Huber v. Oliver County

529 N.W.2d 179, 1995 N.D. LEXIS 32, 1995 WL 78349
CourtNorth Dakota Supreme Court
DecidedFebruary 28, 1995
DocketCiv. 940346
StatusPublished
Cited by24 cases

This text of 529 N.W.2d 179 (Huber v. Oliver County) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huber v. Oliver County, 529 N.W.2d 179, 1995 N.D. LEXIS 32, 1995 WL 78349 (N.D. 1995).

Opinion

NEUMANN, Justice.

This is an appeal from summary judgment in favor of Oliver County. We affirm in part, reverse in part, and remand for further proceedings.

This dispute centers on a 1961 contract between Lloyd and Emma Huber and Oliver County. The contract grants a provisional qualified easement across the Hubers’ land to construct a farm-to-market road. The easement allowed the County to build the road entirely on the Hubers’ land rather than building it along the congressional section line. Building the road along the section line would have required crossing Otter Creek numerous times, each time at tremendous expense. By building the road immediately to the east, however, the crossings could be limited to two, one at either end of a small oxbow in the creek. The contract called for the installation of 24-inch squash culverts at each of the two points where the road crosses the oxbow. The County installed the culverts under the road and constructed a concrete diversion structure at the head of the oxbow. The concrete diversion structure was intended to force normal flows to continue along the oxbow, but it also permitted any excess to partially bypass the oxbow in times of extremely high runoff by running along the newly constructed road ditch. The contract also provided that “[i]n the event said culvert proves unsatisfactory for this purpose, then, and in that event, another method shall be examined and installed at the expense” of the County.

In the spring of 1962 the concrete diversion structure installed in 1961 washed out. After the washout, the creek channel changed. Normal flows began to follow the washed-out and deepened road ditch, rather than flowing through the Hubers’ oxbow. In 1963 the Hubers requested that the County repair the structure. In 1966 the County hauled in rock ballast in an attempt to force the stream back into its original channel. Almost immediately that, too, was washed out. Again, in 1978, Mr. Huber appeared before the county commissioners, requesting the reconstruction of the low-head dam to divert the stream back into its original oxbow channel, so that he might irrigate the adjacent land. Huber complained again in 1978 about the County’s inaction. Finally, in response to his complaints, in 1981 the County told Huber they would attempt to remedy the situation. The County attempted several more times to redirect the stream using rock ballast; however, each attempt failed. The County then employed an engineering firm to give estimates for the reconstruction of the original retention structure. The estimate exceeded $98,000. At this point the County refused to fund the construction.

On appeal the Hubers raise three issues. First, they claim that the trial court improperly found that the statute of limitations had expired; second, they claim that the trial court improperly concluded that they were not eligible to receive specific performance under their contract; and third, they claim the trial court improperly denied them an opportunity to appear and orally argue their motions before the court.

I. Hubers’ Statute of Limitations Claim

The trial court ruled that the proper statute of limitations to be applied in this case is NDCC § 28-01-15. 1 Apparently this was due to the fact that the Hubers’ contract with the County was contained in an instrument granting the County an easement across their land. An easement is defined at least in part as “[a]n interest which one person has in the land of another.” Black’s Law Dictionary 509 (6th ed. 1990). Granting *182 another an interest in real property necessarily “affect[s] the title to real property.” NDCC § 28-01-15(2) (1991). Therefore, on the record before us, we cannot say that the trial court erred in applying this statute of limitations.

Based on the trial court’s ruling, the Hubers’ action had to have been “commenced within ten years after the claim for relief ha[d] accrued.” NDCC § 28-01-15. “The application of the statute of limitations is a legal bar to a cause of action. If it is applicable the claim ceases to be a legal obligation and becomes a mere moral one which the law will not lend its aid to enforce.” Hagen v. Altman, 79 N.W.2d 53, 58-59 (N.D.1956). The statute of limitations begins to run when the underlying cause of action accrues. Keller v. Clark Equipment Co., 474 F.Supp. 966, 969 (D.N.D.1979), aff'd, 715 F.2d 1280 (8th Cir.1983), cert. denied, 464 U.S. 1044, 104 S.Ct. 713, 79 L.Ed.2d 176 (1984). The Legislature has not defined when a cause of action has accrued; in the absence of such a definition, it is for the judiciary to determine what controls the “accrual” of an action. Hebron Pub. Sch. Dist. v. United States Gypsum Co., 475 N.W.2d 120, 121 (N.D.1991). “A cause of action accrues when the right to commence it comes into existence; when it can be brought in a court of law without being subject to dismissal for failure to state a claim.” Keller, 474 F.Supp. at 969. We have recognized that “[a]n injury usually arises contemporaneously with the wrongful act causing the injury.” Erickson v. Scotsman, Inc., 456 N.W.2d 535, 537 (N.D.1990).

