Hudson River Fisherman's Ass'n v. Williams

139 A.D.2d 234, 531 N.Y.S.2d 379, 1988 N.Y. App. Div. LEXIS 7983
Appellate Division of the Supreme Court of the State of New York·Decided July 21, 1988·Published·Cited by 9 cases

Opinion

OPINION OF THE COURT

Yesawich, Jr., J.

Respondent Spring Valley Water Company, Inc. (hereinafter Spring Valley) provides water for approximately 88% of the residents of petitioner Rockland County and various industrial users from four major sources: (1) 57 wells, (2) the Lake De Forest Reservoir and Filter Plant, (3) the Ramapo Valley Well Field, and (4) the Stony Point Reservoir and Filter Plant. In 1979, Spring Valley submitted a water supply application to respondent Department of Environmental Conservation (hereinafter DEC) for permission to construct an additional water source named the Ambrey Pond project on a 364-acre site near the Town of Stony Point, Rockland County, including a reservoir with a nearly two-billion gallon capacity, a filtration plant, and a diversion pipeline to bring water to the reservoir from a nearby brook; acquisition of land to construct the reservoir and filtration plant is contemplated by the first stage of this multistage undertaking. The project, capable of adding a dependable yield of approximately 7.5 million gallons per day (mgd) to the utility’s water distribution capacity, was sought to meet three perceived needs: (1) a present water supply deficit in the Haverstraw-Stony Point area of the Spring Valley system that is currently being met with releases of water from Lake Tiorati, pursuant to an agreement with the Palisades Interstate Park Commission, a circumstance which is not expected to continue, and by pumping water from lower elevations in the system at a substantial cost; (2) an anticipated inability to meet peak demand1 throughout the system in the short-term future; and (3) a [237] projected system-wide inability to meet average demand2 further into the future. A primary factor requiring a new supply is the growth of Rockland County’s population, though other factors include the contamination of six wells, the antiquation of the Stony Point treatment facility, the unavailability of water from the Ramapo Valley Well Field during periods of drought, and the aforementioned loss of water supply from Lake Tiorati.

During the course of extensive hearings, the inevitability of the need for an additional water supply became obvious; there was, however, a great deal of disagreement as to when this need would become manifest. The inherent uncertainty in determining precisely when the project would be necessary prompted Spring Valley and the Department of Public Service, which had expressed interest in increasing the peaking capacity of Spring Valley’s system, to suggest that a "trigger mechanism” tying the date of the project’s implementation to the demand for water be utilized. So that preliminary steps could be taken without authorizing premature construction and yet avoid a redundant new hearing which might perilously delay development of the proposed water supply, respondent Commissioner of Environmental Conservation (hereinafter the Commissioner) approved the project but "triggered” issuance of construction permits upon Spring Valley’s experiencing an average demand of 27.9 mgd for two consecutive years. Although Spring Valley expects to reach its maximum peak demand capacity well before it approaches the limit of its average demand capacity, the "trigger mechanism” was linked to the average demand because it more accurately reflects the relatively smooth trend of increased demand than the erratic peak demand which is heavily influenced by such vagaries as the weather. The point at which Spring Valley’s current peak demand capacity would be exhausted was approximated by divining an appropriate ratio between average and peak demands to determine at which average demand level the peak demand capacity would be exhausted; that average demand figure was then adjusted downwards to allow for the 3 to 4 years’ construction time required for the project. A regrettable and apparently inescapable consequence of the Ambrey Pond project is the likely destruction of a major naturally reproducing trout population due to the diversion of [238] most of the flow from Rockland County’s best trout stream into the Ambrey Pond Reservoir.

Following adoption of the Administrative Law Judge’s conditional approval of the Ambrey Pond project by the Commissioner, petitioners in two separate CPLR article 78 proceedings challenged the Commissioner’s determination as arbitrary and capricious, as an unlawful delegation of legislative authority to a private utility, and as being violative of the State Environmental Quality Review Act (hereinafter SEQRA) (ECL art 8). Supreme Court consolidated the proceedings and transferred them to this court.

Initially, we point out that the consolidated proceeding was improperly transferred. Where an administrative agency takes action as a result of an adjudicatory hearing, judicial review is sought by way of a CPLR article 78 proceeding in the nature of certiorari (CPLR 7803 [4]). If the agency’s findings of fact are challenged, the standard of review is the familiar substantial evidence test, and, where that issue is raised, the proceeding must be transferred to this court (CPLR 7804 [g]). However, where agency action is taken without a hearing, or where the hearing is discretionary or informational as opposed to adjudicatory and evidentiary such that the agency is acting in a legislative or rule-making role, judicial review is sought by way of a CPLR article 78 proceeding in the nature of mandamus to review (CPLR 7803 [3]). In such case, the standard of review is whether the agency’s action had a rational basis and, thus, was not arbitrary or capricious. As a result, the substantial evidence test is not at issue and transfer to this court is not authorized (Matter of Department of Envtl. Protection v Department of Envtl. Conservation, 120 AD2d 166, 169, lv denied 69 NY2d 921; Matter of Incorporated Vil. of Val. Stream v State of New York Pub. Serv. Commn., 107 AD2d 856, 857; Matter of Save the Pine Bush v Planning Bd., 83 AD2d 741, 742). In this case, the hearing conducted was not adjudicatory or quasi-judicial, but was informational (see, e.g., Matter of Save the Pine Bush v Planning Bd., supra). Thus, transfer to this court was inappropriate. However, in the interest of conservation of judicial resources, we choose to entertain the proceeding (see, CPLR 7804 [g]; Matter of Incorporated Vil. of Val. Stream v State of New York. Pub. Serv. Commn., supra).

Free access — add to your briefcase to read the full text and ask questions with AI

Hudson River Fisherman's Ass'n v. Williams, 139 A.D.2d 234, 531 N.Y.S.2d 379, 1988 N.Y. App. Div. LEXIS 7983 (N.Y. Ct. App. 1988).

139 A.D.2d 234 (Hudson River Fisherman's Ass'n v. Williams) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Matter of National Energy Marketers Assn. v. New York State Pub. Serv. Commn.
2018 NY Slip Op 7378 (Appellate Division of the Supreme Court of New York, 2018)
Matter of Village of Woodbury v. Seggos
2017 NY Slip Op 7512 (Appellate Division of the Supreme Court of New York, 2017)
Poster v. Strough
299 A.D.2d 127 (Appellate Division of the Supreme Court of New York, 2002)
Winston v. Freshwater Wetlands Appeals Board
254 A.D.2d 363 (Appellate Division of the Supreme Court of New York, 1998)
Secreto v. County of Ulster
228 A.D.2d 932 (Appellate Division of the Supreme Court of New York, 1996)
Sutherland v. Glennon
221 A.D.2d 893 (Appellate Division of the Supreme Court of New York, 1995)
Diaz v. New York State Office of Mental Health
188 A.D.2d 903 (Appellate Division of the Supreme Court of New York, 1992)
Holmes v. Coughlin
152 A.D.2d 807 (Appellate Division of the Supreme Court of New York, 1989)
McGraw-Hill, Inc. v. State Tax Commission
146 A.D.2d 371 (Appellate Division of the Supreme Court of New York, 1989)