Horizon Pools & Landscapes, Inc. v. Nelson Sucarichi

Court of Appeals of Texas·Decided December 8, 2016·No. 01-15-01079-CV·Published

Opinion

Opinion issued December 8, 2016

In The

Court of Appeals

For The

First District of Texas

fees to the homeowner. Horizon Pools & Landscapes, Inc. appeals from the trial court’s judgment for breach of contract. Finding no error, we affirm.

BACKGROUND

Nelson Sucarichi sued Horizon for breach of contract and violation of the Deceptive Trade Practices Act, alleging that he had contracted for the construction of a pool with two pool lights, but Horizon installed just one. Because of this error, Sucarichi withheld the final payment owed on the contract. Sucarichi also sought to remove Horizon’s construction lien against the property, which clouded the title to his home. The lien related to the remaining amount owed under the contract for the construction of the pool.

Horizon answered and counterclaimed for the amount of the contract price that Sucarichi had not paid.

The trial court granted a partial summary judgment in Sucarichi’s favor, declaring that Horizon’s lien was invalid and void. By agreement, the parties then tried the remaining claims to the bench. Sucarichi testified on his behalf and called Curt Olmstead, Horizon’s President, as a witness. The defense called one additional witness, a Horizon employee, Lauren Olmstead.

Sucarichi identified the parties’ contract, which the trial court admitted into evidence. Sucarichi testified that the contract called for the installation of three lights, two in the pool and one in the spa, but that Horizon installed only one of the

required pool lights. The contract distinguished between the pool and the spa, and Sucarichi testified that the lighting terms applicable to each were separate and distinct from one another. Sucarichi further testified that the handwritten terms of the contract were completed by Horizon’s salesman, who had persuaded Sucarichi to have two lights installed in the pool due to its length. According to Sucarichi, the salesman told him that one light would not be sufficient to light the pool. Sucarichi testified that the bottom of the pool is not visible at night without the second light and that the lighting deficiency is exacerbated because Horizon placed the lone pool light in the shallow end rather than the deep end of the pool, which is six feet deep.

Based on three bids that he obtained, Sucarichi said it would cost either $7,823.30 or $7,923.60 for another company to install the missing pool light. An estimate for the latter amount was admitted into evidence without objection. Sucarichi testified that he had withheld $3,700 of the contract price because Horizon refused to install the second light.

Curt Olmsted testified that the handwriting in the contract belonged to a salesman who was no longer with the company. He agreed that the contract provided for two pool lights. He also agreed that the contract provided for one light in the spa. But he disagreed that the contract therefore called for the installation of three separate lights. He contended that the contract only required two lights total, one in the pool and one in the spa. He explained that the provision relating to the spa light

merely stated a wattage, which he contended did not denote a separate light fixture. Olmstead further explained that a pool light in a pool that is only six feet deep is inconsequential and that the bottom would be visible without one. Olmstead conceded, however, that he did not personally communicate with Sucarichi regarding the terms of the contract. He acknowledged that he was not present for the conversation between Sucarichi and the salesman. Olmstead also testified that his daughter, Lauren Olmstead, who runs the company’s office, was not present when the company’s salesman discussed the contract with Sucarichi. He stated that Sucarichi owed Horizon $3,960.40 for the completed pool.

Lauren Olmstead confirmed that the contract is printed by the company and that the handwritten portions are then completed by a company representative. Like her father, Lauren Olmstead testified that the contract required two lights total. However, she agreed that she was not present when Sucarichi signed the contract.

During closing arguments, Sucarichi’s counsel emphasized a construction diagram of the combined pool and spa. He urged that the diagram showed separate and distinct structures that should be regarded independently of one another, including with respect to their lighting. This diagram was part of Horizon’s file, which had been admitted into evidence by the defense at the beginning of trial. However, no witness testified about this diagram, and counsel for both Sucarichi and Horizon agreed that it was not part of the contract. Sucarichi’s counsel also

represented that, if recalled to the stand, his client would testify that he had never seen it before trial. No evidence admitted at trial suggested otherwise.

The trial court rendered judgment in Sucarichi’s favor from the bench. It subsequently entered a final judgment memorializing its rulings, including a take- nothing judgment in Sucarichi’s favor on Horizon’s counterclaim, and judgment for Sucarichi for $3,963.20 plus attorney’s fees.

