Houghton v. Hoy

172 P. 1148, 102 Wash. 358, 1918 Wash. LEXIS 933
CourtWashington Supreme Court
DecidedMay 10, 1918
DocketNo. 14410
StatusPublished
Cited by1 cases

This text of 172 P. 1148 (Houghton v. Hoy) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Houghton v. Hoy, 172 P. 1148, 102 Wash. 358, 1918 Wash. LEXIS 933 (Wash. 1918).

Opinion

Mount, J.

This action was brought to recover the sum of $50,856.30, alleged to be due from the defendant on account of work done for the defendant under certain contracts. The defendant, after denying certain material allegations of the complaint, alleged a counterclaim and set-off, and demanded judgment against the plaintiff and the Guardian Casualty & Guaranty Company in the sum of $33,485.57. After issues were joined, the case was tried to the court without a jury, and findings were made and judgment entered in favor of the defendant for $22,736. The plaintiff and the Guardian Casualty & Guaranty Company have appealed from that judgment.

The facts may be briefly stated as follows: On October 8,1914, the Northern Pacific Railway Company let a contract to W. J. Hoy Company for the construction of an elevated roadway through the city of Spokane. This elevated roadway was about three miles in length. It consisted of concrete retaining walls on each side of the right of way and overhead bridges across the public streets of the city over which the railway line extended. On November 14, 1914, the W. J. Hoy Company, original contractor for the Northern Pacific Railway Company, entered into a subcontract with R. H. Van Sant, Jr., Shirley Houghton, Raymond Ashton, and G. T. Bridgman, copartners doing business under the name of the Pacific Concrete Placing Company (which shall hereafter be referred to as the Placing company), by which contract the Placing company undertook to mix and place so much of the concrete as would be required for the retaining walls, cross-walls and bridges, at an agreed price of ninety cents per cubic yard. Thereafter, on February 11, 1915, the W. J. Hoy Company entered into another subcontract with the Placing company by which the latter company agreed to construct and maintain, with materials furnished by the Hoy [360]*360company, the wooden forms for retaining walls, cross-walls and abutments. These two contracts provided that the Placing company should furnish surety bonds for the faithful performance of these contracts, and bonds were furnished by the Guardian Casualty & Guaranty Company in the sum of $40,000 for the faithful performance of the concrete contract, and $7,000 for the faithful performance of the other contract. These bonds were both under date of April 9, •1915. Work was commenced on these' contracts by the Placing company in March, 1915, and continued until in December of that year, when the work was stopped on account of the winter months. During the time the work was in progress, payments were made by the Hoy company to the Placing company in accordance with the terms of the contracts to the amount of ninety per cent of the estimates made by the supervising engineers.

After the work was closed down in December of 1915, the superintendent of the railway company notified the Hoy company, and in turn the Hoy company notified the Placing company, that no more deliveries of sand and gravel or concrete would be permitted upon railway tracks west of Division street. The Placing company insisted that it was entitled to deliveries of sand and gravel and cement at the work sites where work was being done, and for failure of the Hoy company to make such deliveries, declined to proceed with'the contract for concrete work when the work was required to be started in March of 1916. The Hoy company thereupon notified the Guardian Casualty & Guaranty Company of this fact and that work would be started on the 28th day of March, 1916, and that, unless the Placing company or the Guardian Casualty & Guaranty Company proceeded with the contract for concrete ■work, the Hoy company would take charge of the work [361]*361and finish it at the cost of the Guardian Casualty & Guaranty Company and of the Placing company, which it did. The Placing company continued with the contract for retaining wall, cross-wall and abutment forms under the retaining wall contract, until the month of August, 1916. At that time the Hoy company refused to pay the monthly estimate of work done by the Placing company upon this contract, because the Placing company was then indebted to the Hoy company in excess of the amount of the monthly estimate. The Placing company thereupon refused to comply with that contract, and shortly afterwards the partners of the Placing company dissolved the copartnership and assigned to Shirley Houghton all their interest in the assets of the partnership and he assumed all the liabilities thereof. He thereafter brought this action, alleging the amounts due from the Hoy company to the Placing company to be $50,856.30. The Hoy company thereafter filed its answer, brought in the Guardian Casualty & Guaranty Company as defendant, and alleged that it had expended in excess of the amount due the Placing "company the sum of $33,485.57, for which the Hoy company prayed judgment against the Placing company and the Guardian Casualty & Guaranty Company.

The trial of the case involved a multitude of accounts on the part of both the appellants and the respondent. The record is voluminous; but the primary question, and the one which controls the disposition of the case, depends upon a construction of the different contracts.

The contract between the Northern Pacific Railway Company and the Hoy company provided, among other things, as follows:

‘ ‘ The contractor agrees to furnish all labor, services and material for, and construct, complete and finish in the most thorough, workmanlike and substantial man[362]*362ner in every respect to the satisfaction of the chief engineer of the company, within the time hereinafter specified, and according to the specifications hereto annexed and made part of this contract, all concrete construction, waterproofing, foundations, . . .
“Date of completion
“The work is to he commenced immediately and completed on or before the first day of June, A. D. 1916.
11 The company will furnish free transportation over its own line subject to the review and instructions of the chief engineer as to the necessity for and proper use of same, for contractor’s outfit-to the work and return to point of origin or to a point having an equivalent tariff rate.
“Free transportation will he furnished for cement west of Logan, Montana.
“The contractor to pay full tariff rate on all other material and supplies entering into or used on the work, and contractor shall buy all such material if possible at points which will .permit the company to receive the haul on such materials, routing same via the lines of the company and its connecting lines.
“Nothing herein contained shall he construed to relieve the contractor of payment of demurrage charges under car service association rules, for shipments of equipment and material by either the’railway company or the contractor to he used on this contract.”

In the specifications above referred to, it was provided as follows:

“Plans and Ordinance:
“All work must conform in every respect to the general and detail plans and specifications of the railway company, ...
“Excavation:
“The price paid for excavation shall include hack-filling and the actual haul of materials for any distance not exceeding 600 feet. The limit to which any materials may he required to he hauled shall be 3,500 feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Poston
269 P.2d 967 (Washington Supreme Court, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
172 P. 1148, 102 Wash. 358, 1918 Wash. LEXIS 933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/houghton-v-hoy-wash-1918.