A plain language reading of the contract in the instant ease contemplates the possibility that the County’s provisions to keep water flowing through the Hubers’ oxbow might, over time, prove inadequate. As noted, the contract provides that if the “culvert proves unsatisfactory^] ..'. another method shall be examined and installed at the expense” of the County. However, the contract fails to establish any time limit within which the County is required to accomplish such an alternative remedy. Where the parties have failed to specify a time for performance, the law will allow a reasonable time. NDCC § 9-07-22 (1987). Determination of what a reasonable time may be is a question of fact, depending upon the particular circumstances of each case. First Nat’l Bank of Belfield v. Bunch, 367 N.W.2d 148, 154 (N.D.1985).

The instant case comes to us from a summary judgment.

Summary judgment is appropriate when, after viewing the evidence most favorable to the party against whom summary judgment is sought, there is no genuine issue of material fact in dispute, and the moving party is entitled to judgment as a matter of law. Even if a factual dispute exists, summary judgment is appropriate if its resolution will not alter the result. Such facts are not material.

Berg v. Lien, 522 N.W.2d 455, 456 (N.D.1994) (citations omitted). In order to determine when the statute of limitations expired for the Hubers, it must be determined when the County failed to perform its obligation under the contract. Determining when a plaintiff’s cause of action has accrued is generally a question of fact. Schmidt v. Grand Forks Country Club, 460 N.W.2d 125, 129 (N.D.1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Landowners Association, et al. v. State, et al.
2025 ND 147 (North Dakota Supreme Court, 2025)
Ordahl v. Lykken
2022 ND 193 (North Dakota Supreme Court, 2022)
Hartman v. Grager
2021 ND 160 (North Dakota Supreme Court, 2021)
Johnson v. Johnson
2017 ND 125 (North Dakota Supreme Court, 2017)
Locken v. Locken
2011 ND 90 (South Dakota Supreme Court, 2011)
State v. Duncan
2011 ND 85 (North Dakota Supreme Court, 2011)
Dunford v. Tryhus
2009 ND 212 (North Dakota Supreme Court, 2009)
Clark v. State
2008 ND 234 (North Dakota Supreme Court, 2008)
Gosbee v. Martinson
2005 ND App 10 (North Dakota Court of Appeals, 2005)
Interest of K.N.H.
2005 ND App 9 (North Dakota Court of Appeals, 2005)
Tarnavsky v. McKenzie County Grazing Ass'n
2003 ND 117 (North Dakota Supreme Court, 2003)
Abel v. Allen
2002 ND 147 (North Dakota Supreme Court, 2002)
Whiteman v. State
2002 ND 77 (North Dakota Supreme Court, 2002)
Syvertson v. State
2000 ND 185 (North Dakota Supreme Court, 2000)
Huber v. Oliver County
1999 ND 220 (North Dakota Supreme Court, 1999)
Owens v. State
1998 ND 106 (North Dakota Supreme Court, 1998)
American Insurance Co. v. Midwest Motor Express, Inc.
554 N.W.2d 182 (North Dakota Supreme Court, 1996)
Diocese of Bismarck Trust v. Ramada, Inc.
553 N.W.2d 760 (North Dakota Supreme Court, 1996)
M.L.L. v. Wessman
532 N.W.2d 653 (North Dakota Supreme Court, 1995)
Bakes v. Bakes
532 N.W.2d 666 (North Dakota Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
529 N.W.2d 179, 1995 N.D. LEXIS 32, 1995 WL 78349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huber-v-oliver-county-nd-1995.