Hub Electric Co. v. Aetna Casualty & Surety Co.

400 F. Supp. 77
CourtDistrict Court, E.D. Michigan
DecidedAugust 4, 1975
DocketCiv. A. No. 74-10048
StatusPublished
Cited by3 cases

This text of 400 F. Supp. 77 (Hub Electric Co. v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hub Electric Co. v. Aetna Casualty & Surety Co., 400 F. Supp. 77 (E.D. Mich. 1975).

Opinion

[78]*78MEMORANDUM OPINION

JAMES HARVEY, District Judge.

These are motions for summary judgment, one having been filed by plaintiff, Hub Electric Company, Inc. (Hub), and the other by defendants Aetna Casualty and Surety Company (Aetna) and Gust Construction Company, Inc. (Gust). In 1972, Gust contracted with defendant Crawford-Ausable School District to construct a high school in Grayling, Michigan. Pursuant to the express terms of the contract, and as required by 1963 P.A. 213 (M.C.L.A. § 129.201 et seq.), the Michigan Public Works Bonding Statute, Gust executed a labor and materials bond. Aetna is the surety on that bond. As work progressed, plaintiff provided electrical fixtures and supplies valued at $28,702.40, which were actually used in the construction. It seems to be agreed that plaintiff has been paid only $8,003.60, and this suit is an attempt to recover the balance.

Three of the five counts of the Complaint are directed at Aetna, and represent attempts by plaintiff to recover on the bond. The issues raised in these motions go directly to plaintiff’s ability to do so, either as a materialman (as alleged in Counts I and II), or as a subcontractor (as alleged in Count V). The Court must determine whether plaintiff is a “claimant” as recognized by Section 6 of the Bonding Statute (M.C.L.A. § 129.206), and if so, whether plaintiff gave the proper statutory notice to defendant as is required by Section 7 (M. C.L.A. § 129.207), for it to recover as a materialman.

A “claimant” is defined in Section 6 of the Bonding Statute as:

“ . . .a person having furnished labor, material, or both, used or reasonably required for use in the performance of the contract. ‘Labor and material’ includes that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the contract.”

Two classes of “claimants,” laborers and materialmen, may seek the protection of the bond under Section 6. It is undisputed that plaintiff is a material-man, and the plain language of the statute would thus seem to settle the issue without further consideration. But as noted in a prior opinion of this Court, the Michigan Supreme Court has chosen to distinguish some materialmen from others. Defendant’s claim is that plaintiff falls within the class of materialmen who are excluded from the Statute’s protection, i. e., that plaintiff is a material-man to a materialman. See People v. Wayne Electric Motor Company, 269 Mich. 537, 257 N.W. 877 (1934).

Before determining plaintiff’s status as a claimant, however, the requirements of Section 7 of the Statute must be examined, for if plaintiff failed to provide defendant with the notice required therein, then under no circumstances can it recover as a materialman. Section 7 requires a “claimant not having a direct contractual relationship with the principal contractor” to serve notice on the latter within thirty days of first supplying materials informing him of the nature of such materials being or to be supplied and to, in addition, give written notice to the principal contractor and the governmental unit involved within ninety days of the date upon which materials were last supplied, stating the amount claimed and the name of the party to whom the material was supplied.

Plaintiff’s complaint, Count I, Paragraph 9 states that plaintiff first furnished material on March 9, 1972, and last furnished material on December 10, 1973. To comply with the statute, the first required notice should have been sent by April 8, 1972. No notice was actually sent until October 18, 1973. That notice purported to be sent pursuant to the provisions of the bond and the laws of Michigan. It noted that certain 'materials had not yet been shipped. A second notice dated December 20, 1973, followed when the shipment had been [79]*79completed. Thus, the notice requirements which plaintiff provided complied with the ninety day requirement of Section 7, but no thirty-day notice was given.

A copy of the bond is attached to the Complaint. Its only requirement regarding the giving of notice is that a claimant who has not been paid so notify the contractor and surety within ninety days of the last delivery. Plaintiff has thus complied with all the requirements of the bond. The only question is whether plaintiff’s claim is defeated by its failure to comply with the initial thirty-day requirement of the statute. Plaintiff argues that the thirty-day requirement is not important, and that defendants can show no prejudice or injury by failure of plaintiff to provide such notice. Therefore, plaintiff concludes that its failure should be excused.

Plaintiff correctly notes that all of the cases which have dealt with the notice requirements of the Public Works Bonding Statute have always referred to the final notice requirement. This is true, but only because the prior act, 1905, P. A. 187 (M.S.A. § 26.321 et seq., M.C.L. A. § 570.101 et seq.) contained but a single notice requirement, that being within sixty days after furnishing the last material. All the cases which have discussed the notice requirements have dealt with the prior act. While 1963 P. A. 213 has been in force for over a decade, its new thirty-day initial notice requirement has never been construed by the Appellate Courts in Michigan. No implication can be derived from this which would indicate that the requirement is not necessary or important to establishing a claim under the present statute.

Plaintiff has argued that the Michigan Courts have held that the failure of a claimant to comply with the notice requirement under the prior statute have not barred the claim unless the defendants can show prejudice or injury. The cases which plaintiff cites in support have no applicability to the present case. New Jersey Terre Cotta Co. v. Traves, 188 Mich. 415, 154 N.W. 120 (1915), and People v. Connell, 195 Mich. 77, 161 N.W. 844 (1917), predate amendments to the Statute in 1925 and 1927 which apparently evidenced a concern for the protection of the surety. In People v. Michigan Surety Co., 360 Mich. 546, 104 N.W.2d 213 (1960), the history of the statute is briefly discussed, the point being that the old rule regarding lack of prejudice to the surety lost its validity with the holding in People v. W. L. Than Co., 307 Mich. 273, 11 N.W.2d 886 (1943). The most recent case to discuss the mandatory nature of the notice requirement is People v. Cooke Contracting Co., 372 Mich. 563, 127 N.W.2d 308 (1964). It is certain that the predecessor of the present public works bonding statute required strict adherence to the notice requirement for a claimant to seek to recover on the bond. The purpose of that rule was to protect the surety from becoming the “virtual insurer of all debts” and from having to “supervise the activities of contractors and subcontractors far beyond what is necessary under this statute.” Id. p. 566, 127 N.W.2d p. 309. There is no reason to believe that the present statute does not serve the same goals or that strict compliance with its notice requirements is not mandatory.

As has been noted, the bond in question here omitted any reference to the initial thirty-day requirement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skyline Steel Corp. v. A.J. Dupuis Co.
648 F. Supp. 360 (E.D. Michigan, 1986)
Hub Electric Co. v. Gust Construction Co.
585 F.2d 183 (Sixth Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
400 F. Supp. 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hub-electric-co-v-aetna-casualty-surety-co-mied-1975.