Opinion

BLODGETT, District Judge

(charging jury). The plaintiff in this case seeks to recover upon a policy of insurance issued by the defendant, bearing date the 15th of June. 1869, countersigned by the defendant’s local agent on the 26th of August, 1869, whereby the defendant insured the paper-hangings manufactory of the plaintiff, situated at Marseilles, in this state, against damage by fire to the amount of five thousand dollars, for the term of one year from the date of said policy. To sustain this claim the plaintiff, in opening, proved the issue of the policy; the fact that his building was burned on the 3d of October, 1869, during the lifetime of the policy; that the loss was total; and that he had at that time furnished the defendant the notice and proofs of loss required by the terms of the policy, and claiming that this evidence made out a prima facie right to recover, and the plaintiff rested. By way of answer to the case thus made out by the plaintiff, the defendant contends: First. That the plaintiff applied for the policy in question upon the property in question by a written application dated the 25th day of May, 1869, which application is, by the terms of the policy, made part thereof, or is made a warranty; that the plaintiff had violated the terms of his warranty in not putting a force pump into the building within a reasonable time after the application was made; and that by reason of such violation of his warranty the policy had become and ivas avoided at the time of the alleged loss. Second. That the plaintiff had procured policies of insurance upon the building and contents to the aggregate amount of about ninety thousand dollars, which, in the whole, exceeded the value of the property, and then caused the building and contents to be burned, with the intent thereby to defraud the defendant and the other insurance companies who had issued policies upon the property.

By the first point the defendant raises a question of law in regard to the plaintiffs right to recover. But the policy refers in express terms to the application therefor which had been made by the plaintiff, and declares said application to be a part of this policy and a warranty on the part of the insured. By reference to the application, which has been produced in evidence, it appears that among other questions in the application to be answered by the assured is the following: “Q. 25. Is there a force pump upon the premises expressly for the purpose of putting out fire, and is it a good pump, and at. all times ready for immediate use?” To which plaintiff replied in writing, opposite the question: “One constructing to flood every floor by open cocks and power applied outside of the building, in constant use for [701] pumping -water for washing purposes.” It is one of the admitted facts in this case that, at the time of the fire which destroyed the building, no force pump had been put in, and no vertical pipe for conducting the water from the pump to the various stores, nor lateral pipes in each story to distribute the water through them, and upon these facts the defendant insists that the plaintiff cannot recover, because the statement, in the application in regard to the force pump, is a warranty or Covenant that said pump shall be constructed within a reasonable time, and inasmuch as the application is dated the 25th of May, 1869, and the fire occurred on the 3d of October, over four months afterward, and as the defendant’s affirmative proof tends to show that the pump could have been put in place within a very short space of time, therefore more than a reasonable time had elapsed, and the policy had become void by reason of this breach of warranty.

Without taking time to discuss at length the position of the learned counsel for the defendant in this case on this point, it will be sufficient for me to say that I find no words in the policy or application which expressly or by implication restrict the policy from taking effect until the force pump is completed. The language of the application, when question and answer are taken together, is that a force pump is in process of construction, which will flood every floor. He does not say there is a force pump there already, which would amount to a warranty of the fact, but says one is constructing, and there is no language which indicates an intention that the policy was not to be operative until the pump was constructed. I think, therefore, and so instruct you, that the policy was not suspended nor prevented from becoming operative by the delay in constructing the force pump, even beyond a reasonable time. It may be that the true construction of the clause of the application requires the plaintiff to put in the pump and pipes for flooding the building, as described, within a reasonable time, as is contended by the defendant, but I think, if the contract of insurance once took effect and became operative, the defendant could not avoid it by the plaintiff’s delay in putting in his pump, without first making a demand upon the plaintiff to comply with this part of his -undertaking, and giving notice that the contract would be rescinded if he did not so comply. This part of the plaintiff’s undertaking was executory, to be performed within a reasonable time; but what is a reasonable time is a question of fact to be controlled by the circumstances shown by the proof, and, if the delay was unreasonable, the defendant could at any time protect itself by notice or demand of compliance with this clause, and by rescinding the contract if the plaintiff refused to comply by putting in the pump; or the defendant might have exercised its reserved right, cancelling the policy under the cancellation clause in the policy itself. To illustrate: This same application contains a question as to whether there are lightning rods on the building, and the answer is, “We will erect rods soon, no rod at present.” Now this would be taken, it seems to me, merely as a promise that the plaintiff will put up lightning rods at some future day, and even if the building had been burned by a stroke of lightning, for want of a rod, it could not avoid the policy, if the defendant acquiesced in the delay in putting up the rod. If the plaintiff had stated that the pump was already put into the building, or a lightning rod erected, such statements would have been a warranty, and, unless waived by the company, would have avoided the policy, if not true, even if the loss had not happened by reason of the breach of such warranty. This proposition I deem sound in law, but not applicable to this case, because the undertaking of the plaintiff is to construct a pump, and not that one is already constructed. This policy shows upon its face that it was not to become binding until countersigned by the defendant’s agents at Marseilles, and that it was not so countersigned until August 26th, from which time it seems to me the delay must not be deemed to have been unreasonable; but that is a question of fact for you to pass upon, as to whether it was reasonable or unreasonable, if such a question of fact were submitted to you. I therefore charge you that no demand being shown by the proof for the construction of the pump by any specified time, and no steps taken to avoid the policy by reason of the delay in putting up the pump, the policy must be considered as in full force at the time of the-fire, notwithstanding the plaintiff’s delay in the construction of the force pump.

Free access — add to your briefcase to read the full text and ask questions with AI

Howell v. Hartford Fire Ins. Co., 12 F. Cas. 700, 3 Ins. L.J. 649 (circtndil 1874).

12 F. Cas. 700 (Howell v. Hartford Fire Ins. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Atlas Assur. Co. of London v. Hurst
11 F.2d 250 (Eighth Circuit, 1926)