Hunter Bros. Systems, Inc. v. Brantley Construction Co.

332 S.E.2d 206, 286 S.C. 59, 1985 S.C. LEXIS 414
CourtSupreme Court of South Carolina
DecidedMay 7, 1985
Docket22313
StatusPublished

This text of 332 S.E.2d 206 (Hunter Bros. Systems, Inc. v. Brantley Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hunter Bros. Systems, Inc. v. Brantley Construction Co., 332 S.E.2d 206, 286 S.C. 59, 1985 S.C. LEXIS 414 (S.C. 1985).

Opinion

Chandler, Justice:

Appellant Hunter Brothers Systems, Inc. (Hunter) subcontracted with the general contractor, Respondent Brantley Construction Company, Inc. (Brantley), to perform the electrical work on a warehouse (project) for State Ports Authority (Owner) at its Wando Terminal.

Upon completion of the project Brantley refused to pay Hunter the remaining $72,161.00 balance of the contract price. Brantley admits owing Hunter some amount but contends that, as the result of a breach of the contract by Hunter, it sustained additional costs which operated as a setoff against Hunter.

Hunter filed suit, denying the breach; Brantley answered and counterclaimed. The matter was referred to the Master in Equity for Charleston County under a stipulation that his order would be final.

The Master found that Hunter breached the contract, entitling Brantley to setoffs totalling $44,370.41, and awarded Hunter a final payment of $27,790.54. Hunter appeals.

We reverse.

ISSUES

The issues to be determined are (1) which party breached the subcontract, and (2) what damages resulted from the breach.

*61 BACKGROUND FACTS

From the beginning the Wando project was beset by construction delays which culminated in the submission to arbitration of scheduling disputes between Brantley and the Owner.

The particular delay which brought about the controversy between Brantley and Hunter relates to the warehouse roof construction.

According to progress schedules (schedule) prepared by Brantley, as required under the general contract and testified to by witnesses for both parties, Hunter’s electrical work was to commence February 23; actual installation of metal conduit, described as hollow aluminum tubing, however, was to begin March 2, being the same date established by the schedule for completion of the roof. Under its subcontractor Hunter was allowed eight (8) weeks from March 2 in which to complete its work.

On March 2 the warehouse roof had not been installed; indeed, the roofing material had not been received by Brantley from the supplier and was not entirely received as late as June 29.

Hunter, concerned over the effect of the roof delay upon its ability to meet the eight weeks deadline, discussed the problem with Brantley’s project manager, Robert Sharpton.

Thereafter, Hunter’s vice president, Jimmy Hunter, instigated a meeting in May, 1981, between ranking officials of Brantley, Hunter and the Owner to resolve the question of Hunter’s start-up. No resolution was reached at the meeting, as a result of which Hunter refused to install conduit prior to completion of the roof.

The Master found that Hunter’s refusal constituted a breach of the subcontract and, after allowing numerous setoffs to Brantley for costs allegedly arising from the breach, awarded Hunter a portion only of the balance due. We disagree.

PROGRESS SCHEDULES AND CONSTRUCTION DELAYS

The general contract between Brantley and the Owner was the standard A.I.A. form which included provisions pertinent to this litigation:

*62 4.10 PROGRESS SCHEDULE

The Contractor, immediately after being awarded the Contract shall prepare and submit for the Owner’s information an itemized progress schedule giving the sequence and dates for all major stages of the Work. This schedule should also include dates for submission of Shop Drawings and other required submittal data. This schedule must be submitted in such a form and in sufficient detail that it will be satisfactory to the Owner. The Contractor shall thereafter so regulate his operations, plans, working shifts, number of men employed as to maintain a program in accordance with the schedule or such revisions thereof as are approved by the Owner. The Contractor shall make periodic reports to the Owner comparing his actual progress with the progress schedule. The Contractor shall work his men overtime and add additional labor and equipment as is necessary to complete the Work on time or where impossible to complete on time, reduce the delay. Contractor must obtain the written consent of the Owner before scheduling overtime work. [Emphasis supplied].

Pursuant to the foregoing section Brantley prepared detailed schedules setting out in graph form the beginning and completion dates for all construction to be performed on the project.

However, Brantley failed to abide by its own schedule, not only with respect to the electrical work of Hunter, but in other phases of the construction as well. Owner’s witnesses, Setzler and Collins, address this condition in much detail in their testimony, to include extensive delays in the erection of building slabs, the construction of the concrete building, installation of rolling steel doors, etc.

There is nothing in the record to attribute any construction delays to Hunter, or to indicate that Hunter was not ready and able to install conduit on March 2. The evidence is clear that the sole reason installation did not commence on that date was Brantley’s failure to complete the roof.

When the scheduled March 2 date for commencement of conduit installation passed, Brantley made no move at that time to compel start-up by Hunter. Indeed, the earliest communication after March 2 between the parties, relative *63 conduit installation, was in May, 1981, when Jimmy Hunter advised Sharpton that Hunter needed to get started. This conversation brought about the meeting in May, 1981, in Setzler’s office, alluded to earlier in this opinion, which was attended by ranking officials of the three principals involved.

MEETING OF MAY, 1981

Present at the meeting on behalf of Hunter was Jimmy Hunter; on behalf of Brantley, Sharpton; and on behalf of the Owner, Larry W. Setzler, its engineer and on-site manager for the project, and George M. Collins, its employee designated “to insure the electrical work followed the plans and specifications.”

The versions of Jimmy Hunter, Setzler and Collins as to what transpired at the meeting are essentially identical. On the other hand, Sharpton denied any recollection of such a meeting in both his pre-trial deposition and initial testimony at the trial. In recall testimony, after Setzler, Collins and Jimmy Hunter had testified fully concerning its events, he did admit to a recollection of the meeting.

Section 4.10 of the general contract required Brantley to prepare “an itemized progress schedule giving the sequence and dates for all major stages of the Work.” It then required Brantley to “so regulate his operations ... as to maintain a program in accordance with the schedule or such revisions thereof as are approved by the Owner. ’’[Emphasis supplied].

Recognizing the requirement in § 4.10 that schedule revisions receive approval of the Owner, Hunter sought permission of the Owner to install conduit prior to roof completion. Setzler, representing the Owner, granted a conditional approval:

A. I then told the — speaking to Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
332 S.E.2d 206, 286 S.C. 59, 1985 S.C. LEXIS 414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hunter-bros-systems-inc-v-brantley-construction-co-sc-1985.