Howard, Needles, Tammen & Bergendoff v. Steers, Perini & Pomeroy

312 A.2d 621, 1973 Del. LEXIS 273
CourtSupreme Court of Delaware
DecidedNovember 1, 1973
StatusPublished
Cited by17 cases

This text of 312 A.2d 621 (Howard, Needles, Tammen & Bergendoff v. Steers, Perini & Pomeroy) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard, Needles, Tammen & Bergendoff v. Steers, Perini & Pomeroy, 312 A.2d 621, 1973 Del. LEXIS 273 (Del. 1973).

Opinion

CAREY, Justice:

This is a suit in which the third-party plaintiffs, appellants Howard, Needles, Tammen and Bergendoff, a partnership, and E. Lionel Pavlo, a partnership doing business as Howard, Needles, Tammen and Bergendoff, and E. Lionel Pavlo, a partnership and/or joint venture (hereinafter Engineers), a consulting engineering firm based in New York, are seeking indemnification from the third-party defendant ap-pellee, Steers, Perini & Pomeroy (hereinafter Contractor), the contractor hired by the Delaware River and Bay Authority (hereinafter Authority) to build the second Delaware Memorial Bridge. Authority *622 had also hired Engineers to assist in the construction of this bridge.

The initial litigation in this case arose out of an accident on April 6, 1966, in which several of Contractor’s employees were injured or killed by the collapse of a reinforced plywood form. This form was a temporary, box-like plywood frame, constructed to contain and shape concrete which was poured into it, and was to be removed after the concrete had set in its intended final form. The frame was constructed by Contractor from plans prepared by Contractor, with materials purchased by Contractor. Each frame was comprised of four flat, rectangular sections of reinforced plywood, joined together at the corners by tie rods purchased by Contractor and installed by Contractor. The concrete was mixed by Contractor from materials purchased by Contractor, and it was poured by Contractor while Contractor’s employees worked within the form to compact the cement to the appropriate density. It was during the pouring of a massive quantity of concrete into one of these forms that the form collapsed, allowing the unset cement to flow freely, causing injury or death to Contractor’s employees.

Those employees, or their representatives, sued Engineers, alleging negligence, and Engineers joined Contractor as third-party defendant. Engineers asserted that insofar as they might be liable to the plaintiffs, Contractor was liable to indemnify Engineers for any amounts they were required to pay the plaintiffs, and for contribution. In view of this Court’s decision in Diamond State Tel. Co. v. University of Delaware, Del.Supr., 269 A.2d 52 (1970), the claim for contribution has not been pursued.

Contractor moved for summary judgment. The Superior Court, by opinion and Order dated July 29, 1971, denied the motion, and Contractor appealed to this Court. Engineers moved to dismiss the appeal on grounds that it was an appeal from an interlocutory order, and hence improper. However, at the time of argument on this motion, Engineers decided that it would be advantageous to all parties if the appeal could be resolved on the merits in order to avoid a trial in Superior Court of issues which the Supreme Court might later determine to be invalid. Therefore, on December 1, 1971, we issued an Order reversing the Superior Court decision, and remanding the case for further proceedings consistent with the Order. The sole issue decided by this Court at that time was whether Article III 1 of Contract 100 between Contractor and Authority meant that Contractor was liable to indemnify Engineers as “agents” or “servants” of Authority. We held that, applying the rule of strict construction which is appropriate to such a contract provision (see State of Delaware v. Amiesite Corporation, Del. Supr., 297 A.2d 41, 1972; Powell v. Interstate Vendaway, Inc., Del.Super., 300 A.2d 241, 1972), Article III was not sufficiently clear on its face to create in Engineers any right of indemnity. Therefore, we said, the question of whether Engineers were “agents” or “servants” of Authority is academic.

Subsequently, the Superior Court granted a severance of the third-party claim and proceeded to a trial of the principal action *623 of the employees. In the early stages of that trial, the defendant third-party plaintiff (Engineers) agreed to an entry of judgment against them in favor of the various plaintiffs, and that judgment was entered on December 18, 1972.

The Superior Court, pursuant to our Order of December 1, 1971, then entered an Order on December 18, 1972, granting Contractor’s motion for summary júdgment. This is Engineers’ appeal from that decision.

