Hoyt v. Greene

33 Mo. App. 205, 1888 Mo. App. LEXIS 460
CourtMissouri Court of Appeals
DecidedDecember 11, 1888
StatusPublished
Cited by1 cases

This text of 33 Mo. App. 205 (Hoyt v. Greene) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoyt v. Greene, 33 Mo. App. 205, 1888 Mo. App. LEXIS 460 (Mo. Ct. App. 1888).

Opinion

Rome aube, P. J.,

delivered the opinion of the court.

The defendant Greene contracted with the plaintiff to erect for him a two-story factory building according t o certain specifications, and'gave bond for the faithful performance of the contract with his co-defendants as [208]*208sureties. The bond was conditioned among other things that Greene would perform the contract and hold the plaintiff harmless and indemnified from and against all and every claim, demand, judgments, liens and mechanic’s liens, costs and fees of every description, incurred in suit or otherwise, that may be had against him or against the buildings to be erected. The contract provided that the last installment of $2,450 should be paid Greene when the building was completed and accepted.

This action is brought on the bond given by Greene. The plaintiff claims that he was compelled to pay $1,080.52 on a mechanic’s lien judgment and one hundred dollars for attorney’s fees in defending against the lien. Also that he was compel led to pay $228.02 for completing the roof, and one hundred and thirty-five dollars- for painting the outside of the roof, items of expense caused by non-completion of the contract in conformity with the specifications. That the whole amount thus paid by him was $422.54 in excess of money due Greene under the contract, and that by the failure on part of Greene to complete said contract he incurred said additional expenses, wherefore he sues on the bond.

The answer denies that there was any failure on part of Greene to perform the contract so far as protecting the plaintiff ’ s property against liens is concerned; admits the bringing of the lien suit, but claims that the same was defended by Greene at plaintiff’s request, and avers that in said suit the question as to whether Greene did complete the contract in conformity with the specifications was fully adjudicated, whereby that question became res judicata. The answer further denies that the one hundred dollars counsel fees paid by plaintiff were necessarily paid by plaintiff in defending against any lien claim, and states there is still a balance of sixty dollars due the defendant Greene by the terms of the [209]*209contract for which he asks judgment. The new matter in the answer was denied by reply.

The cause was tried by the court without the intervention of a jury, and the parties adduced evidence tending to show the following facts: The plaintiff let the contract to Greene for the entire building under certain specifications, and Greene sub-let the contract for the corrugated iron roofing which was to be of a certain make under the identical specifications to Mesker. When the building was completed, the plaintiff claimed that the ironroofing was not done according to specifications. He wrote to the defendant Greene suggesting to him not to settle with Mesker until the roof was inspected by an expert, and he, plaintiff, was satisfied that it had been put up in accordance with the specifications. The defendant Greene and Mesker thereupon called on plaintiff who refused to pay the balance of about $1,121, still in his hands, and Mesker brought suit for $1,664, which he claimed was due him under his contract with Greene, against Greene as contractor and Hoyt as owner. This claim, however, he reduced to $1,097 before the trial, and recovered judgment thereon for$1,082.50, which judgment the plaintiff subsequently paid.

Upon the trial of the present action the plaintiff gave evidence tending to show that the roof was not constructed in conformity with the specifications and that he paid the amounts as claimed in his petition to have it thus completed ; also that he paid to his counsel in the Mesker lien suit one hundred dollars, which was a reasonable fee. The defendant gave evidence tending to show that the roof was completed according to specifications, that he, Greene, defended the lien suit of Mesker at plaintiff’s request, and employed and paid his own counsel; that the plaintiff himself caused the witnesses to be subpoenaed in the Mesker suit, who were to prove that the roof had not been properly constructed. That [210]*210issue was fully and fairly gone into in that suit, and the finding of the court therein was that the roof had been completed in conformity with the specifications.

This being the evidence the plaintiff requested the court to declare that under the pleadings and evidence the plea of res adjudícala, in defendant’s answer cannot be sustained.' This instruction the court refused.

The defendant requested the court to declare, in substance, that if it found that the refusal to pay the sub-contractor on account of which the lien proceeding was instituted was at the instance or by advice of plaintiff the owner, and that the owner had in his hand at beginning of such suit moneys belonging or coming to the the contractor enough or more than sufficient to pay the judgment recovered therein, and that Greene employed and paid his own counsel in' said suit, then within the meaning of the bond there was no breach thereof or damage sustained thereby, notwithstanding that plaintiff employed and paid counsel in defense of said suit. This instruction was also refused.

The court thereupon rendered judgment in favor of plaintiff for $109.65 on the theory that plaintiff was not entitled to recover amounts paid by him as claimed above the contract price for completion of the roof, but was entitled to recover counsel fees paid by him in the said lien suit with interest. Both parties appeal.

It is stated as a general rule in Freeman on Judgments, section 158, that “parties to a judgment are not bound by it in a subsequent controversy between each other, unless they are adversary parties in the original action.” As a general rule this is correct, and as such has been repeatedly approved by our own supreme court. Miller v. Gillespie, 59 Mo. 220 ; McMahan v. Geiger, 73 Mo. 145. The sole reason of the rule, however, is that unless they were adversary parties, the identical question which arises on the second action was not likely to have' been litigated in the former action, as was the [211]*211case in McMahan v. Geiger, supra, or the person against whom the judgment is invoked had no right to control the proceedings as to his co-defendant in the former action, as was the case in Miller v. Gillespie, supra.

Where, however, it conclusively appears that the identical question was litigated, and that the party against whom the former adjudication is invoked did litigate it, and had a right to control the proceedings, or where the litigation was carried on in his interest by one primarily liable, and he had notice and a right to control the proceedings, the reason of the rule falls away, and the rule itself has no application. Cessante ralione cessat lex. In Strong v. Phoenix Ins. Co., 62 Mo. 299 ; Wood v. Unset, 63 Mo. 193; Missouri Pacific Ry. Co. v. Levy, 17 Mo. App. 508, and Landis v. Hamilton, 77 Mo. 565, the parties against whom the former adjudication was invoked were not even parties in the former proceeding, nor privies in a strict semse of the term, yet they were held to be conclusively bound by it on the ground that they participated in a litigation with a right to control the proceedings, and this litigation was carried on in their interest, or for their ultimate benefit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Comstock v. Keating
91 S.W. 416 (Missouri Court of Appeals, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
33 Mo. App. 205, 1888 Mo. App. LEXIS 460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoyt-v-greene-moctapp-1888.