Horgan & Slattery v. City of New York

114 A.D. 555, 100 N.Y.S. 68, 1906 N.Y. App. Div. LEXIS 2139
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 12, 1906
StatusPublished
Cited by15 cases

This text of 114 A.D. 555 (Horgan & Slattery v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Horgan & Slattery v. City of New York, 114 A.D. 555, 100 N.Y.S. 68, 1906 N.Y. App. Div. LEXIS 2139 (N.Y. Ct. App. 1906).

Opinions

Houghton, J.:

The plaintiff is a corporation engaged in the business of making plans and specifications and superintending the. erection of buildings as architect. Prior to the 25th day of October, 1900, a site had been duly selected for the erection of the Sixty-ninth Regiment Armory, between Twenty-fifth and Twenty-sixth streets, on Lexington avenue in the city of New York. The armory board of that city7, consisting at that time of the mayor, two senior ranking officers of or below the grade of brigadier-general, in command of troops of the National Guard quartered in the city of New York, the president of the department of taxes and assessments, and the commissioner of public buildings, lighting and supplies (Military Code [Laws of 1898, chap.' 212], § 134), by resolution directed the plaintiff to prepare plans and specifications for such armory building so proposed to be erected, with estimated cost thereof. Under this employment preliminary plans and estimates were furnished and approved by resolution of that board, on the 23d day of January, 1901, and an appropriation. of $500,000 was asked therefor from the commissioners of the sinking fund of the city óf.New York, whose final approval and action was necessary for the raising of funds therefor. On the eighth of March following, the commissioners of the sinking fund, by7 resolution, authorized the armory [557]*557commissioners or board “ to take such steps as may be necessary to enter into a contract'for the erection of an armory for the Sixty-ninth Regiment N. GL N. Y. * • * * And "" * "" for the purpose of providing means for the payment therefor, including architect’s fees and all incidental expenses connected therewith,” the sum of §450,000 was appropriated. Thereafter and on the third day of April following, the armory board, by resolution forwarded to the plaintiff, directed it to prepare “ detailed plans and specifications in accordance with the plan which has been adopted by the armory board and o/pproi)ed by the Commissioners of the Sinking Fund for an armory building for the Sixty-ninth Regiment,” and directed that they be submitted for approval to a. committee of that board appointed therefor. The approval by the commissioners of the sinking fund referred to in this resolution was the approval by the resolution of March eighth fixing the cost at and making an appropriation of §450,000.

' The testimony discloses that from the third of April to about the middle of June following a large part of the force of plaintiff’s office was engaged in making such plans, and during the summer and fall following the principal part of the specifications were completed. After these plans and specifications had been so completed and approved on the 19th of November, 1901, by resolution, the armory board directed the entering into with plaintiff of a written contract for the preparation of such plans and specifications and the supervision of the construction of such armory building. This was done, and by such contract it was provided that the plaintiff should receive five per cent upon the cost of the erection of the building—such commission being subdivided, one per cent for preliminary studies and sketches, two and one-half per cent for completed plans and general working drawings and specifications and detail, and the balance for further working plans and supervision of erection — this subdivision being in case of the abandonment or suspension of the work. By this contract it was provided that the plans and specifications, for the purpose of. enabling accurate and reliable bids or estimates, should be completed on or before the 15th day of October, 1901, a date prior to that of the contract itself. The total cost of the building, including architect’s fees, it was provided, should “be kept well within the sum of” $450,000, [558]*558On these plans, specifications and details bids were asked. None were received within the $450,000, all being in excess thereof and ■ ranging from $666,394, the lowest, to $744,394, the-highest, exclusive of architect’s fees. By resolution on the 14th day of J anuary, 1902, all of these bids were- rejected because in excess of the appropriation. Subsequently and on the twenty-second day of July following, by resolution, the armory, board rejected the plans of the plaintiff, terminated its employment as architect, and recommended that $100,000 be added to the appropriation and invited competitive plans from certain architects therefor, and the building was subsequently erected at an increased cost, under the plans of other architects. The written contract with plaintiff provided that if the plans and specifications were not satisfactory, the plaintiff would revise and correct the same to conform to suggested requirements; and the plaintiff proved that it had never been requested to revise the plans submitted, so that the building would cost a less amount to erect. This written contract contained the appropriate certificate of' the commissioners and comptroller as to appropriation and unexpended balance applicable to pay the moneys provided thereby, but no other contract of employment of plaintiff complied with this requirement. .

The plaintiff seeks to compel the city to pay for the plans and specifications so furnished, as well as damages for breach of the contract. The first cause of action alleged is for the two and one-half per cent on the proposed cost of the building for the plans and specifications, and the second cause of action is for damages for breach of the contract by wrongful discharge.

The complaint states that the original hiring was October 25, 1900, but on the tidal the plaintiff was allowed to amend by adding appropriate allegations as to the making of the written contract ’of November 19, 1901.

The plaintiff recovered two and one-hálf per cent upon $450,000 for the plans and specifications furnished, amounting," with interest added, to $11,835.10, as well as $5,000 damages for wrongful discharge and refusal to.permit it to complete its contract to superintend the erection of the building and do the work necessary to earn the balance of the five per cent stipulated.

The" defendant appeals from this judgment, asserting that the [559]*559armory board had no power to make the contract of October 25, 1900, and that plaintiff can recover for no work performed prior to the written contract of November 19, 1901, even after the resolutions of March eighth and April third; and further asserts that assuming the written contract executed in November was valid, or that the verbal contract arising out of the resolution of April third was good, plaintiff failed to perform either of them by furnishing plans and specifications according td which the building could be erected within the stipulated sum of $450,000.

We think it must be held, under the doctrine of this court enunciated in Lewis v. City of New York (106 App. Div. 454) and Keane v. City of New York (88 id. 542) and Walton v. Mayor (26 id. 76), that the armory board had no power to incur an indebtedness for architect’s fees, which the city became liable to pay, until it had- been authorized to incur such indebtedness by resolution of the commissioners of the sinking fund. The resolution of those commissioners, passed March 8, 1901, did give the armory board authority to employ plaintiff, which authority they exercised by their resolution of April third following, directing plaintiff to prepare detailed plans and specifications for the erection of the proposed armory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hurd v. Erie County
34 A.D.2d 289 (Appellate Division of the Supreme Court of New York, 1970)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1959
Rowland v. County of Hudson
80 A.2d 433 (Supreme Court of New Jersey, 1951)
Civil Service Technical Guild v. LaGuardia
181 Misc. 492 (New York Supreme Court, 1943)
Johnson-Olmsted Realty Co. v. City & County of Denver
1 P.2d 928 (Supreme Court of Colorado, 1931)
Andry & Feitel v. Ewing
130 So. 570 (Louisiana Court of Appeal, 1930)
Pierce v. Board of Education
125 Misc. 589 (New York Supreme Court, 1925)
Lord v. City of New York
171 A.D. 140 (Appellate Division of the Supreme Court of New York, 1916)
City of Colorado Springs v. Coray
25 Colo. App. 460 (Colorado Court of Appeals, 1914)
Schieffelin v. City of New York
65 Misc. 609 (New York Supreme Court, 1910)
Bernstein v. City of New York
134 A.D. 223 (Appellate Division of the Supreme Court of New York, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
114 A.D. 555, 100 N.Y.S. 68, 1906 N.Y. App. Div. LEXIS 2139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horgan-slattery-v-city-of-new-york-nyappdiv-1906.