Hunt v. Riggins

341 S.W.2d 136, 1960 Mo. App. LEXIS 444
CourtMissouri Court of Appeals
DecidedDecember 5, 1960
DocketNo. 23168
StatusPublished
Cited by1 cases

This text of 341 S.W.2d 136 (Hunt v. Riggins) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hunt v. Riggins, 341 S.W.2d 136, 1960 Mo. App. LEXIS 444 (Mo. Ct. App. 1960).

Opinion

CROSS, Judge.

In this action a subcontractor sues the general building contractor for the value of materials and labor furnished for construction of a house, and seeks to establish a mechanic’s and materialmen’s lien on the house and lot.

The suit was filed as an independent action by Stanley Hunt, a plumbing and heating contractor, against defendant John Rig-gins, the general contractor, and defendants Frank W. Sampson and Emogene H. Sampson, property owners who had contracted with Riggins to build a house. Upon motion, Hunt’s suit was consolidated with a prior action, but was tried separately after the other claims and causes were disposed of.

Trial was before the court without a jury and was upon Hunt’s counterclaim against defendant John Riggins for the sum of $4,425.68 alleged as due for materials and labor furnished, and against the Sampsons, as defendants, praying that a lien be established on their house and lot.

The trial court found that the reasonable value of the materials and labor was $3,-987.65.- Judgment in that sum, with interest, was entered in favor of cross-claimant Hunt against defendant Riggins.

The court additionally found that Hunt had not filed a statement of his claim within four months of the accrual of his debt, as required by the lien statute, and that he was not-entitled to a lien against the Sampson’s property. The judgment ordered that Hunt take nothing from the Sampsons and that they be discharged. Hunt appeals.

Appellant first contends that the trial court erred in entering judgment against Riggins for only $3,987.65, with interest, after having found that sum to be the reasonable value of the work and materials. He claims the judgment should not be limited to the reasonable value of those items but should be for the “contract price”, and in the sum of $4,402.18, with interest.

Appellant says he had been doing the plumbing and heating work on houses built by Riggins with an “understanding” between them that he would charge Riggins 25% over material cost and give him a “fair deal” on labor. Appellant admits there was no new or separate agreement as to each house. The sum of $4,402.18 is the total amount claimed, as calculated in accordance with the “understanding”.

Appellant’s cause of action is bottomed on his first pleading, the counterclaim on which the case was tried. In paragraph 3, he states: “That during a period of time commencing in June, 1956, and continuing through and including the month of May, 1957, this cross-complaint, at the special insistence (sic) and request of the defendant, John Riggins * * * furnished certain material and labor in the construction of a dwelling house and garage * * * in the sum of Four Thousand Four Hundred Twenty-five Dollars and Sixty-eight Cents ($4,425.68).” Judgment was prayed for the alleged sum.

No contract is alleged or referred to anywhere in the pleading. Hence, we cannot regard the claim as one based on a contract. The counterclaim pleads nothing but an entitlement to the reasonable value of the material and labor.

Appellant cannot abandon his claim pleaded in quantum meruit and try the cause on an unpleaded contract. The courts have not permitted that variance. See Kansas City Structural Steel Co. v. Athletic Bldg. Ass’n et al., 297 Mo. 615, 249 S.W. 922.

No argument is here made by appellant that the reasonable value of the material and labor is other than as found by the trial court.

In his after trial motion to amend the judgment and opinion, appellant made no allegation that the court’s finding of reasonable value was erroneous. The complaint made was that he was entitled to the “contract” price. In fact, appellant adopted and relied upon the court’s finding as the [138]*138basis for affirmative relief prayed in the following words of the motion: “Wherefore, the cross-claimant, Stanley Hunt, prays the Court for its order amending its judgment and opinion in the following respects, to-wit: * * * that the cross-claimant is entitled to have a lien on the real estate described in the cross-claim belonging to Frank W. and Emogene H. Sampson in an amount of Three Thousand, Nine Hundred Eighty-seven and 65/100 Dollars ($3,987.65), the reasonable value of work and materials furnished, * * (Emphasis supplied.) Appellant’s motion for new trial contains no further reference to the court’s finding as to reasonable value.

From our review of the evidence, we conclude that it supports the trial court’s finding of the reasonable value of the work performed and materials furnished by appellant under the subcontract, and we make the same finding. The contention is ruled against appellant.

Appellant urges in his second point that he should not have been adjudged liable for costs, but that costs should have been taxed against respondent Riggins. Appellant admits that courts have inherent discretionary power, in equity cases, to depart from the usual rule that the prevailing party is entitled to costs if such action is justified, in equity and good conscience, by the circumstances of the case. Appellant has designated this cause as one in equity, but he denies the existence of such justifying circumstances.

The record shows that respondent Riggins was present at the trial, but not represented by counsel. He was the first witness called by appellant and testified on appellant’s behalf. After the conclusion of appellant’s case, Riggins offered neither himself nor any other witness to testify in his defense. He made no resistance to appellant’s claim. For all practical purposes he stood in default. It is a reasonable inference that a separate claim against him would have gone to judgment by actual default.

It is apparent that the trial arose as a terminal necessity in an unresolved controversy between appellant and the Sampsons over the lien claimed by appellant and not by reason of the claim against Riggins. The trial was devoted almost entirely to the lien issue. The only defense made during its course was on behalf of the Sampsons. Riggins, although a nominal defendant, was not a trial participant. In reality he was an observer—a bystander. In our opinion it would have been unjust to tax the costs against Riggins under the circumstances shown. We rule that the entry of a judgment for costs against appellant was within the trial court’s reasonable discretion.

Appellant contends, in conclusion, that he is entitled to a mechanic’s and material-men’s lien on the Sampson house. Supplementing other reasons urged, appellant says the lien statement was timely filed. The Sampsons had made the defense at the trial that the statement was not filed within four months after the claimed indebtedness accrued, as required by Section 429.080, V.A.M.S. The trial court ruled 'the issue, under conflicting evidence, against appellant.

The statement of lien account was filed on August 23, 1957. It follows that a valid lien could not be adjudged under the provisions of Section 429.080 on account of any labor performed or materials furnished prior to April 23, 1957. Conversely, any item of labor performed or materials furnished after April 23, 1957, is within the statute’s four month limitation period.

Appellant relies upon and claims that he performed two items of labor after April 23, 1957. The first is claimed as two hours of plumbing work performed on May 3, 1957. The second is an alleged four hours of sheet metal work on May 18, 1957. Appellant claims some materials were also furnished on the latter date.

[139]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavic v. Missouri Research Laboratories, Inc.
416 S.W.2d 6 (Missouri Court of Appeals, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
341 S.W.2d 136, 1960 Mo. App. LEXIS 444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hunt-v-riggins-moctapp-1960.