Horgan v. McKenzie

17 N.Y.S. 174, 43 N.Y. St. Rep. 131, 1892 N.Y. Misc. LEXIS 249
New York Court of Common Pleas·Decided January 15, 1892·Published·Cited by 1 cases

Opinion

Bookstaver, J.

This action was brought to foreclose a mechanic’s lien against the premises 765 Broadway for labor and material under a contract for the repair of those premises. The action was tried by a referee, and resulted in a decree of foreclosure. The appeal raises questions of fact, chiefly. The answer admitted the contract, but put in issue its performance, and the claim for extra work, except to the amount of $32, and set up four counterclaims. The first alleged that improper materials had been used, and the-work had not been done according to the contract. The second alleged a failure to perform the work by the time limited in the contract, and claimed that by reason thereof defendant had been compelled to let the premises at a reduced price. The third claimed that plaintiffs had not done all the work and had not furnished all the materials required by the contract, and that she had been compelled to do such work and furnish such materials, to her damage; and the last alleged that the plaintiffs had failed to put in an engine of the capacity required by the contract, and in consequence she had been compelled to remove the one put in, and replace it with another of greater capacity. The referee allowed items under the first and third counter-claims amounting to $254.13, but appellant contends that she should have been allowed the sum of $75 which she paid for gates to the elevator.

The contract- is silent as to whether there were to be gates to the car or not. It merely called for a combination passenger and freight car. If appellant had desired gates to it, she should have provided for it in her specifications. There is no proof in the case that, when they are not specified, the understanding in the trade is that they should be supplied, nor is there proof that such a car is incomplete without gates. It is true that one witness (the mechanic who afterwards put on the gates) testifies that in his opinion gates are proper and necessary on a combination car; but he says nothing as to what constitutes such a car, as understood in the trade.

It was also urged on the appeal that the ceiling in the store was not according to contract, in that the material was not of first quality. Two witnesses on behalf of the defendant testified that the material was of second or third quality, being knotty, and having pitch in it, as well as being the sappy part of the wood; but neither of these witnesses saw the ceiling until after it had two coats of paint on it, while the plaintiff Horgan and one Hirsch, the merchant who sold him the lumber, both testify that the material was of the best quality. There being such contradiction of testimony, we do not think the referee erred in finding as he did on this question.

Defendant also claims that she should have been allowed for loss in rent because the repairs were not completed by the time limited in the contract. But we do not think the referee would have been justified in finding that she [176] had lost rent for that reason. He has found that the work was completed about the 15th of April; the testimony is conflicting as to when it was finished, but we do not think that a very material question in this case. Our attention has not been called to any testimony tending to show that the defendant complained of delay while the work was going on, or, indeed, until this action was commenced, while it does not appear from the testimony of Harrell, the real-estate agent, that the property was placed in his hands to be let early in February, 1890, which was before the contract for repairs was made; that he rented all the lofts to a Mr. White early in March; and that the latter moved in about April 1, 1890. It is therefore clear that the fact that the repairs were not completed by the time fixed in the contract could have had no effect on the rental price of the lofts. According to Harrell the asking price for these lofts was $4,500; and the defendant, after negotiation, agreed to let them for $3,500. Harrell further testified that he had negotiated with several people for the store and basement; that these negotiations' commenced as early as February, 1890; that in that month he had an offer for the premises, but that it was not as much as he afterwards obtained from Yee Long & Co., the present occupants; that he finally let the store premises to them for $4,000 on the 20th of April, 1890. In view of these facts the opinion of this witness and another real-estate broker that they ought to bring from $4,500 to $9,000 amounts to little. It is clear that the defendant obtained more for the premises on the 20th of April than she could have done at any time before.

Under the circumstances of this case, we do not think the referee erred in allowing plaintiff Horgan to testify what the reasonable value of the work actually done was, even although it showed that it was worth more than the contract price. But, if it was error, it did the defendant no harm, as the referee only allowed the contract price for it.

While there is a conflict of evidence as to whether the plaintiffs did the extra work they claimed or not, yet we can see no reason why his conclusions as to this should be disturbed. There is certainly sufficient evidence to support them.

Free access — add to your briefcase to read the full text and ask questions with AI

Horgan v. McKenzie, 17 N.Y.S. 174, 43 N.Y. St. Rep. 131, 1892 N.Y. Misc. LEXIS 249 (N.Y. Super. Ct. 1892).

17 N.Y.S. 174 (Horgan v. McKenzie) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J. J. Newman Lumber Co. v. Wemple
56 Misc. 182 (New York Supreme Court, 1907)