Housing Author. v. Hartford Acc. and Indem.

954 So. 2d 577, 2006 WL 2790037
CourtSupreme Court of Alabama
DecidedSeptember 29, 2006
Docket1040885
StatusPublished
Cited by9 cases

This text of 954 So. 2d 577 (Housing Author. v. Hartford Acc. and Indem.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Housing Author. v. Hartford Acc. and Indem., 954 So. 2d 577, 2006 WL 2790037 (Ala. 2006).

Opinion

On April 21, 2004, the Housing Authority of the City of Huntsville ("the Housing Authority") sued Hartford Accident and Indemnity Company ("Hartford"), alleging that Consolidated Construction Company ("Consolidated"), for whom Hartford had issued a performance bond, had improperly installed fire-alarm systems at a residential *Page 578 facility operated by the Housing Authority. The complaint sought to enforce Hartford's obligations under the performance bond and demanded a judgment against Hartford "for compensatory damages in such amount as a jury may determine, plus interest and the costs of this action." Hartford filed a motion for a summary judgment, which the trial court granted on February 15, 2005. The Housing Authority appeals. We affirm.

Facts and Procedural History
Hartford issued a performance bond in favor of Consolidated, the general contractor for the renovation of the Housing Authority's premises. It is undisputed that Consolidated substantially completed its work at the premises on May 1, 1999, and that the Housing Authority discovered defects in the fire-alarm systems within one year of the completion date. Finally, it is undisputed that the Housing Authority did not file any action against Consolidated or Hartford for damages associated with Consolidated's work at the premises within the applicable two-year statutory limitations period. The Housing Authority filed this action on April 21, 2004, almost five years after Consolidated had completed its work, seeking to enforce Hartford's obligations under the performance bond. Consolidated was not made a party in this case.

The trial court, in its summary-judgment order, held:

"Under the applicable statute of limitations, all civil claims, whether in tort or contract, against an architect, engineer or contractor must be commenced within two (2) years `next after a cause of action accrues or arises, and not thereafter.' Ala. Code [1975,] § 6-5-221(a). . . .

"It is not disputed that the foregoing statute of limitations applies to any action against Consolidated, as a contractor for the [Housing] Authority project. It is also undisputed that the [Housing Authority] failed to commence an action against Consolidated within the period of time required by Ala. Code [1975,] §§ 6-5-220(e) and 6-5-221(a).

"Under Alabama law, a surety may make any defense not personal to the principal that the principal can. More specifically, a surety may assert as a defense the statute of limitations available to the principal even if the principal through negligence, inadvertence, collusion, or otherwise, has not raised it. Alabama Surface Mining Reclamation Comm'n v. Commercial Standard Ins. Co., 469 So.2d 619, 620 (Ala.Civ.App. 1985) (citing Commercial Standard Ins. Co. v. Alabama Surface Mining Reclamation Comm'n, 443 So.2d 1245, 1249 (Ala.Civ.App. 1983), cert. denied, 467 U.S. 1242 (1984)).

"Because the [Housing Authority] failed to commence an action against Consolidated within two years following its discovery of the alleged deficiencies in the fire alarm system, and because Hartford, as surety, is entitled to assert the benefit of all defenses available to its principal, all claims against Hartford, as surety, are time-barred."

Standard of Review
In Smith v. State Farm Mutual Automobile InsuranceCo., 952 So.2d 342, 346 (Ala. 2006), this Court stated the applicable standard of review governing an appeal from a trial court's ruling on a summary-judgment motion:

"We review the trial court's grant or denial of a summary-judgment motion de novo, and we use the same standard used by the trial court to determine whether the evidence presented to the trial court presents a genuine issue of material fact. Bockman v. WCH, *Page 579 L.L.C., 943 So.2d 789 (Ala. 2006). Once the summary-judgment movant shows there is no genuine issue of material fact, the nonmovant must then present substantial evidence creating a genuine issue of material fact. Id. `We view the evidence in the light most favorable to the nonmovant.' 943 So.2d at 795. We review questions of law de novo. Davis v. Hanson Aggregates Southeast, Inc., 952 So.2d 330 (Ala. 2006)."

Discussion
The Housing Authority presents one issue on appeal: Whether Hartford can assert as a defense the two-year statute of limitations found at § 6-5-221, Ala. Code 1975. The Housing Authority alleges that the two-year statute of limitations asserted by Hartford under § 6 — 5 — 221, Ala. Code 1975, applies only to the builder, i.e., Consolidated, and to certain other design professionals. The Housing Authority argues that all other parties, including sureties, are excluded from asserting the two-year statute of limitations.

The statute of limitations in the present case is found at § 6-5-221, Ala. Code 1975; that statute reads, in part:

"(a) All civil actions in tort, contract, or otherwise against any architect or engineer performing or furnishing the design, planning, specifications, testing, supervision, administration, or observation of any construction of any improvement on or to real property, or against builders who constructed, or performed or managed the construction of, an improvement on or to real property designed by and constructed under the supervision, administration, or observation of an architect or engineer, or designed by and constructed in accordance with the plans and specifications prepared by an architect or engineer, for the recovery of damages for:

"(i) Any defect or deficiency in the design, planning, specifications, testing, supervision, administration, or observation of the construction of any such improvement, or any defect or deficiency in the construction of any such improvement; or

"(ii) Damage to real or personal property caused by any such defect or deficiency; or

"(iii) Injury to or wrongful death of a person caused by any such defect or deficiency;

"shall be commenced within two years next after a cause of action accrues or arises, and not thereafter. Notwithstanding the foregoing, no relief can be granted on any cause of action which accrues or would have accrued more than thirteen years after the substantial completion of construction of the improvement on or to the real property, and any right of action which accrues or would have accrued more than thirteen years thereafter is barred, except where prior to the expiration of such thirteen-year period, the architect, engineer, or builder had actual knowledge that such defect or deficiency exists and failed to disclose such defect or deficiency to the person with whom the architect, engineer, or builder contracted to perform such service.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ala. Teachers Credit Union v. Design Build Concepts, Inc.
334 F. Supp. 3d 1171 (N.D. Alabama, 2018)
Henderson v. MeadWestvaco Corp.
23 So. 3d 625 (Supreme Court of Alabama, 2009)
Be-Jeweled, L.L.C. v. AIG Baker Orange Beach Wharf, L.L.C.
12 So. 3d 1204 (Supreme Court of Alabama, 2009)
Ex Parte Aig Baker Orange Beach Wharf
12 So. 3d 1204 (Supreme Court of Alabama, 2009)
Fausnight v. Perkins
994 So. 2d 912 (Supreme Court of Alabama, 2008)
Weinrib v. Wolter
1 So. 3d 1032 (Court of Civil Appeals of Alabama, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
954 So. 2d 577, 2006 WL 2790037, Counsel Stack Legal Research, https://law.counselstack.com/opinion/housing-author-v-hartford-acc-and-indem-ala-2006.