Colorado Court of Appeals Opinions || April 7, 2016

Colorado Court of Appeals -- April 7, 2016
2016 COA 52. No. 14CA2328. City of Aurora v. 1405 Hotel.

COLORADO COURT OF APPEALS 2016 COA 52

Court of Appeals No. 14CA2328
Arapahoe County District Court No. 13CV31506
Honorable Charles M. Pratt, Judge


City of Aurora, Colorado; Aurora Urban Renewal Authority; and RIDA Development Corp,

Plaintiffs-Appellants and Cross-Appellees,

v.

1405 Hotel, LLC; 550 15th Owner, LLC; Broadmoor Hotel Inc.; Brown Palace Hotel Associates Limited Partnership; Cheyenne Mountain Conference Resort; CHSP Denver LLC; DiamondRock Cherry Creek Tenant LLC; DiamondRock Denver Downtown Tenant LLC; HEP Denver Ltd., d/b/a Magnolia Hotel; Oxford Hotel 2005 Holdings LLC; and Westminster Boulevard Finance, LLC,

Defendants-Appellees and Cross-Appellants.


 JUDGMENT AFFIRMED

Division I
Opinion by JUDGE TAUBMAN
Miller and Fox, JJ., concur

Announced April 7, 2016


Kutak Rock LLP, Thomas W. Snyder, Daniel C. Lynch, Michael M. Frandina, Denver, Colorado; Michael J. Hyman, City Attorney, Aurora, Colorado, for Plaintiffs-Appellants and Cross-Appellees City of Aurora, Colorado and Aurora Urban Renewal Authority

Fairfield & Woods, P.C., John M. Tanner, Denver, Colorado, for Plaintiff-Appellant and Cross-Appellee RIDA Development Corp.

Lewis Roca Rothgerber Christie LLP, James M. Lyons, Hilary D. Wells, Jessica L. Fuller, Hermine Kallman, Denver, Colorado, for Defendants-Appellees and Cross-Appellants

¶1       In July 2013, eleven hotels1 along Colorado’s Front Range (collectively, the Hotels) submitted a petition to the Colorado Economic Development Commission (CEDC) requesting that CEDC require the City of Aurora (Aurora) to submit a new application for an $81 million tax subsidy (the Gaylord Project) after the initial company that had been awarded the subsidy, the Gaylord Entertainment Company, assigned its interest to RIDA Development Corporation (RIDA). The Attorney General (AG) denied the petition on behalf of the CEDC.2 The Hotels filed an action in the Denver District Court (Denver lawsuit). Both the Denver District Court and a division of our court affirmed the AG’s denial of the Hotels’ petition. 1405 Hotel, LLC v. Colo. Econ. Dev. Comm’n, 2015 COA 127, ___ P.3d ___ (1405 Hotel I). However, in response to the Hotels’ alleged "conspir[acy] . . . to interfere with the financing and development of the [p]roject," plaintiffs, the City of Aurora, the Aurora Urban Renewal Authority, and RIDA (collectively, the Aurora parties), sued the Hotels in October 2013.

¶2       The Aurora parties now appeal the judgment of the Arapahoe District Court (district court), which dismissed their complaint after the court found the Hotels’ complaint in the Denver lawsuit was immunized under the First Amendment based on Protect Our Mountain Environment, Inc. v. Dist. Court, 677 P.2d 1361 (Colo. 1984) (POME). We affirm.

I. Background

¶3       The underlying facts of this case are set forth in 1405 Hotel I. In the Denver lawsuit, the Hotels sued the CEDC and Aurora alleging four claims for relief: (1) a claim in the nature of mandamus brought under C.R.C.P. 106(a)(2) to compel the CEDC to require Aurora to submit a new application for the Gaylord Project, as required by the Colorado Regional Tourism Act (RTA); (2) a claim brought pursuant to the State Administrative Procedure Act (APA), section 24-4-106(4), C.R.S. 2015, seeking review of the CEDC’s denial of their petition for reconsideration and approving the Gaylord Project; (3) a claim for declaratory relief pursuant to C.R.C.P. 57 and section 13-51-105, C.R.S. 2015, challenging the constitutionality of section 309 of the RTA, section 24-46-309, C.R.S. 2015; and (4) a claim seeking a declaration that procedural irregularities in the CEDC’s approval of the initial Gaylord Project invalidated the RTA award.

¶4       In December 2013, Aurora moved for a C.R.C.P. 12(c) judgment on the pleadings, asserting that the Hotels lacked standing to bring claims one, two, and four. Aurora conceded that the Hotels had standing to bring their third claim, but maintained that the third claim should be resolved in Aurora’s favor on the merits. Following a hearing in March 2014, the Denver court granted Aurora’s C.R.C.P. 12(c) motion in an oral ruling. In July 2014, the Denver District Court entered a written order denying the Hotels’ C.R.C.P. 59 motion. A division of our court affirmed in 1405 Hotel I, ¶1, ___ P.3d at ___.

