Huber, Hunt & Nichols, Inc. v. United Association Of Journeymen And Apprentices Of The Plumbing And Pipefitting Industry, Local 38

282 F.3d 746, 2002 Daily Journal DAR 2653, 2002 Cal. Daily Op. Serv. 2127, 169 L.R.R.M. (BNA) 2641, 2002 U.S. App. LEXIS 3545
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 6, 2002
Docket00-17085
StatusPublished
Cited by1 cases

This text of 282 F.3d 746 (Huber, Hunt & Nichols, Inc. v. United Association Of Journeymen And Apprentices Of The Plumbing And Pipefitting Industry, Local 38) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huber, Hunt & Nichols, Inc. v. United Association Of Journeymen And Apprentices Of The Plumbing And Pipefitting Industry, Local 38, 282 F.3d 746, 2002 Daily Journal DAR 2653, 2002 Cal. Daily Op. Serv. 2127, 169 L.R.R.M. (BNA) 2641, 2002 U.S. App. LEXIS 3545 (9th Cir. 2002).

Opinion

282 F.3d 746

HUBER, HUNT & NICHOLS, INC., Plaintiff-Counter-Defendant-Appellant,
v.
UNITED ASSOCIATION OF JOURNEYMEN AND APPRENTICES OF THE PLUMBING AND PIPEFITTING INDUSTRY, LOCAL 38, Defendant-Counter-Claimant-Appellee.

No. 00-17085.

United States Court of Appeals, Ninth Circuit.

Argued and Submitted October 19, 2001.

Filed March 6, 2002.

James Watson, Stanton, Key & Watson LLP, San Francisco, CA, for the plaintiff-counter-defendant-appellant.

Geoffrey Piller, Beeson, Tayer & Bodine, P.C., San Francisco, CA, for the defendant-counter-claimant-appellee.

Appeal from the United States District Court for the Northern District of California, Charles R. Breyer, District Judge, Presiding. D.C. Nos. CV-00-0578-CRB, CV-00-2377-CRB.

Before: BEEZER, TROTT and TALLMAN, Circuit Judges.

BEEZER, Circuit Judge.

In this case, two arbitrators claim the power to decide a labor dispute under the same umbrella labor agreement. The parties to the agreement disagree over which arbitrator had power to arbitrate, what type of grievance was before the arbitrators and whether both grievances concerned the same dispute. Each party asks us to confirm one award and vacate the other.

The district court held that, under the circumstances, the question of arbitrability turned on analysis of the grievances rather than on analysis of the agreement. We have jurisdiction, and we reverse.

* The facts are undisputed. Appellant Huber, Hunt & Nichols, Inc. (the "General Contractor") was hired to build Pacific Bell Park, the new ballpark of the Giants baseball club in San Francisco, California. Workers from several AFL-CIO-affiliated unions, including appellee United Association of Journeymen and Apprentices of the Plumbing and Pipefitting Industry, Local 38 ("Local 38"), were hired to perform the construction work. The General Contractor and the unions entered into a prehire agreement1 (the "Project Stabilization Agreement" or "Agreement") reconciling the terms of the unions' various collective bargaining agreements for the duration of construction. The Agreement lists and incorporates by reference the unions' collective bargaining agreements, but makes them unenforceable to the extent that they are "contrary to or in conflict with" the Agreement or "the intent and meaning" thereof.

The Project Stabilization Agreement recites an intent to prevent delays and promote efficiency by establishing grievance procedures for settling "all misunderstandings, disputes or grievances which may arise" during construction of the ballpark. Article 5 of the Agreement requires that jurisdictional disputes2 be decided by discussions between the adverse unions' local leadership or, failing that, their international leadership. Article 6 requires that non-jurisdictional disputes "concerning any application or interpretation of the Project Stabilization Agreement" be decided by a designated project-wide arbitrator (the "Permanent Arbitrator"). Non-jurisdictional disputes concerning any application or interpretation of an incorporated collective bargaining agreement, in contrast, are to be decided according to that collective bargaining agreement's "applicable grievance procedure." Local 38's collective bargaining agreement specifies that grievances arising under it are to be decided by an arbitration committee, half of whom must be members of Local 38 (the "Local Committee" or "Committee").

After construction commenced, Local 38 filed a grievance against the General Contractor with the Local Committee. Local 38 claimed that a subcontractor had violated Local 38's collective bargaining agreement by assigning work to carpenters and laborers that should have been assigned to Local 38 pipefitters.3 Local 38 sought contract damages in the amount of lost wages.

In response, the General Contractor filed a grievance against Local 38 with the Permanent Arbitrator. The General Contractor claimed that Local 38's grievance violated the Project Stabilization Agreement by bypassing the Agreement's Article 5 procedures for resolving jurisdictional disputes. The General Contractor asked that Local 38 be ordered to resolve the dispute pursuant to Article 5 instead of by arbitration before the Local Committee. Each party denied that the other's grievance was arbitrable. Each refused to make an appearance in the other's grievance proceeding.4

The Permanent Arbitrator issued an award. He concluded that he had power to decide the grievance before him and that the work assignment question was a jurisdictional dispute. He ordered Local 38 to use the Article 5 jurisdictional dispute resolution procedure instead of arbitration.

A week later the Local Committee issued an award. The Committee determined that it had power to decide the grievance before it and that the work assignment question was not a jurisdictional dispute. The Committee ruled that the General Contractor had violated Local 38's collective bargaining agreement and awarded lost wages as contract damages.

The General Contractor and Local 38 sued each other in federal court. Each sought to have its own award confirmed and the other's vacated. The district court granted summary judgment in favor of Local 38. The General Contractor appeals.

The district court had jurisdiction over this action "for violation of contracts between an employer and a labor organization...." Labor Management Relations Act § 301(a), 29 U.S.C. § 185(a) (1998). See Millmen Local 550, United Bhd. of Carpenters & Joiners v. Wells Exterior Trim, 828 F.2d 1373, 1375 (9th Cir.1987). We have jurisdiction pursuant to 28 U.S.C. § 1291.

II

We address whether the arbitrators had the power to arbitrate the matters before them. Arbitrability is generally a question for the court, rather than the arbitrator, except where a broad arbitration clause is susceptible to more than one interpretation on the question of arbitrability. United Food & Commercial Workers Union, Local 770 v. Geldin Meat Co., 13 F.3d 1365, 1370 (9th Cir.1994); Southern Cal. Dist. Council of Laborers v. Berry Constr., Inc., 984 F.2d 340, 344 (9th Cir.1993). We conclude that only the Permanent Arbitrator had power to arbitrate. The text, structure and context of the Project Stabilization Agreement assign to him the threshold determination whether or not a dispute is jurisdictional. The Permanent Arbitrator's award must be confirmed and the Local Committee's award vacated.

A.

The Permanent Arbitrator made the first ruling. He ruled that the dispute before him was jurisdictional. Local 38 contends that the Permanent Arbitrator lacked the power to issue his award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chastain v. Union Security Life Insurance
502 F. Supp. 2d 1072 (C.D. California, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
282 F.3d 746, 2002 Daily Journal DAR 2653, 2002 Cal. Daily Op. Serv. 2127, 169 L.R.R.M. (BNA) 2641, 2002 U.S. App. LEXIS 3545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huber-hunt-nichols-inc-v-united-association-of-journeymen-and-ca9-2002.