Hubeny Bros., Inc. v. United States

161 Ct. Cl. 838, 1963 U.S. Ct. Cl. LEXIS 95, 1963 WL 8549
CourtUnited States Court of Claims
DecidedMay 10, 1963
DocketNo. 529-58
StatusPublished

This text of 161 Ct. Cl. 838 (Hubeny Bros., Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hubeny Bros., Inc. v. United States, 161 Ct. Cl. 838, 1963 U.S. Ct. Cl. LEXIS 95, 1963 WL 8549 (cc 1963).

Opinion

Per Curiam:

This is a suit by plaintiff to recover $360,921.60 claimed to be due under a price redetermination of contract No. DA 30-069-OBD-938 entered into on September 5, 1952, with the Department of the Army for the production and delivery of ninety-millimeter shells. The complaint shows that the parties executed a supplemental agreement to the contract on June 4, 1957, wherein it was stated that plaintiff accepted a sum of $324,748.25 as “a full and complete settlement for complete performance of the contract”. Plaintiff contends that this instrument is not a valid waiver or relinquishment of plaintiff’s claim herein, alleging that it was obtained by economic duress. Defendant has asserted two affirmative defenses in which it contended that plaintiff’s execution of the supplemental agreement and receipt of the sum thereunder constituted a full and complete settlement of all sums due to plaintiff under the contract, creating an accord and satisfaction, and that plaintiff was guilty of laches in having failed to assert that any further sums were due it under the contract when it executed the supplemental agreement and received the sum due thereunder. Upon consideration of the pleadings filed herein, the argument of counsel for the parties and the findings of fact of the trial commissioner, the court approves the said findings and concludes that the plaintiff has failed to make a sufficient showing of duress in execution of the supplemental agreement and therefore that the settlement reached thereunder is binding. Plaintiff is not entitled to recover and its petition is dismissed.

[840]*840The court, having considered the evidence, the report of Trial Commissioner Saul Richard Gamer, and the briefs and argument of counsel, makes findings of fact as follows:

1. Plaintiff is, and at all times pertinent hereto has been, a corporation organized and existing under the laws of the State of New Jersey, with its principal place of business in Roselle, New Jersey. Plaintiff manufactures metal products for both civilian and military use.

2. Under date of September 5,1952, plaintiff entered into a contract (No. DA-30-069-ORD-938) with defendant, acting by a contracting officer of the New York Ordnance District, Department of the Army, whereby plaintiff was to furnish and deliver to defendant, over a period of 18 months ending in February 1954, 115,800 90 MM shells at a unit price of $15.13, thereby making the total price $1,752,054. The contract contained a “Price Redetermination” provision under which, upon completion of delivery of 40 percent of the shells, the parties were required to negotiate to revise the price thereof. The contract provided, however, that the total maximum revised contract price could not exceed $1,875,653.80.

Thereafter, the contract was, by change orders and supplemental agreements, modified over 80 times. By supplemental agreements Nos. 77 and 82, dated June 11, 1955 and August 15, 1955, respectively, the contract was amended to provide for the delivery of 160,300 shells through June 1956 at a total contract price of $3,648,322.39, with the revised contract price not to exceed $4,166,641.34.

The contract, as amended through said supplemental agreement No. 82, also contained the following provisions:

2. Changes
The Contracting Officer may at any time, by a written order * * * make changes, within the general scope of this contract, in any one or more of the following: (i) drawings, designs, or specifications, where the supplies to be furnished are to be specially manufactured for the Government in accordance therewith; * * *. If any such change causes an increase or decrease in the cost of, or the time required for, performance of this [841]*841contract, an equitable adjustment shall be made in the contract price or delivery schedule, or both, and the contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled “Disputes.” * * *
7. PAYMENTS
The Contractor shall be paid, upon the submission of properly certified invoices or vouchers, the prices stipulated herein for supplies delivered and accepted or services rendered and accepted, less deductions, if any, as herein provided. Unless otherwise specified, payment will be made on partial deliveries accepted by the Government when the amount due on such deliveries so warrants; or, when requested by the Contractor, payment for accepted partial deliveries shall be made whenever such payment would equal or exceed either $1,000 or 50 percent of the total amount of this contract.
$ * $ $ *
12. Disputes
Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the Secretary, and the decision of the Secretary or his duly authorized representative for the hearing of such appeals shall be final and conclusive: Provided, That if no such appeal is taken, the decision of the Contracting Officer shall be final and conclusive. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract [842]*842and in accordance with the Contracting Officer’s decision.
3$ $ ‡ ‡ $
36. Price redetermination * * *
(a) The prices stated herein may be increased or decreased in accordance with this clause. In no event shall the revised price exceed $4,166,641.34.
(b) Times for negotiation.
(1) Upon completion of delivery of 40 percent of Item 1 to be furnished under this contract, the parties shall negotiate to revise the prices of all items theretofore and thereafter to be delivered. Within not to exceed thirty (30) days after the completion of delivery referred to above, the Contractor shall furnish to the Contracting Officer the statements and data referred to in paragraph (c) of this clause. At any time and from time to time after the completion of delivery referred to above, subject to the limitations specified in this clause, either the Government or the Contractor may deliver to the other a written demand that the parties negotiate to adjust the prices under this contract. No demand shall be made prior to 90 days after completion of delivery referred to above, and thereafter neither party shall make a demand having an effective date within 90 days of the effective date of any prior demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
161 Ct. Cl. 838, 1963 U.S. Ct. Cl. LEXIS 95, 1963 WL 8549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hubeny-bros-inc-v-united-states-cc-1963.