Huntington National Bank v. McFarlin LLP

CourtDistrict Court, D. Minnesota
DecidedMarch 31, 2023
Docket0:22-cv-01847
StatusUnknown

This text of Huntington National Bank v. McFarlin LLP (Huntington National Bank v. McFarlin LLP) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huntington National Bank v. McFarlin LLP, (mnd 2023).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA

Huntington National Bank, Case No. 22-cv-1847 (WMW/ECW)

Plaintiff, ORDER v.

McFarlin LLP and Timothy G. McFarlin,

Defendants.

Before the Court is Plaintiff Huntington National Bank’s motion for default judgment. (Dkt. 12.) For the reasons addressed below, the Court grants the motion. BACKGROUND Plaintiff Huntington National Bank (Huntington), a national banking association headquartered in Ohio, alleges that it entered into an Installment Payment Agreement (Agreement) with Defendant McFarlin LLP for a financed amount of $199,561.57. (Dkt. 1 at 3.) The parties entered into the Agreement to facilitate McFarlin LLP’s purchase of certain software and equipment. Under the Agreement, McFarlin LLP was required to make 60 monthly payments of $3,918.63 to Huntington. (Dkt. 1 at 2.) The Agreement also entitled Huntington to obtain fees, costs and expenses associated with Huntington exercising its rights and remedies under the Agreement. The Agreement was secured by a continuing guaranty (Guaranty) from Defendant Timothy G. McFarlin. The Guaranty provided an absolute guaranty of full payment of all obligations that McFarlin LLP owed under the Agreement and obligated McFarlin to pay all costs, fees and expenses that the Creditor incurred in connection with enforcing the Guaranty along with McFarlin LLP’s other obligations. (Dkt. 1 at 6.) On June 9, 2022, McFarlin LLP failed to make its payment, and on June 24, 2022, Huntington notified McFarlin LLP and McFarlin that it was in default under the Agreement. Huntington commenced this action on July 21, 2022, alleging breach of

contract.1 Huntington served McFarlin on July 21, 2022, and served McFarlin LLP on August 5, 2022. The Clerk of Court entered default as to McFarlin and McFarlin LLP on September 30, 2022. Neither McFarlin LLP nor McFarlin has appeared in this case. Huntington now moves for default judgment. ANALYSIS

To obtain a default judgment, a party must follow a two-step process. First, the party seeking a default judgment must obtain an entry of default from the Clerk of Court. “When a party against whom a judgment for affirmative relief is sought has failed to plead or otherwise defend, and that failure is shown by affidavit or otherwise, the clerk must enter the party’s default.” Fed. R. Civ. P. 55(a). Here, on Huntington’s application, the

Clerk of Court entered default as to McFarlin and McFarlin LLP on September 30, 2022. The entry of default is supported by the record, which reflects that McFarlin and McFarlin

1 The complaint also alleges unjust enrichment and promissory or equitable estoppel. In doing so, the complaint asserts Huntington’s rights to claim and obtain collateral and priority liens. But at the default-judgment hearing, however, Huntington advised that it would not object to the Court entering judgment only on Huntington’s breach-of-contract claims and dismissing the remaining claims. LLP were properly served with the complaint and summons and failed to answer or otherwise respond to the complaint. Second, after default is entered, the party seeking affirmative relief “must apply to the court for a default judgment.” Fed. R. Civ. P. 55(b)(2). Upon default, the factual allegations in the complaint are deemed admitted except those relating to the amount of

damages. Fed. R. Civ. P. 8(b)(6); accord Murray v. Lene, 595 F.3d 868, 871 (8th Cir. 2010). However, “it remains for the court to consider whether the unchallenged facts constitute a legitimate cause of action, since a party in default does not admit mere conclusions of law.” Murray, 595 F.3d at 871 (internal quotation marks omitted); accord Marshall v. Baggett, 616 F.3d 849, 852 (8th Cir. 2010). The Court now evaluates the

