Horsley v. Modzelewski

220 F. 241, 136 C.C.A. 503, 1915 U.S. App. LEXIS 2453
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 9, 1915
DocketNo. 1870
StatusPublished
Cited by2 cases

This text of 220 F. 241 (Horsley v. Modzelewski) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Horsley v. Modzelewski, 220 F. 241, 136 C.C.A. 503, 1915 U.S. App. LEXIS 2453 (3d Cir. 1915).

Opinion

J. B. McPHERSON, Circuit Judge.

This is an action in personam by Franciska Modzelewski against M. H. Horsley, who was averred to be the owner of the British steamship Eastwood. It was begun by foreign attachment, and the respondent afterwards appeared and made defense.

On Tuesday, December 14, 1909, the libelant’s husband, a laborer engaged in discharging the cargo of the steamship at Philadelphia, was killed by the fall of a tub or bucket loaded with iron oré, weighing altogether about a'ton. He had been at work in the hold, and the tub fell upon him while the winch was hoisting it out of No. 1 hatch. We shall assume that he died on the ship. The libelant sued under the Pennsylvania statute, and recovered damages on the ground that the wire rope to which the tub was attached “was not in proper condition, that the ship had notice of that fact, and that its failure to provide a suitable rope caused the accident.” This quotation from the opinion below states briefly the essence of the libel, which charges the respondent with furnishing a rope that was “defective, unsafe, improper, and not sufficiently strong,” and avers that, although the condition of the rope [242]*242could have been discovered “by ordinary care and diligence and by reasonable inspection,” nevertheless “the respondent and his agents wholly neglected their duty,” etc.

The libel was filed and the attachment issued in the following July; but the actual seizure of the ship was waived, and bond was entered by the master on behalf of the respondent. It was clearly proved that the Horsley Une, Limited, a British association, and not Horsley as an individual, was the owner of the steamship; but the trial judge held the respondent estopped to deny that he himself was the owner. This is one of the. errors assigned, but we need not consider it, as we think the case , should be decided on another ground. The witnesses were all examined by deposition, so that the case is presented to us just as it was presented to the court below. The Santa Rita, 176 Fed. 893, 100 C. C. A. 360, 30 L. R. A. (N. S.) 1210.

The ship had nothing to do with the work of discharging, except to furnish the winch and the wire rope and some other appliances at each hatch. The rope in question — which was nearly new, and of the usual type and size — broke at a point about 63 feet from the tub, between the winch and the gin block, the upper block of the derrick. It had been made by an English firm of the highest standing in the trade, and had been thoroughly tested in the course of manufacture. It was composed of 6 strands around a main hemp core, and each of these strands had its own hemp core, surrounded by a double layer of galvanized crucible steel wires, 14 outer over 8 inner wires. The rope therefore was made up of 132 wires and 7 hemp cores. It had been tested according to Lloyds’ regulations, both for torsion and for tensile strength. Each of the wires had been subjected to a torsion test of 43 twists in 8 inches, and to a tensile strain of 360 pounds. The completed rope, therefore, would sustain a breaking strain o.f more than 19 tons, and since the safe load of such a-rope is estimated to be from one-seventh to one-tenth of the breaking strain, a large factor of safety was left, so that the rope was abundantly capable of sustaining and raising a load of from 1 % to 2 tons. It had been supplied to the ship in June, 1909, and after being oiled had been stored in the fore-peak for several months. Toward the end of November it was used for the first time at Santiago, Cuba, not for cargo, but merely to lift some of the beams from the hatches. It was then oiled again and stored in the peak during the voyage of eight or nine days from Santiago to Philadelphia. It had been inspected in Cuba, - and was inspected a” second time on December 10, the day before the vessel reached Philadelphia, at which time it was rove into place in order to be in readiness for unloading. It was also inspected by the foreman of the stevedores early on Monday, December 13, before the actual work began, and on each of these three occasions it was found to be in excellent condition. And, although it had been used for about a day and a half in Philadelphia before the accident, nothing wrong was observed at any time either by the winchman or by the hatch tender.

It does not satisfactorily appear why the rope broke. Two or three theories are advanced, but we need not enter the field of conjecture. Unless sufficient evidence is present to establish the negligence of thu [243]*243respondent or his agents, we must accept this deplorable occurrence as an unexplained accident, for which no recovery can be had in this action. And no evidence of negligence exists, except in the testimony of two witnesses, upon which (for reasons to be given as briefly as possible) we do not feel able to rely with confidence.

As already stated, the libel was not filed until July 18, 1910. On the next day, July 19, the master and the second officer were examined by deposition and testified inter alia to the following effect: The second officer deposed that he had been on duty at Santiago and had seen the rope taken out of the forepeak; it was new, and was only used on that occasion to lift the beams and hatches; his business was to handle such ropes, and he saw this particular rope several times in Santiago; it was not broken in any way, even slightly; he had handled it there, and had observed it while in the discharge of his duty; he had also examined the self-lubricating blocks through which the rope ran, and found them in excellent condition; the rope had then been taken down, and had been put up again the day before the ship’s arrival in Philadelphia; he had also greased the rope down by the winch while it was being used here, and had found nothing the matter with it. The master testified: That the rope had been supplied on June 2, 1909, and had never been used before the ship reached Santiago; there it had merely lifted the beams out of the hatches, and had then been oiled and stored in the peak; on the day preceding the ship’s arrival in Philadelphia it had been taken out of the peak and rove to the winch at No. 1 hatch; the standing orders on board the ship were that every rope must be examined before it was used for cargo, and the officers must report any defects or anything wrong with the ropes at any time; the examination was usually made by the first officer and the boatswain, and the custom was to lay the rope along the deck so that it could be thoroughly examined; he had had this rope in his own hands, and had looked it over fathom by fathom; no one made any complaint about it, and he himself had found it in good condition; such rope is subject to government inspection in England, and cannot be used unless it is certified by official inspectors.

The boatswain and first officer had left the ship in the preceding January, and the whereabouts of the boatswain was not discovered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Habicht Braun & Co. v. Kaisha
54 F.2d 265 (Second Circuit, 1931)
Ignetti v. Joseph Intall & Co.
290 F. 953 (Second Circuit, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
220 F. 241, 136 C.C.A. 503, 1915 U.S. App. LEXIS 2453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horsley-v-modzelewski-ca3-1915.