Huckestein & Co. v. J. Kaufman & Bros.

33 A. 1028, 173 Pa. 199, 1896 Pa. LEXIS 682
CourtSupreme Court of Pennsylvania
DecidedJanuary 6, 1896
DocketAppeal No. 259
StatusPublished
Cited by4 cases

This text of 33 A. 1028 (Huckestein & Co. v. J. Kaufman & Bros.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huckestein & Co. v. J. Kaufman & Bros., 33 A. 1028, 173 Pa. 199, 1896 Pa. LEXIS 682 (Pa. 1896).

Opinion

Opinion by

Mr. Justice Dean,

The defendants, Kaufman & Bros., contracted with John Huckestein, a builder doing business as Huckestein & Company, for the erection of a building on Fifth avenue in the city of Pittsburg, for the price of $15,000, to be increased by any changes or additions subsequent to the contract, or during the progress of the work. This price, by subsequent additions, was largely increased. The first contract between the parties was made the 15th of June, 1892, and this, owing to important changes in design and height of building, was followed by three others within sixty days thereafter, whereby the design of the building was greatly changed; before any of the subsequent contracts with Kaufman & Brothers were reduced to writing, Huckestein on 29th of June, 1892, subcontracted the carpenter work to John Frazier, doing business as Frazier Brothers. By this contract, Frazier agreed to do all the carpenter work and furnish all the materials therefor, according to specifications, for the price of $15,000, subject to increase or diminution by change of plans and material; the price was largely increased by subsequent additions. All of the work and material to be subject to the approval of the supervising architect of Kaufman & Brothers. Payments were to be made Frazier as the work progressed, according to the estimate of value by the architect, as follows: When the second floor joists are in place, two thirds of the value of the work up to that point; a like two thirds when third floor joists are in place; and so on, making six distinct payments when the plastering was finished; then the seventh and final payment was to be made when all the work was completed to the satisfaction of the architect; this payment, it was stipulated, might be made by an order drawn by [202]*202Huckestein in favor of Frazier on Kaufman & Brothers. This last payment was not to be made until the architect certified that the work and material were approved and accepted by him. The building was completed February 13, 1893, and Kaufman & Brothers took possession. In the meantime, a number of payments had been made to Frazier by Huckestein, but the seventh and last had not been made, nor had the amount of it been determined.

The contract of Huckestein embodied a stipulation that before final payment to him by Kaufman & Brothers, the building was to be delivered free from all liens. There was also a provision for arbitration, if any dispute arose between owner and contractor concerning the value of any changes or additions to the original contract, and the decision of the arbitrators was to be final and binding on each of the parties. Kaufman refused to make final settlement and payment to Huckestein, until he procured from Frazier a release of right to file a mechanics’ lien. This obstacle to a settlement with Kaufman, brought Huckestein and Frazier into negotiations as to balance due Frazier. On the 2d of June, 1893, they met at the’ office of T. Baird Patterson, Esq., counsel for Frazier, who drew up an agreement, which was there signed by them. In this it was agreed that in consideration of an order for $6,750, given to Frazier by Huckestein on Kaufmans and release by Frazier of right of lien, Huckestein would at once proceed to obtain payment from Kaufman of the full amount yet due over and above the order on his contract as principal contractor; and in case the order was not paid by Kaufmans, would protect Frazier’s claim, and press arbitration against them for the full amount payable under the contract, and on the determination of this suit, then all differences between Huckestein and Frazier should be submitted to arbitration, as provided in the written contract between Huckestein and Frazier, such award to be final. In a subsequent agreement July 27, 1893, it was further agreed that Frazier should have the right to present and prove before the Huckestein-Kaufman arbitration, a bill of $4,971.98, for extra work on the building, for which Huckestein denied liability, but as the architect claimed this bill should be presented through the principal contractor, Huckestein consented it might be so presented, without any acknowledgment of liability therefor on his part.

[203]*203Huckestein filed a lien against Kaufman for the sum claimed by Mm as principal contractor, including tbe work and material of Frazier, the subcontractor. As both parties seem to have anticipated, Kaufman refused payment of the $6,750 order given to Frazier. Huckestein therefore assigned to Frazier that amount of Ms lien as a protection of Ms claim, until the final determination of the Kaufman arbitration. Notwithstanding Ms agreement with Huckestein, in consideration of the $6,750 order to file no liens, acting under the advice of counsel, Frazier, on the 19th of September, filed liens against the buildings, showing a balance due Mm of $16,630.84. Thereafter, Huckestein gave notice to Kaufman that he had revoked the $6,750 order given to Frazier and also notified Frazier that he revoked both order and assignment to him of $6,750 of lien. Huckestein without proceeding to judgment on Ms lien, brought an action of assumpsit against Kaufman, and recovered a judgment of $28,000. In the meantime, however, under the arbitration clause in the contract between Huckestein and Frazier, the latter had demanded an arbitration, and on September 8, 1893, they entered into a written agreement, reciting that differences had arisen between them as to the amount due Frazier “for work done and materials furnished in doing the carpenter work in the erection and construction, additions, alterations and improvements, of the Kaufman Buildings .... Now, for the purpose of adjusting said differences, it is hereby agreed to refer the same to three arbitrators,” as provided in the building contracts. Thereupon Frazier chose John Trimble, and Huckestein, Charles Simon, and the parties further agreed upon John W. Pryor as the third arbitrator, and that the arbitrators thus selected should proceed to ascertain the amount due Frazier “ for the work done and materials furnished in and about said Kaufman buildings, taking into consideration the work omitted and changes made, and the award so made shall be final and conclusive upon all parties of all accounts arising out of the work done and materials furnished in and about said building.” On the 11th of September, three days afterwards, the arbitrators met, and at that and many subsequent meetings heard the parties and. their proofs, and made tMs award: We “do now find under the submission to us, there is due from Huckestein & Company to Frazier Brothers, the sum of $3,539.58, and we award that [204]*204sum.” And thus matters stood when Huckestein obtained his judgment in assumpsit against Kaufman for $28,000. Kaufman then paid the amount of the judgment into court for distribution to those entitled. As Huckestein had made assignments of different amounts of his lien to a number of creditors beside Frazier, by agreement of counsel, and decree of the court, the distribution and all questions arising out of the same were referred to Thomas Herriott, Esq., who after full hearing, passed on all the questions of fact and law, and made report to the court; in this he found the amount payable to Frazier to be $8,539.80, the amount awarded by the arbitrators. Frazier filed exceptions, which the court overruled, and confirmed the report absolutely. From this decree Frazier appeals to this court.

In arriving at the amount due Frazier, the auditor found that bis full claim had been submitted to the arbitrators, and that under the terms of the submission he was concluded by their award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cutshall v. O'Brien
6 Pa. D. & C.2d 296 (Lehigh County Court of Common Pleas, 1955)
Duddy v. Conshohocken Printing Co.
90 A.2d 394 (Superior Court of Pennsylvania, 1952)
Eldridge v. Blue Ridge Tex. Co., Inc.
52 A.2d 330 (Superior Court of Pennsylvania, 1947)
Plankinton's Estate
61 A. 888 (Supreme Court of Pennsylvania, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
33 A. 1028, 173 Pa. 199, 1896 Pa. LEXIS 682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huckestein-co-v-j-kaufman-bros-pa-1896.