Hopkins v. State

131 Misc. 11, 225 N.Y.S. 665, 1925 N.Y. Misc. LEXIS 1222
CourtNew York Court of Claims
DecidedJanuary 23, 1925
DocketClaim No. 16296
StatusPublished

This text of 131 Misc. 11 (Hopkins v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hopkins v. State, 131 Misc. 11, 225 N.Y.S. 665, 1925 N.Y. Misc. LEXIS 1222 (N.Y. Super. Ct. 1925).

Opinion

Parsons, J.

In or about July, 1916, the claimant entered into a contract with the State- of New York for the construction of about ten and one-half miles of road in Clinton county, State of New York, known as the Moffitsville and Franklin County Line Highway No. 1398. Shortly after the execution of the contract the contractor began the construction of the highway, which was to be what is known as a bituminous macadam, penetration method road. The contract was completed and accepted.

The plans or the blueprints furnished the contractor provided that between stations 950 and 960, a distance of from one-half to one-third of a mile, the road should cross a swamp. The specifications provided a twelve-inch subbase across this swamp. This swamp was a somewhat unknown quantity so far as its depth to solid earth was concerned.

In or about October, 1917, the engineer in charge changed the fine of the road for the above-mentioned distance and carried it around the swamp on the old, hard, solid road. This required only a six-inch subbase instead of a twelve-inch, across the swamp.

The claimant in his principal items claims for loss of anticipated profits on this six-inch base eliminated by reason of the swamp, by reason of the fact that his bid was so much per yard for subbase in place.

The contract at page 110, section 4, contained the following clause: The work shall be performed in accordance with the true intent and meaning of the plans and specifications therefor, which are referred to and made a part of the consideration named in this contract. The State, however, reserves the right to make such additions, deductions or changes as it deems necessary, making an allowance or deduction therefor at the price named in the proposal for the work. And this contract shall in no way be invalidated thereby, and no claim shall be made by the contractor for any loss of anticipated profits because of such change, or by reason of any variation between the approximate quantities and the quantities of the work as done.”

It would seem, therefore, that in maki. __ this change the State [13]*13was entirely within its rights. If it was not so, the contractor should have abandoned the contract and stood on his legal rights. He having, however, continued to complete the contract, cannot now claim for extra compensation. That the change was a proper one in the light of good engineering is evidenced by the testimony of the claimant himself, who is a graduate engineer. There seems to be no proof that in ordering the change the engineer in charge acted in a capricious, arbitrary or unnecessary manner.

We; therefore, conclude that the contractor cannot recover on this item.

Another item in the claim is for extra top stone alleged to have been more than was customary. It was attempted to prove a custom as to such quantities. This might be all right if there were no contract. But the contract provides that this filling shall be done, as all other work, to the satisfaction of the engineer in charge. If the engineer in charge required too much, then the contractor had his option to continue or quit, and he cannot now complain unless he proved that the engineer in charge acted in a capricious, arbitrary or unnecessary manner.

The other item was for extra excavation. It appears from the evidence that during the construction some heavy rains fell and washed the sides of the banks into the road and ditches, and that the claimant was required to excavate this extra sand and gravel. It is not claimed that this was caused by faulty specifications or fraud on the part of the State. This was an actual hazard of the contract, and the State cannot be held liable therefor.

We are, therefore, of the opinion that the claimant cannot recover against the State, and that the claim should be dismissed as to all items.

Let judgment be entered accordingly.

Smith, J., concurs.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
131 Misc. 11, 225 N.Y.S. 665, 1925 N.Y. Misc. LEXIS 1222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hopkins-v-state-nyclaimsct-1925.