance held by the defendant Al M. Rome at the time of the accident could not change the above findings because the jury has already found that the defendant Rome was not guilty of any negligence, and therefore not liable for the injuries to the plaintiff. A continuance to obtain such policy should be and is denied.
“No. 6
“As between the defendants the court finds generally for the defendant Rome and against the defendant Nickell; and that the defendant Nickell is not entitled to any recovery from the defendant Rome.
“No. 7
“The court finds that judgment should be entered on all of the foregoing findings; and that all of them should be made a part of the judgment of the court in this instance, pointing out that the trial here today to the court is only on the issue which was reserved earlier by stipulation of the parties, being the issue of liability as between the defendants themselves.”

On appeal, Nickell specifies four points of error all of which go to the central issue stated by him to be:

“Whether or not a general contractor is entitled to indemnification from a subcontractor for damages caused by the breach of a contract or negligence of such subcontractor.”

Generally, Nickell argues the evidence established that Rome contracted, expressly or impliedly, to provide the necessary safeguards for the excavation work he was performing and that his failure to do so resulted in the jury returning a verdict against Nickell as general contractor. Nickell says that under such circumstances Rome should be required to indemnify him for the damages sustained by Huxol.

The trial court found to the contrary. Thus, the controlling issue on appeal is primarily the familiar question whether there is substantial competent evidence to support the findings of the trial court.

Under a state contract, Nickell commenced construction of a power plant on the campus of the Fort Hays State College. The conditions existing and the nature of the work being done on the *105 construction project on the date of the accident are fully set out in our former opinion. (205 Kan. 718). For our purposes here we need reiterate only the evidence bearing on the issue of indemnification.

On April 3, 1967, Romes employees were excavating, what was described as the main heat tunnel, at a location between 100 and 200 feet south of the library. A large tunnel had previously been dug eastward from the power plant site. Wire barricades and warning lights had been placed at night on these excavations.

On the afternoon of April 3, 1967, Shukman, a Rome employee, was instructed by Willis Nelson, superintendent for Nickell, to jump ahead approximately 200 feet from the main excavation, where he had been working, and dig an isolated hole. Shukman commenced digging the hole as directed. Shukman left the area about 5 p. m. Huxol, while making his watchman’s rounds that night, fell into the hole and was injured. The next day Nickell’s employees erected barricades around the hole.

Free access — add to your briefcase to read the full text and ask questions with AI

Huxol v. Nickell, 476 P.2d 606, 206 Kan. 102, 1970 Kan. LEXIS 444 (kan 1970).

476 P.2d 606 (Huxol v. Nickell) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Webb v. Graham
510 P.2d 1195 (Supreme Court of Kansas, 1973)
Rymph v. Derby Oil Co.
507 P.2d 308 (Supreme Court of Kansas, 1973)
Cullen v. Atchison, Topeka & Santa Fe Railway Co.
507 P.2d 353 (Supreme Court of Kansas, 1973)
Conger v. Conger
494 P.2d 1081 (Supreme Court of Kansas, 1972)