I

It is clear that, because Contractor has paid compensation to the original plaintiffs under the Workmen’s Compensation Law, Contractor is not liable to Engineers as a joint tort-feasor. Diamond, supra. Therefore, any claim for indemnity must be based upon a contract, expressed or implied. We have already ruled that Engineers cannot recover against Contractor as “agents” or “servants” within the meaning of Article III, Contract No. 100, and Engineers do not now seek to reassert that theory. Rather, they now contend that there is, flowing from Contractor to Engineers, an implied promise of indemnification. For this argument, they rely upon Diamond, supra.

In Diamond, supra, an employee of the phone company was electrocuted while installing a T.V. cable into one of the University’s buildings. His widow brought suit against the University, alleging that it was negligent in maintaining a dangerous condition on its premises, to-wit, the manhole in which the decedent was killed. The University sought to join the phone company as a third-party defendant for purposes of indemnification. The University alleged that the phone company, an independent contractor, acting at the University’s request, had breached an implied covenant to perform the specified work in a workmanlike manner, giving rise to liability for indemnity. The University argued that a jury could find that the phone company’s failure to notify the University of the beginning of its work (which notification would have enabled the University to cut off power to the cables in the work area) was a breach of an implied promise to perform the work in a workmanlike manner. We held that an employer who has paid workmen’s compensation benefits to injured employees may be held liable for indemnity if he has breached an independent duty owed a third party, or if there is a basis for finding an implied promise of indemnity.

In our discussion in Diamond, supra, we briefly reviewed Larson’s treatment of this field of indemnity liability, 2 and we noted that there were four categories of cases in which such an implied promise may exist. We said:

“The first category is that in which the employer coming upon the premises to perform his services creates a dangerous condition and the third party fails to discover that dangerous condition and injury results. In that circumstance, the employer is liable to indemnify the third party for any damages obtained against it.” Diamond, supra, p. 57 of 269 A.2d.

Engineers contend that a jury could find that Engineers’ negligence consisted only of their failure to discover defects in Contractor’s work, and hence they fit squarely within this category of cases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hindinger v. J&M Temp, LLC
Superior Court of Delaware, 2023
Freeman v. Carter
Superior Court of Delaware, 2022
Patrone v. Commerce Associates LP
Superior Court of Delaware, 2018
Laugelle v. Bell Helicopter Textron, Inc.
88 A.3d 110 (Superior Court of Delaware, 2014)
Chamison v. HealthTrust, Inc.-Hosp. Co.
735 A.2d 912 (Court of Chancery of Delaware, 1999)
Precision Air, Inc. v. Standard Chlorine of Delaware, Inc.
654 A.2d 403 (Supreme Court of Delaware, 1995)
Alten v. Ellin & Tucker, Chartered
854 F. Supp. 283 (D. Delaware, 1994)
Askanase v. Fatjo
148 F.R.D. 570 (S.D. Texas, 1993)
Pierce Associates, Inc. v. The Nemours Foundation
865 F.2d 530 (Third Circuit, 1989)
Pierce Associates, Inc. v. Nemours Foundation
865 F.2d 530 (Third Circuit, 1988)
Wyoming Johnson, Inc. v. Stag Industries, Inc.
662 P.2d 96 (Wyoming Supreme Court, 1983)
Farrall v. Armstrong Cork Co.
457 A.2d 763 (Superior Court of Delaware, 1983)
SW (Delaware), Inc. v. American Consumers Industries, Inc.
450 A.2d 887 (Supreme Court of Delaware, 1982)
Cumberbatch v. BD. OF TRUSTEES, ETC.
382 A.2d 1383 (Superior Court of Delaware, 1978)
Cumberbatch v. Board of Trustees, Delaware Technical & Community College
382 A.2d 1383 (Superior Court of Delaware, 1978)
Rock v. Delaware Electric Cooperative, Inc.
328 A.2d 449 (Superior Court of Delaware, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
312 A.2d 621, 1973 Del. LEXIS 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-needles-tammen-bergendoff-v-steers-perini-pomeroy-del-1973.