¶5       However, after the Hotels filed their appeal in the Denver lawsuit but before the 1405 Hotel I decision, the Aurora parties filed this lawsuit before the Arapahoe District Court, asserting claims against the Hotels for intentional interference with contract, intentional interference with business expectancy, abuse of process, and civil conspiracy. First, the Hotels filed an answer and asserted several counterclaims. Later the same day, the Hotels moved to dismiss pursuant to C.R.C.P. 12(b)(5), arguing their initial complaint was protected by the First Amendment privilege to petition the government for redress of grievances as described in POME. Also on the same day, the Hotels filed a separate C.R.C.P. 12(b)(5) motion to dismiss against RIDA’s claims individually.

¶6       The court granted the Hotels’ POME motion and dismissed all four of the Aurora parties’ claims. Although the court held that one of the claims brought by the Hotels in the Denver lawsuit lacked a cognizable basis in law and was therefore a "sham," it nevertheless granted the Hotels’ motion because it concluded that POME requires an entire lawsuit to be frivolous in order to remove the First Amendment privilege.

¶7       On appeal, the Aurora parties seek reversal of the district court’s order and contend: (1) the court abused its discretion in refusing to allow discovery and a hearing; (2) the court erred in determining that three of the Hotels’ claims in the Denver lawsuit had reasonable factual support or a cognizable basis in law; and (3) the court erred in dismissing their complaint despite concluding that one of the Hotels’ claims from the Denver lawsuit was a "sham." We disagree.

¶8       In their cross-appeal, the Hotels contend (1) the court erred in concluding that the Hotels lacked probable cause to bring an as-applied constitutional challenge to section 309 of the RTA under Colorado Constitution article II, section 11 and therefore their third claim was not a sham; and (2) we should affirm the C.R.C.P. 12(b)(5) dismissal of RIDA’s claims. We agree with the Hotels’ first contention and do not address their second contention.

II. Nature of the Hotels’ Motion

¶9       At the outset, in considering what standard of review to apply to the POME motion to dismiss, we need to consider whether the Hotels’ POME motion was properly decided as a motion to dismiss or whether it should have been converted into a motion for summary judgment. The Aurora parties contend that POME requires a motion to dismiss be converted into a motion for summary judgment. Because the outcome would be the same regardless of whether the motion was treated as a C.R.C.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dorman v. Petrol Aspen, Inc.
914 P.2d 909 (Supreme Court of Colorado, 1996)
City of Englewood v. Mountain States Telephone & Telegraph Co.
431 P.2d 40 (Supreme Court of Colorado, 1967)
Perl-Mack Enterprises Co. v. City & County of Denver
568 P.2d 468 (Supreme Court of Colorado, 1977)
Cloverleaf Kennel Club, Inc. v. Colorado Racing Commission
620 P.2d 1051 (Supreme Court of Colorado, 1980)
Allen v. Steele
252 P.3d 476 (Supreme Court of Colorado, 2011)
Walker v. Van Laningham
148 P.3d 391 (Colorado Court of Appeals, 2006)
A-1 Auto Repair & Detail, Inc. v. Bilunas-Hardy
93 P.3d 598 (Colorado Court of Appeals, 2004)
Waskel v. Guaranty National Corp.
23 P.3d 1214 (Colorado Court of Appeals, 2000)
Busse v. City of Golden
73 P.3d 660 (Supreme Court of Colorado, 2003)
McIntyre v. Board of County Commissioners
86 P.3d 402 (Supreme Court of Colorado, 2004)
City and County of Denver v. Qwest Corp.
18 P.3d 748 (Supreme Court of Colorado, 2001)
W.O. Brisben Companies, Inc. v. Krystkowiak
66 P.3d 133 (Colorado Court of Appeals, 2003)
Boyer v. Health Grades, Inc.
2015 CO 40 (Supreme Court of Colorado, 2015)
Krystkowiak v. W.O. Brisben Companies, Inc.
90 P.3d 859 (Supreme Court of Colorado, 2004)
In re Foster
253 P.3d 1244 (Supreme Court of Colorado, 2011)
Denver Post Corp. v. Ritter
255 P.3d 1083 (Supreme Court of Colorado, 2011)
BSLNI, Inc. v. Russ T. Diamonds, Inc.
2012 COA 214 (Colorado Court of Appeals, 2012)
Roque v. Allstate Insurance Co.
2012 COA 10 (Colorado Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2016 COA 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hotel-coloctapp-2016.