Horizon requested findings of fact and conclusions of law. Among other things, the trial court found that:

● other than Sucarichi’s signature, the handwritten portions of the contract were filled in by Horizon’s salesman;

● Horizon’s salesman told Sucarichi that two lights were necessary due to the length of the pool;

● one light was installed in the pool and another one was installed in the spa;

● the diagram of the pool in Horizon’s file showed that the pool and spa were “separate components” of the construction.

The trial court concluded that Horizon breached the contract by failing to install two lights in the pool. In sum, the trial court implicitly concluded that the contract was ambiguous and looked to extraneous proof of the parties’ intent—the salesman’s discussion with Sucarichi and the construction diagram—and found that the parties intended to install two lights in the pool and a third in the spa. It calculated

Sucarichi’s damages by subtracting the amount he withheld from Horizon from the amount it would cost him to install a second light in the pool.1 DISCUSSION

Horizon contends that the contract unambiguously required it to install one light in the pool and a second one in the spa; thus, it further contends, it did not breach the contract as a matter of law. Even if the contract is ambiguous, Horizon contends that the proof is legally insufficient to support the trial court’s implicit finding that the parties agreed that the combined pool and spa would have three lights. Horizon does not challenge the judgment on any other grounds.

I. The contract is ambiguous as to whether it required Horizon to install a total of two or three underwater lights in the combined pool and spa.

A. Standard of review and applicable law Whether a contract is ambiguous is a question of law, which we review de novo. Charles R. Tips Family Tr. v. PB Commercial, 459 S.W.3d 147, 153 (Tex. App.—Houston [1st Dist.] 2015, no pet.). When we review an issue de novo, we accord no deference to the trial court’s decision. Cooke v. Morrison, 404 S.W.3d 100, 111 (Tex. App.—Houston [1st Dist.] 2013, no pet.).

1 The trial court’s findings of fact and conclusions of law erroneously state that the court subtracted $3,700 from $7,823.30 to arrive at Sucarichi’s damages of $3,963.20. Instead, the court subtracted $3,960.40—the amount that the Olmsteads testified Sucarichi still owed—from $7,923.60—the amount stated on the face of Sucarichi’s estimate for installation of a second light.

Free access — add to your briefcase to read the full text and ask questions with AI

Horizon Pools & Landscapes, Inc. v. Nelson Sucarichi, (Tex. Ct. App. 2016).

Horizon Pools & Landscapes, Inc. v. Nelson Sucarichi (Horizon Pools & Landscapes, Inc. v. Nelson Sucarichi) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
North Central Oil Corp. v. Louisiana Land & Exploration Co.
22 S.W.3d 572 (Court of Appeals of Texas, 2000)
Mescalero Energy, Inc. v. Underwriters Indemnity General Agency, Inc.
56 S.W.3d 313 (Court of Appeals of Texas, 2001)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Plotkin v. Joekel
304 S.W.3d 455 (Court of Appeals of Texas, 2009)
Entzminger v. Provident Life & Accident Insurance Co.
652 S.W.2d 533 (Court of Appeals of Texas, 1983)
Guzman v. Acuna
653 S.W.2d 315 (Court of Appeals of Texas, 1983)
Heritage Housing Development, Inc. v. Carr
199 S.W.3d 560 (Court of Appeals of Texas, 2006)
MJR Corp. v. B & B VENDING CO.
760 S.W.2d 4 (Court of Appeals of Texas, 1988)
Sage Street Associates v. Northdale Construction Co.
863 S.W.2d 438 (Texas Supreme Court, 1993)
GTE Mobilnet of South Texas Ltd. Partnership v. Telecell Cellular, Inc.
955 S.W.2d 286 (Court of Appeals of Texas, 1997)
Darrell Lee Hodges Junior v. Safeco Lloyds Insurance Company
438 S.W.3d 698 (Court of Appeals of Texas, 2014)
Stephen Patrick McAleer v. Karen Christopher McAleer
394 S.W.3d 613 (Court of Appeals of Texas, 2012)
Hung Tan Phan v. an Dinh Le, Tan Minh Cao, and Huy Dinh Truong
426 S.W.3d 786 (Court of Appeals of Texas, 2012)
Elizabeth M. Trammell v. Fletcher v. Trammell, Sr.
485 S.W.3d 571 (Court of Appeals of Texas, 2016)
Mark Thompson, Sr. v. Karen Smith
483 S.W.3d 87 (Court of Appeals of Texas, 2015)