factual basis for each claim Huntington advances in its complaint. I. Breach of Contract by McFarlin LLP (Count I) Huntington alleges breach of contract by McFarlin LLP. Under Minnesota law, “[t]he elements of a breach of contract claim are (1) formation of a contract, (2) performance by plaintiff of any conditions precedent to his right to demand

performance by the defendant, and (3) breach of the contract by defendant.” Lyon Fin. Servs., Inc. v. Ill. Paper & Copier Co., 848 N.W.2d 539, 543 (Minn. 2014). Huntington alleges that McFarlin LLP entered into the Agreement with Huntington on July 8, 2021, in which Huntington lent McFarlin LLP $199,561.57. According to Huntington, failing to make a required monthly payment is an occurrence that entitles

Huntington to exercise all of its remedies under the contract, including accelerating the entire indebtedness. (Dkt. 1 at 8.) Huntington alleges that it provided Defendants notice of the default on June 24, 2022. In Huntington’s June 2022 notice, Huntington also notified Defendants that it planned to exercise its right to accelerate the payments—that is, “to declare immediately due and payable the sum of all amounts currently due under the [Agreement], plus all unpaid Payments for the remaining term of the [Agreement].”

(Dkt. 1 at 4; Dkt. 1-1 at 21-22.) Huntington alleges that, as of July 15, 2022, McFarlin LLP owed Huntington $181,394.69. Accepting these facts as true, Huntington has alleged sufficient facts to support a breach-of-contract claim against McFarlin LLP. For this reason, Huntington has established that the unchallenged facts constitute a legitimate claim for breach of contract

as to McFarlin LLP. II. Breach of Contract by McFarlin (Count II) Huntington also alleges breach of contract by McFarlin. Huntington alleges that the Agreement is secured in part by a Guaranty from McFarlin in favor of Huntington. (Dkt. 1 at 6.) Huntington contends that under the Guaranty, McFarlin “unconditionally and

absolutely guaranteed the full and prompt payment of all obligations of [McFarlin LLP] including, without limitation, amounts due under the [Agreement].” (Dkt. 1 at 6.) And the Guaranty provides that McFarlin is liable for all costs and expenses incurred by the Creditor in connection with enforcing the Guaranty and McFarlin LLP’s obligations. (Dkt. 1 at 6.) McFarlin LLP breached the Agreement, Huntington alleges, by failing to

make the required monthly payments due. (Dkt. 1 at 7.) Huntington provided Defendants notice of the default on June 24, 2022. (Dkt. 1 at 7.) In the June 2022 notice, Huntington also notified Defendants that it planned to exercise its right to accelerate the payments— that is, “to declare immediately due and payable the sum of all amounts currently due under the [Agreement], plus all unpaid Payments for the remaining term of the [Agreement].” (Dkt. 1 at 7; Dkt. 1-1 at 21-22.) Huntington alleges that, as of July 15, 2022, McFarlin

LLP owed Huntington $181,394.69. McFarlin has failed and refused to pay the amounts owed under the Agreement, thereby breaching the Guaranty, Huntington alleges. (Dkt. 1 at 10.) Accepting these facts as true, Huntington has alleged sufficient facts to support a breach-of-contract claim against McFarlin. Huntington has established that the

unchallenged facts constitute a legitimate claim for breach of contract as to McFarlin. III. Damages Huntington asks the Court to award damages in its favor. A district court must ascertain the amount of damages before entering a default judgment. See Hagen v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pope v. United States
323 U.S. 1 (Supreme Court, 1944)
Marshall v. Baggett
616 F.3d 849 (Eighth Circuit, 2010)
Murray v. Lene
595 F.3d 868 (Eighth Circuit, 2010)
State Bank of Cokato v. Ziehwein
510 N.W.2d 268 (Court of Appeals of Minnesota, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Huntington National Bank v. McFarlin LLP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huntington-national-bank-v-mcfarlin-llp-mnd-2023.