Howard v. Hughes

293 N.W. 740, 294 Mich. 533, 1940 Mich. LEXIS 790
CourtMichigan Supreme Court
DecidedSeptember 6, 1940
DocketDocket No. 63, Calendar No. 41,098.
StatusPublished
Cited by13 cases

This text of 293 N.W. 740 (Howard v. Hughes) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard v. Hughes, 293 N.W. 740, 294 Mich. 533, 1940 Mich. LEXIS 790 (Mich. 1940).

Opinion

Chandler, J.

Plaintiffs Neil and Anna Howard are the owners of 12 acres of land in Walker township in Kent county. On May 25, 1939, they leased this land to defendant J. P. Hughes, doing business as the Texagan Oil & Gas Company, for a nominal sum under the commonly accepted form of oil and gas lease. The following clause was typed in the lease:

“This lease must have a well started within 30 days of the completion of the well now being drilled in section 31.”

It is conceded that this provision referred to a well being drilled by the Yoorhies Company, called the Powers well.

On July 15, 1939, the Howards gave a second oil and gas lease covering the same property to Harvey Yander Laan. This so-called “top” lease provided for commencement of operations within 90 days. Lessee Yander Laan knew of the former lease to *535 Hughes and in the lease he agreed to bear all expense of litigation in defense of any action commenced against the Howards because of the prior lease.

Vander Laan assigned his lease to plaintiff Crown Development Company on August 21, 1939, and this suit was started on August 23, 1939.

The parties to this action had no control over the progress of the Powers well. The date of its completion was used as an arbitrary standard from which a period of 30 days was to be measured within which the Howard well was to be commenced.

The contractors developing the Powers well ceased drilling about June 3d, and then the usual acid treatments were employed in an attempt to induce the oil to flow. Various treatments and pumping operations continued until about July 10th in an effort to make it a producing well. Finally, the contractor decided he had a dry hole and commenced plugging operations which were completed on July 24, 1939.

On July 19, 1939, there was filed with the conservation commission a notice of intention to abandon the Powers well. This notice states that it was completed on July 19,1939, and that plugging operations were commenced. On August 9, 1939, the log of oil, gas or test well was filed. This must be filed, according to the rules of the commission, within 30 days after the “first completion” of the well. The log shows that the drilling on the Powers well was finished on June 3, 1939.

On July 10, 1939, a well on neighboring property called the Oummings well came in as a producer. This gave the Howard property more potential value as oil land.

Defendant Hughes applied to the conservation commission for a drilling permit for the Howard land on July 18th and on July 25th, and had a survey *536 made on the latter date. The permit to drill was issued July 26th and the drilling contractor moved his rig on the land on July 27th. Actual drilling began on August 5, 1939, and continued steadily after that.

On August 24,1939, defendant Hughes was served with a summons in this case. At that time, the drilling had reached a depth of 62.5 feet and approximately $2,500 had been spent by the Texagan company in drilling the hole. The suit sought to restrain further operations by Hughes and the Texagan company and to cancel the lease given by the Howards to Hughes, representing the Texagan company..

After hearing the testimony of the parties and of the oil men and experts who were called by each side, the trial court found that the Howard well was commenced within 30 days after the completion of the Powers well, and entered a decree upholding the lease of the Texagan Oil & Gas Company, dismissing the bill of complaint, and dissolving the temporary injunction. The Crown Development Company takes a general appeal from that decree.

The primary question to be determined is: When was the Powers well “completed”?

Appellants contend that the Powers well was completed prior to June 7, 1939, when it was drilled in. Appellees contend that the well was not completed until it was determined by good oil-field practice whether it was a producing well or a dry hole.

There is a conflict in the testimony as to the intention of the parties in inserting the 30-day provision in the lease.

Mr. and Mrs. Howard testified that they wanted a well right away and that they understood that the term “completion of well” as used in the lease referring to the Powers well should mean “drilled in.”

*537 On the other hand,. Hughes testified that it was understood and agreed that the Texagan company would commence drilling on the Howard land within 30 days if the Powers well came in as a producer, hut that if the Powers well was a dry hole he would have a year in which to commence drilling operations.

This claim was denied by the Howards, but in this connection we must note the clause in the lease which provided:

“It is agreed that this lease shall remain in force for a term of one year from this date, and as long thereafter as oil or gas or either of them is produced from said land by the lessee.”

The provision tends to support the contention of Mr. Hughes.

It is also difficult to justify the Howards ’ position in insisting that they understood the Texagan company would commence within 30 days after the Powers well was “drilled in” because they wanted a “short-term lease” and wanted a well “right away” in view of the fact that the top lease given to Vander Laan and assigned to appellant provided for the drilling to start in 90 days. It would seem more consistent with their position if the Howards had insisted on immediate drilling by Yander Laan instead of allowing him about three months to start a well.

Upon reading and considering the testimony and examining the exhibits, we are constrained to uphold the trial judge in his finding that the parties intended that the word “completion” meant the finding either of a producing well or a dry hole on the Powers land and not merely “drilled in” as contended by appellant. As a whole the record indicates that the purpose of the clause was to have a well started on the Howard land within 30 days after it was *538 determined definitely that the Powers well was a commercial well or a dry hole. There would be no point in setting the completion of a well as a starting date if only the completion of the drilling was meant. Merely drilling a well will not disclose whether there was oil or not, and apparently the parties here wanted to know whether there was oil on the Powers land before starting a well on their own land. In J. J. Fagan & Co. v. Burns, 247 Mich. 674 (67 A. L. R. 522), it was said, concerning an oil and gas lease:

“The lease should be read not only according to its words, but in connection with the purpose of its clauses.”

In some States the courts have given a technical construction to the word “completion” as used in an oil and gas lease. But this is generally applied to the situation where a lessee agrees to complete a well within a given time or pay a delay rental or forfeit his lease. In such cases, these courts have held that the well is completed when drilled into the oil-bearing sands.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bledsoe Land Co. v. Forest Oil Corp.
277 P.3d 838 (Colorado Court of Appeals, 2011)
Schroeder v. Terra Energy, Ltd.
565 N.W.2d 887 (Michigan Court of Appeals, 1997)
Steinkuehler v. Hawkins Oil and Gas, Inc.
1986 OK CIV APP 9 (Court of Civil Appeals of Oklahoma, 1986)
Boyer v. Tucker & Baumgardner Corp.
372 N.W.2d 555 (Michigan Court of Appeals, 1985)
Michigan Wisconsin Pipeline Co. v. Michigan National Bank
118 Mich. App. 74 (Michigan Court of Appeals, 1982)
Mi. Wis. Pipe. Co. v. Mi. Nat'l Bank
324 N.W.2d 541 (Michigan Court of Appeals, 1982)
LeBar v. Haynie
552 P.2d 1107 (Wyoming Supreme Court, 1976)
Leighton v. Leighton
159 N.W.2d 750 (Michigan Court of Appeals, 1968)
Edwards v. Hardwick
1960 OK 38 (Supreme Court of Oklahoma, 1960)
Totah Drilling Company v. Abraham
328 P.2d 1083 (New Mexico Supreme Court, 1958)
Braun v. Mon-O-Co Oil Corporation
320 P.2d 366 (Montana Supreme Court, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
293 N.W. 740, 294 Mich. 533, 1940 Mich. LEXIS 790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-v-hughes-mich-1940.