House of Power Electric, LC v. BMRJ Heights LLC

CourtCourt of Appeals of Texas
DecidedAugust 15, 2024
Docket14-23-00640-CV
StatusPublished

This text of House of Power Electric, LC v. BMRJ Heights LLC (House of Power Electric, LC v. BMRJ Heights LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
House of Power Electric, LC v. BMRJ Heights LLC, (Tex. Ct. App. 2024).

Opinion

Reversed and Remanded and Memorandum Opinion filed August 15, 2024.

In The

Fourteenth Court of Appeals

NO. 14-23-00640-CV

HOUSE OF POWER ELECTRIC, LC, Appellant

V.

BMRJ HEIGHTS LLC, Appellee

On Appeal from the 234th District Court Harris County, Texas Trial Court Cause No. 2019-34108

MEMORANDUM OPINION

In this fraudulent-lien case, second-tier subcontractor House of Power Electric, LC, appeals the summary judgment rendered against it and in favor of property owner BMRJ Heights, LLC. Although it is undisputed that House of Power’s lien affidavits are unenforceable, genuine issues of material fact preclude summary judgment. Thus, we reverse the judgment and remand the case to the trial court. I. BACKGROUND

BMRJ contracted with Gene Giles Design Group, Inc. (Giles) to construct six single-family townhomes at 2511 Ohsfeldt Street in Houston. Giles subcontracted with Paragon Homes, LLC, who subcontracted certain work to House of Power in August and September 2017. According to BMRJ, House of Power performed some of the work incorrectly and ultimately did not complete the project. Paragon told BMRJ that it had contracted with ICON Electric Inc. to perform or correct work that House of Power had been required to perform, and BMRJ paid Paragon for those extra charges.

On January 11, 2018, House of Power’s president Albert Chlouber signed lien affidavits for each of the six townhomes in amounts ranging from $3,018.00 to $7.596.20. The six lien affidavits were filed in Harris County’s property records the next day. Each affidavit correctly identified BMRJ as the owner of the property but incorrectly identified Paragon as the original contractor. In each affidavit, House of Power attested that it sent a notice of claim to BMRJ on January 11, 2018, via certified mail, return receipt requested. In October 2018, House of Power sued Paragon and BMRJ seeking payment or foreclosure, but soon after, House of Power released the liens and dismissed BMRJ from the case.

BMRJ sued House of Power for filing fraudulent liens and requested an award of statutory damages for each, together with attorney’s fees and costs. BMRJ filed a traditional motion for partial summary judgment to establish House of Power’s liability on BMRJ’s fraudulent-lien claim for statutory damages, reserving the issue of attorney’s fees. The trial court initially denied the motion and a first motion for reconsideration, but after a second motion for reconsideration, the trial court granted partial summary judgment awarding BMRJ $60,000 in statutory damages. BMRJ then moved for entry of final judgment including attorney’s fees. The trial court

2 granted the motion, awarding BMRJ statutory damages, costs, over $145,000 for attorney’s fees in the trial court, and a further $60,000 if BMRJ prevailed in appeals from the judgment.

The trial court denied House of Power’s motions for reconsideration and for new trial, and House of Power now appeals the final judgment.

II. ISSUES

In four issues, House of Power argues that the trial court erred in (a) granting BMRJ summary judgment, (b) awarding BMRJ statutory damages, (c) awarding BMRJ any attorneys’ fees, and (d) awarding excessive attorney’s fees.

III. STANDARD OF REVIEW

The movant for traditional summary judgment has the burden to prove that no genuine issue of material fact exists and that the movant is entitled to judgment as a matter of law. TEX. R. CIV. P. 166a(c). In determining whether the movant has conclusively established every essential element of its claim or defense as a matter of law, courts consider all of the evidence in the light most favorable to the nonmovant, crediting evidence favorable to the nonmovant if a reasonable factfinder could, and disregarding contrary evidence unless a reasonable factfinder could not. See Mack Trucks, Inc. v. Tamez, 206 S.W.3d 572, 582 (Tex. 2006). We review the ruling on the motion de novo. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex. 2005). Questions of statutory construction are likewise subject to de novo review. Chambers-Liberty Ctys. Navigation Dist. v. State, 575 S.W.3d 339, 345 (Tex. 2019).

