Hubbard v. Norton

28 Ohio St. (N.S.) 116
Ohio Supreme Court·Decided December 15, 1875·Published

Opinion

Johnson, J.

Three objections are made to the judgment in this case:

First. That the board of improvements should not only have recommended to the council the improvement, but that an assessment would be necessary to pay for the same, and the proper amount to be assessed. That such report, that an assessment would be necessary and the proper amount, is as much a condition precedent, as a report in favor of such improvement.

Second. That the city extended the time for the performance of the work from December 1, 1869, to August 1, 1870, without authority of law.

Third. That the contract was obtained from the city by fraud practiced on the city council and on the property owners.

I. "Was it necessary to the validity of the action of the city council that the board of improvements should have recommended not only the improvement, but that an assessment would be required to pay for the same, and the amount thereof?

In Welker v. Potter, 18 Ohio St. 85, it was held: “ That the adoption of the resolution declaring the improvements necessary, etc., were conditions precedent to the exercise of authority to pass a valid ordinance or make an assessment on adjoining property to pay for them;” and it is claimed, for the same reasons, that the board of improvements must report, “ that an. assessment will be required to pay for the same and the proper amount to be assessed; ” and that such report is as much a condition precedent as the recommendation of the improvement itself.

[126]*126'We do not concur in this view. The statute (2 S. & O. 1526, sec. 105) provides that, “in all cities of the first-class, where there shall be a board of city improvements, no improvement or repair in relation to streets, sewers, or bridges shall be ordered or directed by the city council, except on the report and recommendation of said board. All petitions from owners of property in relation to such improvements shall be presented to such board, who shall report from time to time to the city council when any such improvement is necessary or proper, and when an assessment is required, and the proper amount to be assessed ; and the city council shall take such action thereon as may be deemed proper.”

The statute does not vest in the board of improvements the power to determine when an improvement shall be paid for by an assessment. The mode of payment must either be determined by the law, or, when not, by the council.

If no assessment is required, as if the improvement is to be paid for out of the general fund, then no such report is necessary or required.

In cases where it is required, the amount must be ascertained before an assessment can bo reported. Until the contract is awarded, the amount can not be ascertained. Before that it would be an estimate.

The statute says no improvement or repair shall be ordered, except on the report and recommendation of the board of improvements; but it does not say it shall not be ordered, except on a report that an assessment would be required, and the proper amount required. These duties of the board are not conditions precedent, like the report and recommendation of the improvement.

II. It is claimed that in law this contract expired December 1, 1869, the time the work was to have been completed; that prior to that time no work had been done under it, and that the action of the city council on the 29th of November, 1869, in extending the time of performance to August 1,1870, was in fact equivalent to making a new. contract, and required, under sections 97 and 98 of the mu[127]*127nicipal code, the assent of a majority of all the members elected to grant such extension.

Section 97, aforesaid, provides that “all ordinances and resolutions, and all by-laws for the government of the council, shall require for their passage or adoption the concurrence of a majority of ail the members elected.”

If, therefore, the action of the city council on the 29th of November comes within the purview of this section, it was illegal, as but seven out of sixteen members voted in its favor.

To determine this we must look to the record to see what the facts were, and what action, if any, was necessary to warrant the contractors in taking further time to complete the job.

The record discloses the fact that prior to November 29th the contractors had rented a dock, and made contracts for the delivery of stone from Buffalo, and had delivered a small quantity ready for use in paving, but were unable to get possession of the street to grade and pave, because one Welker, who had the contract for bringing the street to grade, had not completed his work, and in fact did not do so until about the last of April, 1870. In this condition of things, the contractors sent a petition to council, representing that they had all the material contracted for, and a portion delivered, and that they were ready and anxious to proceed whenever the street was delivered into their hands, but that the grading was let in a separate contract to other parties, and was not completed. Eor these reasons they asked an extension of time. Their request was granted by a vote of seven to five, there being only twelve out of sixteen members present.

It does not appear there was any want of diligence by the contractors, or that they were otherwise in default; on the contrary, it clearly appears that the delay was one for which they were not responsible.

The contract provided that in the event of failure of the contractors to perform their covenants, the city had the option to declare it forfeited, and re-let the work, or to em[128]*128ploy others to complete the work, and charge them with the difference.

There was no forfeiture if the work was not done within the time, except at the option of the city.

If it did not choose to exercise that option, the contractors might continue their work, and the right to exercise such option depended on the contractors being in default.

In this case the delay was not theirs, and hence no cause for forfeiture existed.

The municipal code took effect July 1, 1869.

By caution 725 all rights and liabilities, either in favor of or against the city, which existed when the code took effect, were expressly saved ; so that if this was a subsisting valid contract July 1, 1869, and was not thereafter forfeited, it continued to be such valid obligation without the assent of the council to the extentions of time.

It was an act of prudence to obtain such consent, but, under the circumstances, was unnecessary.

But, admitting that the contractors were in default, it was within the discretion of the city authorities to declare a forfeiture, and re-let the work, or to allow them to complete it.

In the exercise of that discretion they acted as the legal representatives of the public, including these plaintiffs in error. By their action, in good faith and within the scope of their authority — and there is no impeachment of their conduct in this case — the tax-payer is bound.

Time is. not of the essence of the contract, unless made so by its terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Hubbard v. Norton, 28 Ohio St. (N.S.) 116 (Ohio 1875).

28 Ohio St. (N.S.) 116 (Hubbard v. Norton) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.