IV. GOVERNING LAW

To prevail in its traditional motion for partial summary judgment, BMRJ bore the burden to conclusively prove its allegations that House of Power made,

3 presented, or used a lien affidavit with (1) knowledge that it was a fraudulent lien; (2) intent that it be given legal effect; and (3) intent to cause BMRJ financial injury. See TEX. CIV. PRAC. & REM. CODE § 12.002(a); Gray v. Entis Mech. Servs., L.L.C., 343 S.W.3d 527, 530 (Tex. App.—Houston [14th Dist.] 2011, no pet.). A fraudulent lien is one created in bad faith or with dishonesty, a lack of integrity, or moral turpitude. Nationstar Mortg., LLC v. Barefoot, 654 S.W.3d 440, 447 (Tex. App.— Houston [14th Dist.] 2021, pet. denied). A person claiming a mechanic’s or materialman’s lien under Chapter 53 of the Property Code is not liable under the fraudulent-lien provision of Texas Civil Practice and Remedies Code section 12.002 for the making, presentation, or use of a document or other record in connection with the assertion of the claim unless the person acts with intent to defraud. TEX. CIV. PRAC. & REM. CODE § 12.002(c).

House of Power filed six mechanic’s and materialman’s liens under Chapter 53 of the Property Code. Under the applicable version of the statute, the claimant (here, House of Power) is required to give certain notices to the property owner (BMRJ) and the original contractor (Giles) at different times. Where, as here, a lien claim arises from a debt incurred by a subcontractor (that is, Paragon), the claimant must give written notice of the unpaid balance to the original contractor (Giles) “not later than the 15th day of the second month following each month in which all or part of the claimant’s labor was performed or material delivered.”1 The claimant must notify the original contractor and the owner or reputed owner (BMRJ) of the outstanding balance “not later than the 15th day of the third month following each

1 For this prior version of Texas Property Code § 53.056, see Act of May 19, 1997, 75th Leg., R.S., ch. 526, § 8, sec. 53.056(a), 1997 TEX. GEN. LAWS 1880, 1882 (amended 2021), and Act of May 28, 1989, 71st Leg., R.S., ch. 1138, § 8, sec. 8, secs. 53.056(b)–(e), 1989 TEX. GEN. LAWS 4693, 4696 (repealed 2021). The 2021 amendments apply only to original contracts entered into on or after January 1, 2022.

4 month in which all or part of the claimant’s labor was performed or material or specially fabricated material was delivered.”2 Finally, the claimant must file the lien affidavit by the 15th day of the fourth month after the indebtedness accrued,3 sending copies by registered or certified mail to the original contractor and owner within five days.4

Because House of Power performed its work in August and September 2017, it was required to give Giles the second-month notices in October and November 2017; to give Giles and BMRJ the third-month notices in November and December 2017; and to file the lien affidavits by January 15, 2018.

Although the lien affidavits were filed before the fourth-month deadline, House of Power did not comply with the second- and third-month notice requirements discussed above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Anderson, Greenwood & Co. v. Martin
44 S.W.3d 200 (Court of Appeals of Texas, 2001)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
Gordon v. West Houston Trees, Ltd.
352 S.W.3d 32 (Court of Appeals of Texas, 2011)
Gray v. Entis Mechanical Services, L.L.C.
343 S.W.3d 527 (Court of Appeals of Texas, 2011)
in Re Sustainable Texas Oyster Resource Management, L.L.C.
575 S.W.3d 339 (Texas Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
House of Power Electric, LC v. BMRJ Heights LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/house-of-power-electric-lc-v-bmrj-heights-llc-texapp-2024.